Company Brochure

Page 1

Lipton Soft Drinks Ireland Ltd. Client: Engineer:

Lipton Soft Drinks Ireland Ltd RPS Consulting Engineers, Ballincollig, Cork Value: â‚Ź980,000 Timeframe: 9 months Completed: 2010 Project Description: Construction of an extension to a pharmaceutical facility, including construction of new office block & internal refurbishment of existing continuously live production facility within a 'clean' environment, where we had to adhere to strict environmental control procedures to ensure no cross contamination of the product occurred. Also as this facility provided a specific product required by all the other plants in Europe no down time apart from planned shutdowns was allowed.


Lipton Soft Drinks Ireland Ltd.


Intel Ireland Client: M+W Group 1A Sussex Terrace, Dublin4 (working on of Intel Ireland) Engineer: M+W Group

behalf

Value: â‚Ź3.3million Timeframe: 20weeks Completed: 2012 Project Description: Site Enabling Works for 3 extensions to the existing buildings & associated site works in a live manufacturing facility. Safety Milestone achieved on Site at 35,835 accident free hours.


Carrigaline Library, Carrigaline, Co. Cork. Client: Cork County Council Engineer: Cork County Council Value: â‚Ź226,117 Timeframe: 3 months Completed: 2010 Project Description: Refurbishment and fit out works to Carrigaline Library . This Project was delivered on budget & time. Works were carried out in a Town centre based works involving strict safety management.


Mitchelstown Library, Mitchelstown, Co. Cork. Client: Cork County Council Engineer: Cork County Council Value: â‚Ź194,891 Timeframe: 3 months Completed: 2010 Project Description: Conversion of existing Commercial/Retail units into new Library at Sutton Court. This Project was delivered on budget & time. Works were carried out in a Town centre based works involving strict safety management.


Ozolaid House, Camden Quay, Cork. Client: Murray Properties Ltd. Quantity Surveyor: James Sheehan & Associates Value: €380,000 Timeframe: 4 months Completed: 2009 Project Description: Refurbishment & Alterations to ‘Ozolaid House’,1 Camden Quay, Cork.(Listed Building). The building consists of five storeys including one retail unit and 18 residential units. This project consists of the strip out of the existing mechanical and electrical of the existing listed building. Refurbishment of original Sash windows. The removal of existing internal doors, floors walls and ceiling finishes and the installation of new, to achieve a fire rating for the fire cert Compliance. City Centre location required very tightly managed safety and construction procedures


Bowens Menswear, Bandon. Co. Cork Client: Bandon Menswear Quantity Surveyors: Unique Fit out Value: â‚Ź315,000 Timeframe: 7 months Completed: 2010 Project Description: Refurbishment, Strip Out & Complete fit out of Bowens Menswear including some roof/structural works on Main St. Bandon. Town Centre location required very tightly managed safety and construction procedures. Traffic Management plans fully operational during night time works and for deliveries


Kerry Foods, Wallingstown, Little Island, Cork Client: Engineer: Architect: Value: Timeframe: Completed:

Kerry Food Group Thomas O Brien Wilson Architecture â‚Ź2.5million 16week (turnkey project) 2008

Project Description: Design & Build of complete Turnkey Package 25,000sqft Light Industrial Units with Substantial Civil Elements. Phase 1 consisting of a steel structure with in-situ concrete slab floors of high tolerance. Office space (fit out) accounted for 7000sqft of the total space.


An Post DSU, Ballincollig, Cork Client: An Post Architects: Jack Coughlan & Associates Value: â‚Ź120,000 Timeframe: 2 months

Completed: 2011

Project Description: Refurbishment, fit out works and construction of extension to the existing sorting post office in Ballincollig. Ancillary site works include fit out of office space & creation of new opens and associated works.


Woodlands Depot, Killarney, Co. Kerry. Client: Killarney Town Council (Kerry) Engineer: Malone O’Regan McGillicuddy Value: €2.4million Timeframe: 11 months Completed: 2009 Project Description: GFA 960m2 –Construction of energy efficient offices and fit out of same(Mechanical 7% & Electrical 9%) & loading areas on a Greenfield site for Killarney Town Council. Works also included a 450m NRA spec link road with extensive Traffic Management works.


High Street, Killarney, Co. Kerry Client: High Street Development s(Niall Fleming) Architect: O Sullivan Campbell & Associates Engineer: Malone O'Regan McGillicuddy, 4 Day Place, Tralee,Co Kerry M&E Specialist: Martin Buckley & Associates, Tramway House, Albert Road, Cork Value: â‚Ź3.5million Timeframe: 12 months Completed: 2008-Fit Outs are ongoing Project Description: A Design Build Fixed Price Project- Construction of a 4 Storey Steel Commercial & Residential Units & Fit Out- Apartment / Duplex Apartments with extensive Mechanical(8%) & Electrical(20%) Works. These works were completed on a part brownfield town centre site(located in the heart of Killarney). Careful sequencing of works was vital due to access only from the site as adjacent properties on 3sides. The fit out of the different floors has been carried out over the last number of years as required by different longterm clients. Facilities include: Canteen/tea rooms/large scale board room/studios. Open plan and closed plan workspace/office space. A large storage back house facility was developed for the ground floor 'Daybreak Shop'. Installation of a lift serving all floors.


High Street, Killarney, Co. Kerry


High Street, Killarney, Co. Kerry


Television Mobiles Ltd. (TVM) Client: Television Mobiles Ltd. Bartlemy, Co. Cork Engineer: Malachy Walsh & Partners Value: â‚Ź1,951,847 Timeframe: 17 months Completed: 2012 Project Description: Demolition of existing derelict cottage and construction of new centralised office building with attached truck workshop. The office building comprises of offices- constructed to a passive standard, meeting rooms, production rooms, editing suites(strict dust regulatory guidelines to abide by), storage rooms, roof garden, Canteen, Kitchen, large reception area, truck workshop comprising of 3no. bays and large scale plant room (editing/production purposes) and associated works.


Television Mobiles Ltd. (TVM)


The Framemaker Artist Studios Client: The Framemaker Architect: Wilson Architecture Value: â‚Ź765,000 Timeframe: 5 months Completed: 2006 Project Description: Construction of a retail warehouse facility which included the provision of artist studios and office areas. Works included the fitting out of the unit, artist studios and office areas.


Killarney Areas Services Centre Client: Kerry County Council Engineer: Kerry County Council Value: â‚Ź148,000 Timeframe: 2 months Completed: 2010 Project Description: Construction of internal office development for a primarily open plan office for local authority functions in an existing new building shell of approximately 241m2. Installation of self contained aero-thermal heating system c/w heat recovery ventilation for above office development. Installation of electrical power, security system, fire alarm system, CCTV system as well as providing conduits for IT and communications requirements by others.


Bandon Town Council Offices. Client: Bandon Town Council Engineer: Cork County Council Value: â‚Ź50,000 Timeframe: 1 month Completed: 2011 Project Description: Refurbishment and fit out to Bandon Town Council offices. Works comprised of removal of existing office fitting and re-establishment of office space with new furniture. Work was carried out also to remove and replace a subsiding floor and all associated refurbishment works.


Goleen Coast Guard Station, Cork Client: The Office of Public Works (OPW) Engineer: The Office of Public Works (OPW) Value: â‚Ź644,757 Timeframe: 11 month Completed: 2011 Project Description: Goleen Coast Guard Station Demolition of existing Rocket Cart Shed; the realignment of existing slip road adjacent to the shed; construction of new slip road; construction of two storey Coast Guard Station of 326 sq metres; and associated landscaping and other ancillary works


Goleen Coast Guard Station


Cascade Carrigtowhill, Cork Client: Castlelake Partnership Engineer: Denis O Sullivan & Associates (DOSA) Architects: PRC Architects, Morrisons Island, Cork City M&E Specialist:Martin Buckley & Associates, Tramway House, Albert Road, Cork Value: â‚Ź14million Timeframe: 11 month Completed: 2008 Project Description: Cascade is Design Build(fixed price) project constructed on a greenfield development & fit out of 95 Luxury Apartments in Carrigtwohill, Co. Cork. Phase 1. This development was 10,000sqm in size and 4-6 floors high. It is located just on the outskirts of Carrigtwohill town in close proximity to existing residential and commercial units. Works included extensive piling and the construction of footbridge over a lake on the site.


33 Oliver Plunkett St. Cork Client: Murray Properties Ltd Thompson House, 55 McCurtain St. Cork Engineer: Dan Mulvihill & Associates. Value: â‚Ź244,461 Timeframe: 11 month 2011

Completed:

Project Description: Structural Stabilization Works and complete refurbishment/renovation works to No. 33 Oliver Plunkett Street located in Cork City. This 4storey building required careful monitoring and sequencing of works to ensure minimal disruption to the residents, businesses and pedestrians of the city centre location.


Swimming Pools-Bishopstown, Churchfield, Douglas, Cork City Client: Engineer:

Cork City Council JODA Engineers, Model Farm Road, Cork

Value: â‚Ź742,290 Timeframe: 1 month

Completed: 2011

Project Description: Douglas Swimming Pool, Bishopstown Leisureworld & Churchfield Leisureworld.-Live Operational Public Environment Energy upgrade and disability works including associated site works. Electrical works(35%) & Mechanical works(31%).


OS Sheet Metals, Tramore Road, Cork City Client: OS Sheet Metals Engineer: Watermans Consulting Engineers Value: â‚Ź1.6million Timeframe: 11months

Completed: 2008

Project Description: Refurbishment, alterations and fit out to Industrial Unit. Including extensive site works. Works included a large scale Electrical element including the provision of a new substation to supply fabrication machinery.


Nyhan Motors, Midleton, Co. Cork Client: Architect:

Nyhan Motors Joe O’ Sullivan Architectural Design & Planning, Unit 8, Airways Technology Park, Farmer’s Cross, Cork Engineer: Gearoid Hayes & Associates, 13 Oliver Plunkett. St. Bandon. Co. Cork M&E Specialist:Martin Buckley & Associates, Tramway House, Albert Road, Cork Value: €2million Timeframe: 2month Completed: 2008 Project Description: A Design Build Fixed Price Contract-Construction of a Car Showrooms with Offices and extensive parking facilities for both stock cars and customer cars. A mechanics full fitted garage and all associated site works including extensive tarmac works and landscaping to car show areas.


Cobh Community Centre, Cobh, Co. Cork Client: Engineer:

Cobh Community Centre O'Brien Thomas J Consulting Engineers Ltd, Discovery House U22Airport East Business pk,Farmers Cross, Cork Architect: Stephen Kowalski Architects. M&E Specialist:Martin Buckley & Associates, Tramway House, Albert Road, Cork Value: â‚Ź2.3 million Timeframe: 9 month Completed: 2008 Project Description: A Design Build Fixed Price Contract- Construction of a Community Centre in Cobh Co. Cork for Cobh Parish to include area assigned to COPE, theatre and 3 floors of workshops, kitchen/servery and entrance lobby & Fit out of same. Extensive piling to ground works, tarmac car park facilities, playing court areas & perimeter boundaries


St. Patricks GRD School, Whitechurch, Co. Cork Client: Architect: Value: Timeframe: Completed:

St. Patrick's NS Whitechurch / Department of Education KOBW Architects, Heron House, Blackpool Park, Blackpool, Co. Cork .. â‚Ź2.3 million 11 month 2012

Project Description: Phased demolition of existing school building, provision of 1 no. temporary classroom and the construction of a new 16 classroom Generic Repeat Design school of 2,268m2 including construction of a fully equipped PE Hall, activity areas including Ball courts etc. with associated site works.


Cork University Hospital – All Works Client: Architect: Value: Timeframe: Completed:

Health Service Executive –Cork University Hospital Health Service Executive €676,996 2011-2012 (over the space of the 2years) ongoing

Project Description: -Ultrasound room -Concourse Room -Pergola -Ward 2C,3A,5B -Fire Door Compartmentation

-GI Clinic -Medical Records -X-Ray room -CAT Lab -Water Filtration

-Fire Door Refurbishment -Acroyvn Wall -Phlebotomy Unit


Cork University Hospital – All Works


Cork University Hospital – All Works


Prosys Industrial Unit, Carrigtwohill, Co. Cork Client: Engineer: Value: Timeframe: Completed:

Prosys Sampling Systems Ltd. David Kelly Partnership, Nelson House, Emmet Place, Youghal, Co. Cork â‚Ź930,000 11months 2011

Project Description: Construction of a New Light Industrial Building with ancillary office accommodation and parking facilities including associated site works at IDA Business Park


Youghal Hospital, Youghal, Co. Cork Client: Engineer:

Youghal Hospital -Live Operational Environment HSE South, Estates Department, Block B, St. Finbarrs Hospital, Douglas Road, Cork Value: â‚Ź307,885 Timeframe: 2months Completed: 2012

Project Description: Fire upgrade works, ceilings, partitions, electrical works(15%), mechanical works (20%) including doors and flooring etc. Works included an upgraded access roadway & site services. Works carried out over 6phases in a very tight project programme.


Salt Barn, Ballincollig, Co. Cork Client: Cork County Council Engineer: Cork County Council, ref. National Roads Office, Richmond, Glanmire, Co. Cork Value: â‚Ź235,000 Timeframe: 4months Completed: 2012 Project Description: Construction of a salt storage barn and a machinery storage area in Ballincollig. Works included building works, construction of concrete aprons, installation of services and all associated works


Salt Barn, Skibbereen, Co. Cork Client: Cork County Council Engineer: Cork County Council, ref. National Roads Office, Richmond, Glanmire, Co. Cork Value: â‚Ź230,000 Timeframe: 4months Completed: 2012 Project Description: Construction of a salt storage barn and a machinery storage area in Skibbereen. Works included building works, construction of concrete aprons, installation of services, extensive piling and all associated works


AOC Iron Mountain, Carrigtwohill, Co. Cork Client: AOC Commercials, Carrigtwohill, Co. Cork Engineer: Denis O Sullivan & Associates (DOSA), Barrack Square, Ballincollig, Co. Cork Value: â‚Ź2.6million Timeframe: Phased Development over 3 years Completed: 2008 Project Description: Large industrial Building for Iron Mountain Paper Storage, Carrigtwohill, Co. Cork including the provision of extensive car parking spaces and associated works


Cobh Cross, Carrigtwohill, Co. Cork Client: James Fenton & John Cahill, Killacloyne, Carrigtwohill, Co. Cork Engineer: Tony Dunlea Value: â‚Ź2.8million Timeframe: 9months Completed: 2008 Project Description: Phase one. Six Industrial/ Warehouse Units, associated car parking spaces, machinery storage unit with ancillary two storey offices, including Road works & other Civil Elements


North Monastery Secondary School, Cork Client: North Monastery Secondary School Board of Management Engineer: O Connell Harley O Dwyers Value: â‚Ź616,584 Timeframe: 4months Completed: 2009 Project Description: Complete Upgrading of Electrical Works, Fire upgrading & Associated Building to 32 classrooms & Refurbishment Works including the installation of an underground, waterproofed reinforced concrete structure.

Before

After


Cork Institute of Technology – Shop & Handrails Client: Cork Institute of Technology (CIT) Architect: Neff Design, Liberty Bridge, Kilmurriheen, Spur Hill Cork Engineers: Horgan Lynch Engineers, Blackrock, Cork Value: €74,684 Timeframe: August 09-September 09 & February ‘10 – June ‘10 Completed: 2009 & 2010 Project Description: Refurbishment & Upgrade to Cork Institute of Technology Main Campus Shop. Also the Make up & installation of handrails & balustrades for Cork Institute of Technology Athletic Track


Bandon Co-op Kinsale, Co. Cork Client: Bandon Co-operative Society Ltd. Engineers: Murphy, McCarthy Consulting Engineers. Ltd. Centre Park Road, Cork Value: â‚Ź729,876 Timeframe: 11months Completed: 2011 Project Description: Construction of a new detached store and yard entrance; provision of new wall and roof sheeting to existing building; internal alterations to convert existing building store into a retail shop area. These works were carried out in 3 phases.


Cork Institute of Technology – Block A Works Client: Cork Institute of Technology (CIT) Architect: Neff Design, Liberty Bridge, Kilmurriheen, Spur Hill Cork Value: ₏1,078,250 Timeframe: 11months Completed: 2012 Project Description: Construction of an extension to the rear (North) of A Block of Cork IT. It will comprise of a generally single storey build with part mezzanine and a new first floor over room A183 in the existing A Block including 3 new workshops


Shanakiel Hospital, Cork City Client: Board of Management- Shanakiel Hospital Architect: HBK Architects, Lisburn, Co. Antrim Value: â‚Ź110,000 Timeframe: 3months Completed: 2009 Project Description: Refurbishment and Removal/Demolition of a section of 600mm thick structural wall and the shuttering and pouring of an insitu concrete structural lift shaft to facilitate the Installation of a Lift and all associated site works.


St. Stephens Hospital, Glanmire, Co. Cork Client: Architect: Value: Timeframe: Completed:

Health Service Executive –Cork University Hospital Health Service Executive ₏114,000 2 months 2012

Project Description: Fire Safety Upgrading works to Unit 8, St. Stephens Hospital Glanmire- works carried out in a live hospital environment working within strict Hospital Health & Safety guidelines with an emphasis on Aspergillus Control.


Nurture Creche, Fairylawn, Western Road, Cork Client: Nurture Creche Ltd. Architect: QDM Architecture, Cork Value: €1.6m Timeframe: 6months Completed: 2007 Project Description: Renovation & Refurbishment of existing 3 storey Building(protected façade) in a city environment. Development & Construction of an Assembly Area, Provision of a Lift Shaft, Lift & Access Ramp & associated site works- comprising of Crèche Facility, external specialized play areas & Apartment Duplex & associated site works including extensive piling and hard landscaping.


Fota House, Co. Cork Client: Irish Heritage Trust Q. Surveyors:Bill Feehely & Associates Value: â‚Ź785,000 Timeframe: 6months Completed: 2010 Project Description: Development of Road Network & Extensive Car Parking facilities at Fota House, Cobh, Co. Cork . These works included lighting, road alignment, widening and resurfacing and all works carried out to ensure minimum disruption to the ongoing work/activities of Fota House


Cullen NS, Cullen, Co. Cork

Client: Architect:

Cullen NS –Board of Management Joe O Sullivan Architects


St. Marys NS, Carrigaline, Co. Cork Construction of a single storey, including an Autism Spectrum Disorder unit

Client: NS Architect:

Board of Management- St. Marys Declan O Sullivan Architects


Blue Haven Hotel-Hamlets- Old Fish Market Wall Restoration Complete restoration of original Old Fish Market Wall & internal structure upgrading works (value of works and timeframe includes all three projects Blue Haven Hotel/Oz Haven & Hamlets Bar)

Client:

Fitzgerald & Partners Contract Value: â‚Ź515,000 Quantity Surveyors: James Sheehan & Associates Timeframe: 6months


Blue Haven Hotel-Hamlets- Old Fish Market Wall Restoration

(value of works and timeframe includes all three projects Blue Haven Hotel/Oz Haven & Hamlets Bar)

Client:

Fitzgerald & Partners Contract Value: â‚Ź515,000 Quantity Surveyors: James Sheehan & Associates Timeframe: 6months


Oz Haven-Blue Haven Food Company Complete stripout & fit out of Oz Haven CafĂŠ (value of works and timeframe includes all three projects Blue Haven Hotel/Oz Haven & Hamlets Bar)

Client:

Fitzgerald & Partners Contract Value: â‚Ź515,000 Quantity Surveyors: James Sheehan & Associates Timeframe: 6months


Iron Mountain Development @ Carrigwohill, Co. Cork Development consisting of a Comerical Unit which took place over two phases.

Client: Engineer:

Iron Mountain Denis O’ sullivan

Cobh Cross, Carrgtwohill, Co. Cork Light weight Industrial/ Warehouse Units with Ancillary Two- Storey Offices.

Client: Mr. James Fenton & Mr. John Cahill Architect: Tony Dunlea Consulting Engineer Engineer: Tony Dunlea Consulting Engineer


Christy Kearney, Little Island, Co. Cork Commercial retail unit located within Euro Business Park Little Island.

Client: Architect: Engineer:

Christy Keanrey Concept Design Concept Design


OS Sheet Metals, Tramore Rd, Cork Refurbishment & Alterations to Industrial Unit & associated site works.

Client: OS Sheet Metals Value: ₏1,700,000 Engineer: Waterman Consulting Engineer’s Frame: 10months

Contract Time


Toss Bryan, Fermoy, Co. Cork Commercial Unit located in Fermoy

Client:

Toss Bryan

Engineer: Engineers

Sean McCarthy Consulting


Greenstar Recycling Ltd. Construction of an commercial recycling unit with underground waterproof concrete structures , in Glanmire, Co. Cork

Client:

Greenstar Recycling Ltd.

Architects: O Riordan Staehli Architects


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.