Utility February 2022

Page 90

SWIT CHGE AR

ENERGYCONNECT: MEETING THE CHALLENGES OF A REMOTE ENVIRONMENT

Project EnergyConnect, once approved and constructed, will directly link the energy networks of South Australia and New South Wales for the first time.

T

he largest electricity interconnector project to date in Australia, EnergyConnect is a cornerstone of the Australian Energy Market Operator’s (AEMO) 2020 Integrated System Plan (ISP). The ISP is a roadmap to ensure Australia has a resilient and secure grid to accommodate future renewable energy, and promote a decarbonised future. The project has passed a cost-benefit analysis, overseen by the Australian Energy Regulator (AER) and is progressing through the final phase of a rigorous approval process. The challenges of delivering EnergyConnect are being assessed, including the transmission route, the construction of transmission lines and substation requirements. EnergyConnect will enable the renewable wind and solar energy generated in South Australia to flow into the New South Wales grid, helping stabilise prices in the National Energy Market (NEM).

ENERGYCONNECT TIMELINE Phase

Status

Timing

Preliminary investigations and project scoping

Completed

Regulatory Approval received in July 2021

Community and landowner consultation

In progress

From 2018

Project approvals

In progress

From early 2020 – mid 2022

Detailed Design and Site Early Works

In progress

Early 2021 – mid 2022

Construction

Proposed

From 2022 (NSW Western section)

Project commissioning

Proposed

By 2024

THE CHALLENGES OF DISTANCE Transgrid will build the New South Wales section of EnergyConnect, ElectraNet will deliver the South Australian component and Secure Energy has been appointed as the primary contractor.

88

UTILITY • FEBRUARY 2022

Transgrid will construct a 674km transmission line from the South Australian – New South Wales border to Wagga Wagga, linking two existing substations and one new substation. This isolation, combined with the project’s required 50-year life span, requires that infrastructure choices assure iron-clad network reliability and security. Yousseph Ters, Transgrid Project Integration Manager, said, “The stability of the network is vital, with outages requiring quick remediation, which will be a challenge given the remoteness of the transmission and substation infrastructure.”

INNOVATION VS TRIED AND TESTED TECHNOLOGY Transgrid’s delivery of EnergyConnect includes an estimated 1,900 new transmission towers, linking the three substations to South Australia. “We need to demonstrate the value that EnergyConnect will provide, balancing the concerns of landholders and affected communities with environmental, heritage and economic constraints,” Mr Ters said. “Our Network Planning team works closely with team EnergyConnect to choose technical solutions that blend innovative transmission tower technology, with tried and tested substation installations familiar to transmission infrastructure across Australia.” TRANSMISSION TOWERS TO SUIT THE TERRAIN EnergyConnect is using innovative guyed tower technology, consisting of a single mast with guyed wires that spread out diagonally, providing the support required for the tower. Guyed towers are used extensively in the US, South America, Africa and Europe in locations where the topography is flat. Australia’s grid is often in hilly and rocky areas, so this will be the first use of double circuit guyed towers in

WWW.UTILITYMAGAZINE.COM.AU


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Utility February 2022 by Monkey Media - Issuu