CHAPTER 5

Stakeholder Analysis and Communication Planning

LEARNING OBJECTIVES

This chapter introduces the need for and the methods of both stakeholder analysis and communication planning. After completing this chapter, each student should be able to perform the following:

1. Enumerate, describe, and prioritize each set of stakeholders for a project.

2. Tell how to build project relationships and why they are important for communications.

3. Enumerate each section of a project communications plan and describe the role each plays.

4. Develop a project communications management plan for a real project.

5. Plan, conduct, and improve project meetings.

6. Describe communication challenges of virtual and global project teams.

TEACHING STRATEGIES

• An interesting Segway between chapters 4 and 5 is the introductory essay. Arthur Shelly has developed the organizational zoo. Using this or another instrument like StrengthsFinders from Gallup can give the students more understanding of themselves, their team, and their stakeholders. Students may enjoy creating their own profiles now

Instructor’s Manual Chapter 5 1
copied or duplicated, or posted to a publicly accessible website, in whole
in part.
© 2015 Cengage Learning. All Rights Reserved. May not be scanned,
or

(early in the course) and having their teammates create profiles for them later in the course.

• I like to use projects that are in the news as examples to demonstrate points in this chapter. Controversial, local projects that are either under way or are under consideration work very well since they typically have many stakeholders with communication needs.

• One breakout is to have students identify and categorize as many stakeholders as they can for an upcoming project. I often assign four groups of students to identify respectively internal stakeholders affected by the process, external stakeholders affected by the process, internal stakeholders affected by the results and external stakeholders affected by the results. I tell them bragging rights go to the group that identifies the most stakeholders like in Exhibit 5.3. If any of the stakeholders identified are unexpected, I ask the group in what way they are stakeholders. It often takes the students by surprise how many people could have an interest in some of the projects.

• A follow-up break out session is to have the students then prioritize the stakeholders and to justify their decisions. They can prioritize in accordance with Exhibit 5.4.

• A third possible breakout for this chapter is to have students make plans for a local project about how decisions should be made. I ask them to use the generic situations listed in Exhibit 5.7 and to give specific examples of each. We then discuss why each method makes sense for the situations listed.

• Another breakout can be for the communication matrix. Show them Exhibit 5.11 as the communication matrix for the Alternative Breaks Project. I usually let the student teams begin the communication matrix for their class project. Giving them 10 minutes of class time to start and then to discuss gets them off to a good start. Be sure to emphasize that if they look at one or more previous projects (such as Alternative Breaks), that the stakeholder list is likely to be quite different than theirs and, therefore, much of the information in the other columns will also differ. They need to be careful to look at other projects for ideas – not with an eye toward just copying.

• When introducing the subject of managing the meetings, I ask if anyone ever wasted time in a meeting. That is so obviously a rhetorical question that students will actually laugh. At any rate, explaining the meeting agenda and having the students plan a meeting for their project illustrates the point. I tell them I will want to see copies of their agenda, minutes, and evaluation for one of their meetings.

• You may wish to include some time for virtual and global project teams. If some of your students have much work experience, this is easier as they will be quick to want to tell their classmates how they do things. Even if few of your students have much experience, you can engage them in interesting discussions.

LECTURE AND WORKSHOP OUTLINE

A good place to start detailed planning (after the charter is accepted) is with understanding who the stakeholders are and how to communicate with them.

5.1 Develop the Project Management Plan

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

5 2
Instructor’s Manual Chapter

Chapters 5-11 deal with the project management plan (the formal, approved document that tells how the project will be executed, monitored, and controlled). It can be started now, but will not be finished until project kick-off.

5.2 Identify Stakeholders

It is imperative to understand the various stakeholders and their sometimes conflicting desires.

Find stakeholders

Anyone impacted positively or negatively by the process of performing the project or the results of the project is a stakeholder that needs to be identified.

Analyze Stakeholders

Prioritizing among the many stakeholders is vital to ensure the most important project needs are addressed.

Document Stakeholders

The stakeholder register is a document for recording all information on stakeholders.

5.3 Build Relationships

Since PMs often do not have enough formal authority to command, developing relationships to influence others is critical.

Relationship building within the core team

A smart PM develops effective working relationships within the core team.

Relationship building with all other stakeholders

This is important both to influence favorable behavior and to lay the groundwork for effective communication.

5.4 Plan Communications Management

Purposes of a project communications management plan

A PM must use effective communications to set and manage expectations from all stakeholders as well as to ensure that project work is completed properly.

Communications plan considerations

Purpose

Project communications need to be clear, concise, courteous, consistent, confidential, and compelling.

Structures

Projects can use existing organizational communication forms if they are satisfactory, but need to create their own to supplement.

Methods

Communications can be pushed to recipients, or pulled by them, or interactive with them.

Timing

Communications can be tied to the project life cycle, be routine, or as needed.

Communications matrix

o Who does the project team need to learn from?

o What does the team need to learn from this stakeholder?

o Who does the project team need to share with?

o What does this stakeholder need to know?

o When do they need to know it?

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 3

o What is the most effective communications method for this stakeholder to understand?

o Who on the project team is responsible for this communication? (the owner)

Knowledge management

If lessons-learned are captured and shared, a project can learn from previous projects.

5.5 Project Meeting Management

Projects require many meetings and can benefit from having them well-run. Improving project meetings

Meetings are a process that can be studied and improved.

PDCA model

This quality approach to process improvement can be applied to the meeting process.

Project meeting agenda template

Well-run meetings require planning. A clear agenda helps.

Project meeting minutes template

Decisions made, issues surfaced or resolved, action items agreed to, and evaluation of the meeting should be concisely captured.

Issues management

An issues log is a living document adding new issues and removing resolved issues.

Decisions and Issues

All decisions made should be documented. An issue is something that does not need to be resolved immediately, but will need to be resolved in time.

Action items

For each agreed upon action, capture who will do it and by when.

Evaluation

Meetings can be evaluated using a plus-delta. Evaluations on agile projects are called retrospectives.

5.6 Communications Needs of Global and Virtual Project Teams

More projects are conducted by virtual and global teams and these teams often have increased communication challenges. Virtual teams

Even more persuasion is needed since these teams are scattered. Cultural differences

It is vital for the PM to understand cultural influences on behavior. Countries and project communications preferences

People in various countries have widely differing communication preferences that need to be understood.

5.7 Communications Technologies

An ever increasing number of communication choices are available.

CHAPTER REVIEW QUESTIONS –

SUGGESTED

ANSWERS

1. List three reasons why understanding stakeholders is important to successful project management. (objective #1, p.120)

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 4

By determining who the stakeholders are and what each group wants, project managers effectively:

• Set clear direction for further project planning, negotiating, and execution

• Prioritize among competing objectives

• Learn to recognize complex tradeoffs and the consequences of each

• Make and facilitate necessary decisions

• Develop a shared sense of risk

• Build a strong relationship with their customers

• Lead associates, customers, and suppliers with an empowering style

• Serve as good stewards of the resources of both the parent and customer organizations

2. What is the difference between an internal and external stakeholder? (objective #1, p.119) Internal stakeholders are within the organization performing the project; external stakeholders are not.

3. Which three criteria should you consider when prioritizing stakeholders? (objective #1, pp.120-121)

• Proximity to the project – those that are closest are often the most important.

• Power they have over the project – more powerful stakeholders need to be prioritized higher.

• Urgency of their need – stakeholders who need something very quickly need to be given priority.

4. When should relationship building between the project manager/other core team members and important stakeholders occur? (objective #2, p.123) Throughout the life of the project

5. What are some ways to build relationships within the core team? (objective #2, p.124)

• Acknowledging individual motives

• Encouraging open communication

• Jointly establishing project meeting agendas

• Sharing in meaningful project learning

• Frequently celebrating small successes

6. What are some ways to build relationships with key stakeholders? (objective #2, p.125) The sponsor, project manager, and core team can establish powerful relationships with key stakeholders by delivering on all promises, always providing fair treatment, creating a sense of pride by association, and even helping the stakeholder develop a passion for the project.

7. What are some important functions of communication from stakeholders? (objective #3, p. 126)

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 5

Communications from stakeholders are necessary in authorizing work, determining requirements, uncovering and resolving issues, and receiving feedback on project progress and results.

8. What are some important functions of communication to stakeholders? (objective #3, p.126) Communications to stakeholders are necessary to help them make good decisions (by understanding options and risks), assure them of adequate understanding and progress, enable them to more fully commit to the project, and be ready to accept project deliverables.

9. What is the difference between “push” and “pull” methods of communication? (objective #3, p.128)

Projects rely on “push” methods in which communications are sent or pushed; “pull” methods where communications are posted either on paper or in electronic form and interested stakeholders need to take the initiative to receive the communication.

10. What are three types of project communications timing schedules? (objective #4, p.128)

First is the project life cycle, with communications typically needed at the end of each major stage in the project and at the end of each major project deliverable. The second timing schedule follows a more formal organizational structure. Project progress is often reported at regularly scheduled meetings. Meetings at the frontline level are usually more frequent than reports to higher levels within the organization. The third timing scheme is an as-needed basis.

11. What six columns should a communication matrix contain? (objective #4, p.129)

1. STAKEHOLDER

2. LEARN FROM

3. SHARE WITH

4. TIMING

5. METHOD

6. OWNER

12. Why is it so important to capture lessons learned in a knowledge database? (objective #4, p.130)

Keep developing and utilizing strengths, but avoid repeating failures.

13. List the items that go into a project team meeting agenda and tell the purpose of each. (objective #5, pp.130-131)

Meeting logistics such as people, date, time, and place – so that all can attend. Purpose – so that people know what the meeting needs to accomplish and not hold the meeting if there is no good purpose.

Topics in order – so that people know what to expect and to prepare for.

Person responsible for each topic – so that they will be prepared and so any stakeholder can communicate with that person in advance.

Estimated time for each topic – to stay on track.

Summary – so that people remember what decisions were made, issues raised or resolved, and what are the items on which they agreed to take action, and the deadline for each.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Manual Chapter 5 6
Instructor’s

Evaluation

so that future meetings can repeat what worked and avoid what did not.

14. Describe an AGILE “stand-up” meeting. (objective #5, p.130)

These short (15 minute or less) meetings are often held at the start of each day with no coffee or chairs to be comfortable. Each project team member briefly states what she accomplished the previous day, what she plans to accomplish this day, and what obstacles may challenge her.

15. List and describe the four main types of information captured in project meeting minutes. (objective #5, p.132)

• Decisions made – to communicate to all stakeholders.

• Issues raised and resolved – to keep track of active issues.

• Items on which actions to be taken, with responsibility and timing – to ensure agreed to items are completed.

• Evaluation – so that the pluses and deltas identified can be associated with the specific meeting when they were identified.

16. What is a virtual team? (objective #6, pp.134-135)

“A group of people with a shared goal who fulfill their roles with little or no time meeting face to face” (PMBOK)

17. Name three increased challenges for global and/or virtual teams. (objective #6, p.135)

• More unique project needs

• More difficult to understand

• Needs more time

• More reliance on electronic means

• More facilitating than directing

• Fewer nonverbal cues, interest may wander

• With less group interaction, harder to identify

18. Why is it helpful for a virtual team to meet in person at least once? (objective #6, pp.135136)

To foster a sense of teamwork and common understanding of the project

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 7

DISCUSSION QUESTIONS

SUGGESTED ANSWERS

1. A new grocery store is being erected, which will demolish a neighborhood basketball court. Who would be an internal stakeholder? Who would be an external stakeholder? (p.119, Analyzing)

Internal stakeholders include anyone working on the project. External stakeholders could include neighborhood residents and/or anyone affected by either the project execution or the results of the project.

2. Think of a recent project you completed and choose three stakeholders. Prioritize them, using Bourne’s and Walker’s three criteria model. (p.120, Creating)

Answers will vary.

3. In your opinion, what is the single most important component of building relationships within a project team? Why? (p.124, Evaluating)

Answers will vary but should be supported.

4. In your opinion, what is the greatest benefit of having good communication between the project team and project stakeholders? Why? (pp124-126, Evaluating)

Answers will vary but should be supported.5. Imagine you are the project manager of a team tasked with building a new hotel. When brainstorming project communication plan considerations, what would you list under “purposes”? (pp.126-128, Applying)

Answers will vary and may include: authorization, status reporting, information seeking, etc.

6. Using the same scenario as Question 5, which timing schedule would you choose to use? Why? (p. 128, Evaluating)

Answers will vary among the three timing schedules listed but should be supported.

7. Create a project meeting agenda for an upcoming project (or class) meeting you have. (pp.130-132, Creating)

Student examples should use template given on p.131.

8. Betty, a project manager, sent out agendas before an upcoming meeting to everyone involved. During the meeting, she got a team member to take minutes. After the meeting, Betty followed up with team members to check their progress.

Evaluate Betty’s actions using the PDCA model. What, if anything, could she have done better? (p.131, Evaluating)

Betty neglected the “Check” step of the PDCA model, which entails having the team members evaluate the meeting itself.

9. You are working for a multinational organization and need to relay information to Japan. Which communication method would you chose to use and why? (pp.135-136, Analyzing)

Answers will vary but should be supported. The chart on p.136 says that the Japanese often value face-to-face interaction, so perhaps a video conference would be a good choice.

Instructor’s Manual Chapter 5 8
part.
© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in

10. Give as many examples of cultural differences as you can, using information from the text and your own experiences. (pp.135-136, Applying)

Answers will vary and should include some of the examples listed on pp.135-136.

PMBOK® Guide Questions

1) The “component of the project management plan that describes how project communications will be planned, structured, monitored and controlled” is the:

a) Communication model

b) Communications management plan

c) Stakeholder register

d) Organizational breakdown structure

Answer: b

Page 126 in textbook

Page 296 PMBOK 5th Edition

2) In order for a new grocery store to be erected, a neighborhood basketball court located on the building site will have to be demolished. The neighborhood children who liked to play basketball there could be considered as _________:

a) Subject matter experts

b) Internal stakeholders

c) External stakeholders

d) Customers

Answer: c

Page 119 in textbook

Page 394 PMBOK 5th Edition

3) According to the PMBOK® Guide, stakeholders can be prioritized by their potential impact on the project based on a determination of all of the factors below EXCEPT:

a) Level of authority

b) Level of concern

c) Active involvement

d) Political connections

Answer: d

Page 120 in textbook

Pages 395 - 397 PMBOK 5th Edition

4) The components of a project communications management plan should typically include the purpose of the communication, structure (format, content etc.), methods or technologies to be used, and _______:

a) Work performance data

b) Time frame and frequency

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 9

c) Stakeholder priorities

d) Lessons learned

Answer: b

Pages 127-128 in textbook

Page 296 PMBOK 5th Edition

5) Which of these is NOT a challenge of working on global and virtual teams?

a) Competencies

b) Language

c) Time zones

d) Culture

Answer: a

Pages 134-135 in textbook

Pages 292 - 295 PMBOK 5th Edition

6) Most project meetings are formal, planned events between project stakeholders. Effective meetings typically have a purpose, a pre-arranged time and place, a list of attendees and their roles, and an agenda with topics and issues to be discussed. After the meeting, _______ are circulated.

a) Refreshments

b) Business cards

c) Meeting minutes

d) Lessons learned

Answer: c

Page 132 in textbook

Pages 84 and 295 PMBOK 5th Edition

7) The “project document that includes the identification, assessment and classification of project stakeholders” is called the _____________.

a) Stakeholder engagement matrix

b) Organizational breakdown structure

c) Stakeholder register

d) Weighted scoring model

Answer: c

Pages 121-122 in textbook

Pages 398 & 563, PMBOK 5th Edition

8) Inadequate communications planning may endanger the success of the project. Which of these could be a problem resulting from poor communications planning?

a) Communication to the wrong audience

b) Delay in message delivery

c) Misinterpretation of the message communicated

d) All of the above could be problems

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 10

Answer: d

Pages 126-128 in textbook

Page 290 PMBOK, 5th Edition

9) One of the key responsibilities of a project manager is to manage stakeholder expectations. It is important for the project manager to have interpersonal or “soft” skills that include: overcoming resistance to change, resolving conflict, active listening and _____:

a) Displaying confidence

b) Subject matter expertise

c) Ability to command and control

d) Building trust

Answer: d

Pages 123-125 in textbook

Pages 407 - 408 PMBOK

10) The communication method that is used for large audiences or large volumes of information and requires recipients to access the content at their own discretion, is called

communication.

a) Push

b) Pull

c) Synchronous

d) Interactive

Answer: b

Page 128 in textbook

Page 295, PMBOK 5th Edition

EXAMPLE PROJECT

Develop a stakeholder analysis for your example project. Identify as many stakeholders as you can using Exhibit 5.3. List stakeholders by name and title where possible. Then prioritize the listed stakeholders as in Exhibit 5.4. Be very specific regarding what each stakeholder is interested in. Recognize some stakeholders may have an interest in multiple aspects of the project process or results. Create a Stakeholder Matrix (register) like exhibit 5.6.

Answers will vary, but students should have identified quite a few individuals, groups, or organizations as stakeholders, prioritized them as key or other, listed their interests, and have at least an idea for support and/or mitigation strategies for each.

Describe the activities you are using to build relationships both within your core team and with other stakeholders. Create a project decision-making guide for your project like Exhibit 5.7. List specific examples of decisions to the extent you can.

Again, answers will vary, but the more specific the students are, the better.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 11
__________

Create a stakeholder engagement assessment matrix like Exhibit 5.8.

The students may struggle with this initially, but try to get them to realistically assess what the various stakeholder groups think about their project and how to improve those attitudes.

Develop a communications matrix for your project like Exhibit 5.11. Be sure to use considerations in Exhibit 5.10 for ideas regarding purpose, structure, method, and timing for each communication need.

This is the primary deliverable from Chapter 5. Most of the other work leads up to this. Since many projects experience problems due to poor communication, a workable communication matrix is quite valuable. The matrix should have all six columns shown in Exhibit 5.11. One big lesson for students is many stakeholders need to learn certain things from the project team, but need to supply the project team with very different information. Hence, check the learn from and share with columns for logic carefully.

Document a project meeting with an advance agenda, meeting minutes, issues log, and Plus Delta form of evaluation like Exhibits 5.11 through 5.14.

This can be a major assignment in itself or part of a communications plan assignment. I try hard to get the students to plan at least one meeting effectively, run it according to the agenda, capture minutes and issues, and then evaluate the meeting. If you only talk about this, but do not require it, many students will not do it. The learning comes from the practice, not being lectured.

Communication Plan Grading Suggestions

1. Plan purpose – A brief description of why and how the plan was developed, and an overview of the overall team communication philosophy. Also states types of communications planned, for lateral, downward, and upward communication.

2. Identification of stakeholders – The “who” in the project that requires information, (i.e. team members, project sponsor, class professor, etc.) and also the responsible parties to receive and/or communicate information.

3. Information to be shared – The “what” in terms of project information communication. Describes types of information that the team uses to communicate amongst its own team members, and also to the agency sponsor and the class professor.

4. Frequency of information exchange – The “when” describes how often communications will be held (i.e. daily, weekly, monthly, as needed, etc.)

5. Location of information exchange – The “where” states the location of the meeting or other interactions

6. Purpose of communication – The “why” description assures that communications are held effectively.

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Manual Chapter 5 12
Instructor’s

7. Mechanism for communication – The “how” describes the media for communication (i.e. physical meeting, email, phone, message group, etc.)

8. Change management – Description on how the team will handle changes in the project, whether it is in terms of project scope, schedule, or resources. This includes how the team plans to communicate changes as well as how the team plans to make decisions about changes.

9. Meeting agenda – Gives a brief overview of what the team plans to accomplish in each of its meetings, how it documents goals and objectives for meetings, and defines and assigns actions for the team to accomplish project objectives.

PMP judges use the following criteria when evaluating communication plans.

Communication

Deliverable 1 2 3 4 5 Team Meetings Not Considered Defined but unclear.

Internal team meetings are planned and conducted as per a schedule.

Meetings are planned, conducted followed by Minute of the Meetings

Meetings are planned, conducted followed by Minute of the Meetings and Action items.

Communication Plan (Who, When, How, What, inbound, outbound)

Not Considered Defined but unclear.

Defined Who and When communication will take place.

Defined Who, When and How (method) communication will take place.

Defined Who, When, How, What communication will take place. Forms / Templates are covered. Issue Escalation Methods

Not Considered Escalation method is defined but unclear

Escalation method is defined, but without process documentation

Escalation method is defined including process documentation.

Escalation method is defined including process documentation & Issue log template

© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.

Instructor’s Manual Chapter 5 13