5. Concretework

Beams mh/m3

Width of beam Width of beam 150 mm 500 mm Casting with crane 0,9 0,5 The volume of the work is anticipated to be 200 m3. by 25 m3, add 17%.

Colums mh/m3

Circumference Circumference Circumference 1,2 m 1,8 m 2,4 m Casting with crane 2,1 1,3 0,8 The volume of the work is anticipated to be 200 m3. by 25 m3, add 17%.

Storey partition rough casting mh/m3

Thickness of storey partition Thickness of storey partition 160 mm 250 mm Casting with crane 500 l. bucket 0,44 0,37 Casting with crane 750 l. bucket 0,33 0,28 Casting with pump 0,21 0,21 Casting with conveyor belt 0,30 0,30 The volume of the work is anticipated to be 2000 m3. by 250 m3, add 17%.