extended
jack elliott
portfolio
residential - private
eas Report - ‘House on the Seafront’
01
02
Rear extension
Side extension
New build
New build
Rear extension
Internal refurbishment*
Internal refurbishment
Internal refurbishment
RIBA stages 1-3
RIBA stages 1-4
RIBA stages 1-3
RIBA stages 1-3
RIBA stages 1-3
RIBA stage 4
RIBA stages 1-2
RIBA stages 1-6
09
10
11
12
13
15
16
Feasibility study Developed design Planning application
Feasibility study Developed design Planning application Building regulations package
03
Feasibility study Developed design Planning application
04
Feasibility study Developed design Planning application
05
Feasibility study Developed design Planning application
06
07
Construction drawings package
08
Feasibility study Developed design
14
Feasibility study Developed design Construction drawings package Draft Schedule of Works Tender and negotiations Site inspections Contract administration Handover
L Ridge level: +76,536 (10,986)
Drawing notes: 1. Steps leading to basement/external courtyard area. Rise of 192mm with going of 270mm. Pitch of 34 degrees. Steps to be formed in reinforced concrete as per structural engineer's design and calculations. Tread and Rise finishes as per finishes schedule. Allow for 20mm overhang nosing. Handrail to at 900mm above pitch line of steps and comply with BS8300/Part M. 2. B/01 Workshop below natural ground level formed in 'Insulated Concrete Forms' (specification by specialist). Mechanical ventilation to be designed by specialist. Finishes as per finishes schedule. Refer to drawing 009-4-000-Basement for further details and setting out.
Roof slopes upwards
Roof slopes upwards
Second floor FFL: +76,022 (10,472)
3. 350mm x 100m structural support (vertical and following angle of roof pitch) to structural engineer's design and calculations. Appearance/external finish to be untreated Oak to allow for weathering. Allow for 'metal' capping above support (spec. to be confirmed). Refer to 009-4-001-Ground for further details and setting out.
Timber cladding Tiles
Tiles
3823
Second floor window head: +74,400 (8,850)
2200
2200
6282
3000
10
6. Oak front door (solid) with vertical fluting to match timber cladding design elsewhere. Oak frame with 'Multilock' locking mechanism (or similar approved) within door leaf to comply with insurance requirements etc. Refer to architect's detailed joinery drawings for further details and specification.
47°
Eaves: +72,840 (7,290)
W2-01 Timber cladding
Timber cladding Second floor FFL: +72,200 (6,650)
Second floor window cill: +72,200 (6,650)
575
565
575
575
Ground slab FFL: +72,025 (6,475) Ground slab soffit: +71,825 (6,275) First ceiling soffit: +71,625 (6,075)
First floor window head: +71,625 (6,075)
W1-06
2905
Opening (top hung)
Timber cladding
1850
First floor window - 1850
1850
Opening (top hung)
Fixed
Timber cladding First floor window cill: +69,775 (4,225)
948
3000
900
500
8
W1-01
200
Eaves height - 7290
1242
First floor FFL: +68,875 (3,325)
7
Cantilevered canopy structure
500
948
1242
5898 Top of canopy: +68,700 (3,150)
First slab soffit: +68,450 (2,900)
200
First slab FFL: +68,700 (3,150) 625
8. Vertically installed, untreated timber cladding (Oak) width/setting out to be confirmed) on horizontal/vertical 25mm x 38mm preservative treated softwood battens. Stainless steel screw fixing through external face of timber. Note: horizontal line of fitting to be accurately set out to create neat finish
10. Hidden guttering detail within roof (to be confirmed pending tile choice). 11. Roof build up: - Tiled (specification to be confirmed) on; - 25mm x 38mm timber battens on; - DuPont Tyvek Supro Plus breather membrane or equal. - New timber rafters to structural engineer's spec. - Maintain 50mm clear ventilation void with; - 50mm Celotex GA4000 or equal installed between rafters. - 100mm Celotex GA4000 or equal installed beneath rafters. - DuPont Tyvek AirGuard Control vapour barrier or equal below. - 12.5mm Gyproc Wallboard plasterboard. - Skimmed and decorated. - Roof build-up to achieve a U-value of 0.18 W/m2k or better.
1075
FFL to FFL - 3325
W1-02
2750
Top of slab to top of slab - 3325
9
7. Cantilevered concrete canopy to structural engineer's design and calculations (finish to be confirmed). Overall dimensions of W.6,020mm, H.280mm and D.1,200mm. Drainage as per mechanical drawings (Waterproofing above/capping etc.).
9. Glazing with top hung opening pane for ventilation: Windows to be double glazed aluminium frames in standard RAL colour (to be confirmed). All windows to comply with building regulations and achieve a U-value of 1.6m/m2k or better OR window energy rating Band C or above. Allow for trickle vents to comply with ventilation requirements. Glazing in critical locations to be toughened or laminated safety glass.
Timber cladding
350
4. Elevation to ground floor level to be rendered. ICF structural system with render-boards (Knauf AQUAPANEL® Cement Board Outdoor (or similar) fixed as per manufacturer's recommendations to 25mm x 38mm treated cross battens for ventilation. Nominal insect mesh at top and bottom. OR direct render application to ICF system to manufacturer's recommendation. 5. Fixed, glazed windows to both sides of entrance door W.960mm x H2,776mm: Windows to be double glazed aluminium frames in standard RAL colour (to be confirmed). All windows to comply with building regulations and achieve a U-value of 1.6m/m2k or better OR window energy rating Band C or above. Allow for trickle vents to comply with ventilation requirements. Glazing in critical locations to be toughened or laminated safety glass as per part K of the building regulations and in accordance with Class 3B3 of BS EN 12600 or Class C of BS 6206 and BS EN 14179-1: 2005. Critical glazing locations refers to all glazing within 1,500mm above finished floor level in doors, glazing within 300mm of door openings and all glazing within 800mm above finished floor level in windows.
11
Canopy soffit: +68,500 (2,950)
20
Ground ceiling soffit: +68,250 (2,700) Open
4704
First floor window cill - 4225
Open
Render
Fixed
Fixed
5
4
Render
2930
Door/fenestration shown indicatively
2950
Render - 3150
Render
E D C B A /
6 Door D1-01
3 40 17
375
Ground floor FFL: +65,550 (0,000) Ground slab FFL: +65,375 (-0,175)
16
Ground slab soffit: +65,175 (-0,375)
15
350
14
Rev:
960 1318
Basement ceiling soffit: +64,975 (-0,575) 2690
1080 3000
13
2690
1318
350
Width of elevation - 8380 Overall width - 11716
12
2950
FFL to FFL - 3325
Top of slab to top of slab - 3325
B/01
WORKSHOP AREA = 12.5m² FFL - U/C = 2,964mm
10
Basement height: FFL to underside slab: 2,750mm FFL not shown due to paper size refer to basement layout/sections)
9 8
External stairs to basement level. Rise of 195.6mm Going of 364mm
B/02
BASEMENT AREA = xx.xm² FFL - U/C = 2,964mm
7 6 5 4
1
1
PROPOSED ELEVATION (NORTH) Scale 1:25 at A1
0mm
1,000mm
Balcony amended
16.08.22
Issued for information
29.06.22 25.05.22
Issued for information Issued for information
29.04.22
Issued for costing
08.12.21
Issued for information
Date:
Notes:
JMP JMP JMP JMP JMP JMP Drawn by:
4A ERRINGHAM FARM SHOREHAM-BY-SEA BN43 5FA
009-4-101-E
11
2
18.08.22
PUMP HOUSE
960
2,000mm
3 2
ELEVATION 1 (NORTH)
INFORMATION
FFL to FFL - 3325
2700
Top of slab to top of slab - 3325
Render
SCALE: 1:25 AT A1 DRAWN BY: JMP STATUS:
FOR INFORMATION NOTES: Do not scale from this drawing, use given dimensions. All measurements and site conditions are to be checked prior to the preparation of drawings or commencement of works. This drawing belongs to James Patterson Architects Ltd. and is protected by the Copyright, Designs and Patents Act, 1998.
Car port
Rear extension
New build*
Rear & loft extensions
Rear & side extensions
Internal refurbishment*
New build*
Full renovation
RIBA stages 1-4
RIBA stages 3-5
RIBA stages 1-3
RIBA stages 1-3
RIBA stages 0-4
RIBA stages 2-4
RIBA stages 2-4
RIBA stages 0-3
Feasibility study Developed design Planning application Construction drawings package Draft Schedule of Works Tender and negotiations
Planning application Construction drawings package Draft Schedule of Works Tender and negotiations Site inspections
Feasibility study Developed design Planning application
Feasibility study Developed design Planning application
Pre-employment client meeting Draft fee proposal Feasibility study Planning application Construction drawings package Draft Schedule of Works Tender and negotiations
Developed design Construction drawings package
Developed design Planning application Construction drawings package
Pre-employment client meeting Draft fee proposal Feasibility study Planning application
*Assistant to lead designer
Complete remodelling of 30m² apartment Marylebone, London Completed 2021 £75k
project location work stage budget
Lead Designer
Initial concept design Detailed developed design Coordination of obtaining appropriate permissions Construction drawings package Draft Schedule of Works Tender and negotiations On-site management Handover
role
RIBA Stage 1 Created feasibility study document Precedent study Presented ideas to clients Discussed procurement strategies with client RIBA Stage 2 Developed design ideas in response to client feedback Finalisation of design brief Consolidation of aesthetic preference Discussed third-party professional consultants
Concept design 3D visuals using Revit
RIBA Stage 3 Coordination of obtaining appropriate permissions Confirmed outline specification for key elements Discussed cost plan opportunity with clients Initiated conversations with prospective contractors RIBA Stage 4 Compiled all necessary specification information Formed comprehensive set of construction drawings Coordinated & integrated structural design into drawings Prepared Schedule of Works Issued all tender documentation to prospective contractors Value engineer design to fit within final budget RIBA Stage 5 Site inspections & build quality assurance Response to site queries Monitor progress according to construction programme Valuations & contract administration RIBA Stage 6 Project review Rectify defects Issue final certificate
08
Concept design sketches
ALL CUPBOARD DOORS AND DRAWERS TO BE MEASURED ON-SITE FOLLOWING INSTALLATION OF KITCHEN CARCASS
18mm MDF with white lacquered upboard doors. 2mm gaps around doors to carcass. Specialist/contractor to advise. Clothes hanging rail within wardrobe.
75mm (w) x 36mm (d) cuts into carcass with 18mm radius corners for storage access. Specialist/contractor to advise.
LED strip lighting recessed to underside of shelf. FRIDGE
18mm MDF with oak veneered cupboard doors. 2mm gaps around doors to carcass. Specialist/contractor to advise.
Milano Aruba - White Designer-Style Vertical Radiator 1780mm x 354mm (Double Panel).
EXTRACT
USB/Power outlets with flush finished faceplates.
1800
Parkside Halford White 297x97mm tiles gloss finish with 3mm grey coloured grout. Pattern as shown. TBC by client.
PULL-OUT DRAWER
OVEN
PULL-OUT DRAWER
FREEZER
PULL-OUT DRAWER PULL-OUT WASTE DRAWER
1200
Concealed hinges to be rebated into door and door lining. Specialist/contractor to advise on specification.
Howdens supplied kitchen carcass. Specialist/contractor to advise. 20mm Bianco Assoluto honed counter top.
18mm MDF with white lacquered cupboard doors. 2mm gaps around doors to carcass. Specialist/contractor to advise.
400
Concealed hinges to be rebated into door and door lining. Specialist/contractor to advise on specification.
Dotted line denotes drawer side runners. Specialist/contractor to advise.
D/W PULL-OUT DRAWER PULL-OUT DRAWER
50x100mm timber structure. Specialist/contractor to advise. 75mm kick plate depth set back.
Section A-A extract from construction drawings package
PROPOSED SECTION A-A 1:20 @ A1
03 det New ceiling installed to house lighting and electrics. Ensure waterproof coating on 18mm marine plywood. Finished ceiling heights to be level throughout flat.
909 Denotes as installed dropped ceiling system
30mm frame Crittall-style internal glazing fixed to joinery. Specialist/contractor to advise.
486
600
Shelves fixed to joinery. Specialist/contractor to advise.
18
168
600
600
600
168
204
240
Contractor to install dropped ceilings throughout to house electrics. No insulation. Cornicing removed.
Clear 6 side panel 900mm and In-fold door in clear glass/black. TBC by Contractor.
50
30mm frame Crittall-style internal glazing with fluted obscure glass. Specialist/contractor to advise.
451
30mm frame Crittall-style internal sliding glazed screen with suspended track. Specialist/contractor to advise.
50
486
1464
18
Alcove shelf recessed into studded out walls lined with Neutra Greyish tiles to match floor. TBC by Contractor.
50
Boxed out shelf to enclose pipework to bathroom and toilet systern finished with Neutra Greyish tiles to match floor. TBC by Contractor. Flushe 2.0 Framed Cistern - Front Flush with Flushe 2.0 square chrome face plate. Austen Slim white gloss wall mounted WC with Austen white gloss soft close seat & cover.
984
20mm quartz detachable breakfast bar with fixed steel leg. Metal dowels at end to slot into holes in joinery ledge. Specialist/contractor to advise. TBC on-site.
336 480
25
930
OG
450
50x100mm timber structure. Specialist/contractor to advise. 75mm kick plate depth set back.
Universal 40 900 x 900mm shower tray in grey to match floor tiles and chrome waste. Installed as per manufacturers instructions. Tray recessed into stud wall by 46mm Contractor to confirm on-site.
Finished project photograph showing kitchen area
PROPOSED SECTION B-B 1:20 @ A1 0 d
08
Contractor to install dropped ceilings throughout to house electrics. No insulation. Cornicing removed.
451 50
486
1464
486 336
25
OG
OG
450
50x100mm timber structure. Specialist/contractor to advise. 75mm kick plate depth set back.
450
50x100mm timber structure. Specialist/contractor to advise. 75mm kick plate depth set back.
30mm frame Crittall-style internal glazing with fluted obscure glass. Specialist/contractor to advise.
Alcove shelf recessed into studded out walls lined with Neutra Greyish tiles to match floor. TBC by Contractor.
Alcove shelf recessed into studded out walls lined with Neutra Greyish tiles to match floor. TBC by Contractor.
Boxed out shelf to enclose pipework to bathroom and toilet systern finished with Neutra Greyish tiles to match floor. TBC by Contractor. Flushe 2.0 Framed Cistern - Front Flush with Flushe 2.0 square chrome face plate. Austen Slim white gloss wall mounted WC with Austen white gloss soft close seat & cover.
Boxed out shelf to enclose pipework to bathroom and toilet systern finished with Neutra Greyish tiles to match floor. TBC by Contractor. Flushe 2.0 Framed Cistern - Front Flush with Flushe 2.0 square chrome face plate. Austen Slim white gloss wall mounted WC with Austen white gloss soft close seat & cover.
Universal 40 900 x 900mm shower tray in grey to match floor tiles and chrome waste. Installed as per manufacturers instructions. Tray recessed into stud wall by 46mm Contractor to confirm on-site.
Universal 40 900 x 900mm shower tray in grey to match floor tiles and chrome waste. Installed as per manufacturers instructions. Tray recessed into stud wall by 46mm Contractor to confirm on-site.
930
930
480
25
480
336
984
50 984
50
30mm frame Crittall-style internal glazing with fluted obscure glass. Specialist/contractor to advise.
1464
20mm quartz detachable breakfast bar with fixed steel leg. Metal dowels at end to slot into holes in joinery ledge. Specialist/contractor to advise. TBC on-site.
50 18
20mm quartz detachable breakfast bar with fixed steel leg. Metal dowels at end to slot into holes in joinery ledge. Specialist/contractor to advise. TBC on-site.
451
30mm frame Crittall-style internal sliding glazed screen with suspended track. Specialist/contractor to advise.
18
30mm frame Crittall-style internal sliding glazed screen with suspended track. Specialist/contractor to advise.
PROPOSED SECTIONPROPOSED B-B 1:20 @ SECTION A1 B-B 1:20 @ A1 03 det
03 det
Concrete ceiling
Concrete ceiling
240
240
Timber ladder beam per structural Timber ladder engineer beam drawing per structural engineer drawing
6 204
204
6
Additional 50x100mm timber Additional between 50x100mm steel joists timber between steel joists
Steel struts fixed to ceilingSteel struts fixed to ceiling
Sliding door track
Sliding door track
Wardrobe
Wardrobe 01273 688 744 studio@lifesizearchitecture.co.uk www.lifesizearchitecture.co.uk
description:
title:
01273 688 744 studio@lifesizearchitecture.co.uk www.lifesizearchitecture.co.uk
revision: date: description:
title:
PROPOSED SECTION PROPOSED B-B SECTION & HANGING TRACK & HANGING DETAILTRACK 03 D
project no:
19036HS
no: drawingproject no:
02319036HS
drawing status:
drawing no:
023
drawing status:
CONSTRUCTION CONSTRUCTION
Section detail of hanging track for sliding glazed screen extract from construction drawings package
Photograph of completed project to show hanging track for sliding glazed screen
client:
client:
project:
project:
KATRI KAIKKONEN
KATRI KAIKKONEN
FLAT 73, 105 HALLAM STREET FLAT 73, 105 HALLAM STREET LONDON LONDON
PROPOSED HANGINGPROPOSED TRACK DETAIL HANGING 03 1:5TRACK DETAIL 03 1:5 @ A1 @ A1
08
date:
06/04/21
scale:
1:VAR @ A1
date: drawn:
06/04/21 JE
checked: scale:
1:VAR RB @ A1
drawn:
JE
Finished project photographs showing sliding privacy door to bedroom area
08
Life Size Architecture (trading name of Life Size Architecture ltd) reserves the right to all drawings produced, please see company Terms & Conditions for further details.
Notes Do not scale directly from drawing, all measurements are to be taken from site prior to the commencement of works. It is the contractors responsibility to ensure compliance with Building Regulations.
ght to all drawings produced, please see company Terms & Conditions for further details.
Notes
39
Do not scale directly from drawing, all measurements are to be taken from site prior to the commencement of works. It is the contractors responsibility to ensure compliance with Building Regulations.
Denotes extent of cuts.
18
75
36
75
111
Denotes line of cupboard door.
PROPOSED DOOR HANDLE DETAIL 05 (PLAN) 1:1 @ A1
36
75mm (w) x 36mm (d) cuts into 18mm MDF with 18mm radius corners for storage access. Specialist/contractor to advise.
01273 688 744 studio@lifesizearchitecture.co.uk www.lifesizearchitecture.co.uk
39
Denotes extent of cuts.
date:
revision:
PROPOSED DOOR HANDLE DETAILS
PROPOSED DOOR HANDLE DETAIL 04 (AXO) 1:1 @ A1 18
project no:
19036HS
36
75
drawing no:
024
drawing status:
75
CONSTRUCTION
08
client:
KATRI KAIKKONEN
111
project:
es line of cupboard door.
FLAT 73, 105 HALLAM STREET LONDON
PROPOSED HANDLE DETAIL 05 (PLAN) 1:1 @drawings A1 Cut-out door handle detailDOOR extract from construction package
Finished project photograph showing variations of handle detail
36
(w) x 36mm (d) cuts into m MDF with 18mm radius rners for storage access. alist/contractor to advise.
description:
title:
01273 688 744 studio@lifesizearchitecture.co.uk www.lifesizearchitecture.co.uk
title:
description:
date:
revision:
date:
06/04/21
scale:
1:VAR @ A1
drawn:
JE
checked:
RB
Panel).
18mm MDF with oak veneered cupboard doors. 2mm gaps around doors to carcass. Specialist/contractor to advise.
EXTRACT
USB/Power outlets with flush finished faceplates.
1800
Parkside Halford White 297x97mm tiles gloss finish with 3mm grey coloured grout. Pattern as shown. TBC by client.
Howdens supplied kitchen carcass. Specialist/contractor to advise. 20mm Bianco Assoluto honed counter top.
PULL-OUT DRAWER
OVEN
PULL-OUT DRAWER
FREEZER
PULL-OUT DRAWER
18mm MDF with white lacquered cupboard doors. 2mm gaps around doors to carcass. Specialist/contractor to advise.
PULL-OUT WASTE DRAWER
1200
Concealed hinges to be rebated into door and door lining. Specialist/contractor to advise on specification.
Dotted line denotes drawer side runners. Specialist/contractor to advise.
D/W PULL-OUT DRAWER PULL-OUT DRAWER
50x100mm timber structure. Specialist/contractor to advise. 75mm kick plate depth set back.
Life Size Architecture (trading name of Life Size Architecture ltd) reserves the right to all drawings produced, please see company Terms & Conditions for further details.
PROPOSED SECTION A-A 1:20 @ A1
03 det
Mirrored face to fixed panel. Specialist/contractor to advise. Contractor to install dropped ceilings throughout to house electrics. No insulation. Cornicing removed.
909 Denotes as installed dropped White lacquered face to fixed ceiling panel.system Specialist/contractor to advise.
New ceiling installed to house lighting and electrics. Ensure waterproof coating on 18mm marine plywood. Finished ceiling heights to be level throughout flat.
Concealed hinges to be rebated into door and door lining. Specialist/contractor to advise on specification.
486
30mm frame Crittall-style internal glazing fixed to joinery. Specialist/contractor to advise.
Clear 6 side panel 900mm and In-fold door in clear glass/black. TBC by Contractor.
30mm frame Crittall-style internal glazing with fluted obscure glass. Specialist/contractor to advise.
50
400 100
OG 984
Detachable breakfast bar. Details on Section B-B.
480
25
USB
Boxed out shelf to enclose pipework to bathroom and toilet systern finished with Neutra Greyish tiles to match floor. TBC by Contractor. Flushe 2.0 Framed Cistern - Front Flush with Flushe 2.0 square chrome face plate. Austen Slim white gloss wall mounted WC with Austen white gloss soft close seat & cover.
930
OG
OG
100
1200
USB
1464
2400
Alcove shelf recessed into studded out walls lined with Neutra Greyish tiles to match floor. TBC by Contractor.
200
30mm frame Crittall-style internal glazing with fluted obscure glass. Specialist/contractor to advise.
50
18mm oak veneered MDF with white lacquered cupboard doors to low-level units. 2mm gaps around doors to carcass. Specialist/contractor to advise.
168
18
75mm (w) x 36mm (d) cuts into 18mm plywood with 18mm radius corners for storage access. Specialist/contractor to advise.
Howdens supplied kitchen/storage carcass. Specialist/contractor to advise. 20mm Bianco Assoluto 336 honed counter top.
600
50
Howdens supplied carcass. 18mm oak veneered MDF cupboard doors to mid-level units. 2mm gaps around doors to carcass. Specialist/contractor to advise.
Parkside Halford White 297x97mm tiles gloss finish with 3mm white coloured grout. TBC by client.
20mm quartz detachable breakfast bar with fixed steel leg. Metal dowels at end to slot into holes in joinery ledge. Specialist/contractor to advise. TBC on-site.
600
336
451
30mm frame Crittall-style internal sliding glazed screen with suspended track. Specialist/contractor to advise.
Howdens supplied carcass. 18mm MDF with white lacquered cupboard doors to high-level units. 2mm gaps around doors to carcass. Specialist/contractor to advise.
600
300
18
Shelves fixed to joinery. Specialist/contractor to advise.
600 596
486
30mm frame Crittall-style internal glazing fixed to joinery. Specialist/contractor to advise.
168
204
240
Contractor to install dropped ceilings throughout to house electrics. No insulation. Cornicing removed.
PULL-OUT DRAWER
OG
01273 688 744 studio@lifesizearchitecture.co.uk www.lifesizearchitecture.co.uk
OG
450
50x100mm timber structure. Specialist/contractor to advise. 75mm kick plate depth set back.
50x100mm timber structure. Specialist/contractor to advise. 75mm kick plate depth set back.
Universal 40 900 x 900mm shower tray in grey to match floor tiles and chrome waste. Installed as per manufacturers instructions. Tray recessed into stud wall by 46mm Contractor to confirm on-site.
description:
title:
PROPOSED SEC A-A & B-B
project no:
19036HS
PROPOSED SECTION B-B 1:20 SECTION @ A1 PROPOSED D-D 1:20 @ A1
drawing no
011
03 det
drawing status: PROPOSED BEDROOM HEADBOARD/SHELVING ELEVATION 1:20 @ A1 CONSTRUCTION client:
KATRI KAIKKONEN
project:
FLAT 73, 105 HALLAM STREET LONDON date:
06/04/21
484 18
1018
468
132
336
286
50
286
448
18
444
222 18 456
18
286 900
50
234 18
234
18
482
75 75
1950
462
462
900
18
18
50
18
08
Section and internal elevation showing internal glazing to bathroom from bedroom area extract from construction drawings package
486
Finished project photograph showing internal glazing to bathroom from bedroom area
scale:
1:20 @ A1
Car port East Grinstead, East Sussex Tender £50k
project location work stage budget
Lead Designer
Initial concept design Detailed developed design Planning application Construction drawings package Draft Schedule of Works Tender
role
RIBA Stage 1 Created feasibility study document Presented ideas to clients Discussed procurement strategies with client RIBA Stage 2 Developed design ideas in response to client feedback Finalisation of design brief Consolidation of aesthetic preference Discussed third-party professional consultants RIBA Stage 3 Planning application submission & monitoring Confirmed outline specification for key elements Discussed cost plan opportunity with clients Initiated conversations with prospective contractors RIBA Stage 4 Compiled all necessary specification information Formed set of construction drawings Coordinated & integrated structural design into drawings Prepared Schedule of Works Issued all tender documentation to prospective contractors Value engineer design to fit within final budget
09
Stage 1 concept design models using Rhino and Lumion
3
1
18 18
falls to vegetation barrier
4
5
Min. 50mm181.5
falls to vegetation barrier
9
10
OSB (external/visible): Supply and install 12mm x 2,440mm x 1220mm (cut to size as required) Duraply plywood (or similar approved) to all visible external faces of the structure, inc. posts. Allow for fixing of all curved elements to sub-structure. All fixings to be hidden (where practical). Where screws are used 8 9steel. 10 allow for stainless
18 6
200
18
7
420
5995.2 2
11
13
12
14
Cantilevered beam (timber clad) in elevation 5995.2
18 10
18
18
B
PROPOSED SECTION
14
0mm
Scale 1:10 at A1
200mm
199.5
B 0mm
Scale 1:10 at A1
200mm
400mm
18mm Duraply plywood (or similar approved)
2
18mm Exterior grade plywood
Formwork timber in elevation/section
GRP to be installed over top of parapet and terminated at edge of cover strip.
18
400mm
PROPOSED SECTION
18mm Exterior grade plywood
11
18 18
18mm Duraply plywood (or similar approved) 18mm Duraply plywood (or similar
approved) to internal face of parapet.
Stage 4 section drawing extract from construction drawings Formwork timberpackage in elevation/section Vegetation barrier. Width as per green
18 10
Painting: Canopy soffit to be decorated (before installation of timber battens item 10.01 above). Contractor to fill all surface defects with suitable filler and sand to a smooth surface. Allow for the repair/replacement of all damaged areas to match existing. Fill all surface defects with suitable filler and abrade to a smooth surface. Ensure all timber is properly, thoroughly primed before finish coats applied. Surfaces to receive 1no. mist coat (more if required) and 2no. top coats. Allow for Dulux trade suitable for external use. Colour to Client's Future confirmation.
Gravel border: Contractor to supply and install gravel border to green roof system. 13 This 12 NOTE: 14item may be omitted and undertaken by landscape. Painting: Canopy soffit to be decorated (before installation of timber battens 5995.2 item 10.01 above). Contractor to fill all surface defects with suitable filler and sand to a smooth surface. Allow for the repair/replacement of all damaged areas 13 abrade 11suitable 12 filler and 14 to a to match existing. Fill all surface defects with smooth surface. Ensure all timber is properly, thoroughly primed before finish coats applied. Surfaces to receive 1no. mist coat (more if required) and 2no. top coats. Allow for Dulux trade suitable for external use. Colour to Client's Future confirmation. 238 18 Railings: to supply and install Stainless steel metal railings to rear of 182 Contractor18 canopy structure (above existing retaining wall). Allow for 4no. Stainless steel GRP stainless to be installed top(with of parapet posts 30mm dia. With hozizontally installed steel over cables max. and terminated at edge of cover strip. 99mm vertical gaps between) on tensioners to each cable.
+/- 150mm
214
+/- 150mm
214
538
520
214
195
30
Timber fixing plate. Min 12mm thick on timber packers fixed to I beam.
195
5
3
09
1
0mm
18mm Duraply plywood (or similar approved) 18mm Duraply plywood (or similar approved) 18mm Exterior grade plywood
Formwork timber in elevation/section
Formwork timber in elevation/section
100mm
200mm
James Patterson Architect's Ltd. info@jp-architects.co.uk
Timber packer (depth as required).
DRAFT
/
Proposed sections
50mm x 50mm rev. timber packing.
047-4-201 Scale: Issue date: Drawn by:
06/09/2023 318 JMP
18
247
James Patterson Architect's Ltd. info@jp-architects.co.uk
2 200mm
2
PROPOSED HOPPER SECTION Scale 1:5 at A1
0mm
18
2
100mm
4
200mm
9
DRAFT 18mm exterior grade plywood. 50mm x 50mm timber packing.
Proposed sections
Accoya (or similar approved) timber battens 50mm x 30mm) to underside of canopy structure. In line with angled timbers of curved canopy. Battens full length of canopy u/s.
047-4-201
5
NOTES: 255 All measurements and site conditions are to be checked prior to the preparation of drawings or commencement of works. This drawing belongs to James Patterson Architects Ltd. and is protected by the 318 Copyright, Designs and Patents Act, 1998.
100mm
2. Location of angle timber "fins" in background. V 1. 3. Timber fins in 100mm x 50mm Accoya (or simila ap angles and lengths. Angled junction between "fins sit screwed (stainless steel screws) and glued. Cu 4. Galvanised steel truss (x3no.) to provide additio GRP to be installed over top of parapet 2. Steel trusses bolted to underside of beam B1 to S and terminated at edge of cover strip. 3. calculations. Trusses to be clad in Accoya (or simi an 100mm x 50mm "fin" with truss hidden. sc 5. 18mm Duraply plywood (or similar approved) co 4. Timber packer (depth as required). Laid to fall (min.s 1:60) to vegetation barrier. St 6. GRP to be installed over top of parapet and term ca Timber packer (depth as required). 10 7. Vegetation barrier. Width as per green roof man 5. 18mm exterior grade plywood. Allow for pea gravel (or similar approved) to maxim La of earth/gravel min. 50mm below top of G.R.P. me 6. 8. Biodiverse Substrate, varying depth from min. 1 Ti 9. Bauder Filter Fleece 18mm Duraply plywood (or similar 7. 10. DES40 Drainage Board (Refer to the specifica approved) to all visible external faces of Al the structure. used) above Bauder Protection Mat. of 11. Accoya (or similar approved) timber battens 50 8. 356 x 171 x 51 UB (Galvanised). canopy Steel structure. In line with angled timbers of cur 9. beam B2 bolted to Columns C1. Refer of canopy u/s. 10 to Structural Design for connection 12. 18mm exterior grade plywood. us details. 13. 47mm x 195mm C24 Timber Joists. Centres to 11 14. 18mm exterior grade plywood laid to falls min. ca of Timber fixing plate. Min 12mm thick on 12 timber packers fixed to I beam. 13 14 Timber packer (depth as required).
18
18mm exterior grade plywood.
Accoya (or similar approved) timber battens 50mm x 30mm) to underside of canopy structure. In line with angled High Weald RH19of4ED 247 House, ShipStreet, East Grinstead. timbers curved canopy. Battens full length of canopy u/s. 5 1:10 at A1 255
Project:
30
2
Stage 4 detail drawing extract from construction drawings package 18mm Exterior grade plywood Scale 1:5 at A1
/
Ra ca ADDITIONAL DRAWING NOTES (refer to numbe po 99 1. Curved fascia formed from timber clad - 120mm approved) curved flat bar. 80mm x 10mm steel, fla site welded (or bolted) to beams B3 (x2no.) and in AD Curved timber fascia. 80mm x 100mm steel flat ba
7. Vegetation barrier. Width as per green roof manufacturer recommendation. Timber packer (depth as required). Allow for pea gravel (or similar approved) to maximise drainage to hopper. Top of earth/gravel min. 50mm below top of G.R.P. membrane. 7 8. Biodiverse Substrate, varying depth from min. 100mm to max. 150mm. 200 9. Bauder Filter Fleece 10. DES40 Drainage Board (Refer to the specification for the correct board to be 18mm exterior grade plywood. Gravel used) above Bauder Protection Mat. 11. Accoya (or similar approved) timber battens 50mm x 30mm) to underside of 18mm Duraply plywood (or similar canopy structure. In line with angled timbers 200of curved canopy. Battens full length approved) to all visible external faces of of canopy u/s. Biodiverse Substrate the structure. 12. 18mm exterior grade plywood. Gravel to be confirmed with S.E. 13. 47mm x 195mm C24 Timber Joists. Centres 356firrings. x 171 x 51 UB (Galvanised). Steel 14. 18mm exterior grade plywood laid to falls min. 1:60 of softwood beam B2 bolted to Columns C1. Refer 6 to Structural Design for connection details.
30
30
1
047-4-201
18
1. Curved fascia formed from timber clad - 120mm x 50mm Accoya (or similar approved) curved flat bar. 80mm x 10mm steel, flat bar. Curved in 4 sections and site welded (or bolted) to beams B3 (x2no.) and interim steel trusses. Curved timber fascia. 80mm x 100mm steel flat bar. 2. Location of angle timber "fins" in background. Varying angles. 3. Timber fins in 100mm x 50mm Accoya (or similar approved). Fins at varying angles and lengths. Angled junction between "fins" and curved fascia to be screwed (stainless steel screws) and glued. 4. Galvanised steel truss (x3no.) to provide additional support for curved fascia. 238 of beam B1 to Structural Engineer's design and Steel trusses bolted to underside 18 calculations. Trusses to be clad similar approved) to achieve 182 in Accoya (or18 18 18 100mm x 50mm "fin" with truss hidden. 5. 18mm Duraply plywood (or similar approved) covering over timber GRP form-work. to be installed over top of parapet and terminated Laid to fall (min.s 1:60) to vegetation barrier. 238 at edge of cover strip. 6. GRP to be installed over top of parapet and terminated at edge of cover strip. 182 18 18 18 Timber packer (depth as required).
538
520
538
520
538
520
195
+/- 150mm
195
195 30
2
Proposed sections
171.5 199.5
ADDITIONAL DRAWING NOTES (refer to numbered indicators):
60
Min. 50
60
Min. 50
214
195
30
DRAFT
18
18 10
Railings: Contractor to supply and install Stainless steel metal railings to rear of canopy structure (above existing retaining wall). Allow for 4no. Stainless steel posts 30mm dia. With hozizontally installed stainless steel cables (with max. 99mm vertical gaps between) on tensioners to each cable.
Car Port
60
+/- 150mm
+/- 150mm
214
214
538
520
Min. 50
238
18
181.5
Gravel border: Contractor to supply and install gravel border to green roof system. NOTE: This item may be omitted and undertaken by landscape.
2
ADDITIONAL DRAWING NOTES (refer to numbered indicators): Timber packer (depth as required). roof manufacturer recommendation. Allow for pea gravel (or similar 18 1. Curved fascia formed from timber clad - 120mm x 50mm Accoya (or similar approved) to maximise drainage to 238 182 18 18 18 18 approved) curved flat bar. 80mm x 10mm steel, flat bar. Curved in 4 sections and 18mm exterior grade plywood. hopper. Top of earth/gravel min. 50mm 200 Exploded model 18 18 18 site welded (or bolted) to beams B3 (x2no.) and interim steel trusses. below top182 of G.R.P. membrane. GRP to be installed over top of parapet Duraply plywood (or similar Biodiverse Substrate 18mm Duraply plywood18mm (or similar 18mm80mm Duraply plywood (or similar Curved timber fascia. x 100mm steel flat bar. grade plywood. 18mm exterior and terminated at edge of cover strip. 238 approved) to all visible external faces of Bauder filter fleece against AL150 GRP to be installed over top of parapet approved) to internal face of parapet. to internal of parapet. 1. Steel box section columns installed into foundations (Glulam/CLT alternative). 18 2. Location ofapproved) angle timber "fins" inface background. Varying angles. Gravel the structure. 18mm Duraply plywood (or similar Edge/Drainage trim18or18 as per and terminated at edge of cover strip. 2. Steel beams installed onto columns (Glulam/CLT alternative). 182 18 3. Timber fins in 100mm x 50mm Accoya (or similar approved). Fins at varying approved) to internal face of parapet. manufacturer recommendation. 3. Timber joists and furrings laid between beams.Vegetation barrier. Width as 18mm Duraply plywood similar Vegetation barrier. Width as per green per green angles and lengths. Angled junction between "fins" and curved(or fascia to be 4. Timber sheet cladding fixed to underside of joists. Timber packer (depth as required). 50mm x 50mm arris rail (or as required approved) to all visible external faces of roof manufacturer recommendation. roof manufacturer recommendation. GRP to be installed over top of parapet screwed (stainless steel screws) and glued. Biodiverse Substrate, varying depth 5. Timber sheet lining to form bed for green roof. Lattice network installed to form curved elements. Vegetation barrier. Width as per green 18mm Duraply plywood (or similar 18mm Duraply plywood (or similar the Allow for pea gravelfor(orG.R.P. similarroofing membrane). Allow for peatoto gravel (orstructure. similar and terminated at6.edgeGRP of cover strip. membrane applied 4. Galvanised steel truss (x3no.) provide additional support for curved from min. 100mm to max. 150mm. Timber packer (depth as required). waterproofing to bed. Timber sheet covering lattice. Timber battens laid on top of GRP. roof manufacturer approved) to internal face of parapet. approved) tofascia. internal face of parapet. approved) to maximise drainage to recommendation. approved) to maximise drainage to 7. Bauder WB Native Wildflower Blanket Green Roof system installed into bed gravel border. SteelBiodiverse trusses bolted to underside of beam B1 with to Structural Engineer's design and Additional timber fixing plate (as pea gravel (or similar 18mm exterior grade plywood. hopper. Top of earth/gravelAllow min. for 50mm Top of earth/gravel 356 min.x50mm 171 x 51 UB (Galvanised). Steel 8. Timber sheet cladding applied tocalculations. structure. hopper. DES40 Drainage Board (use spec. required. Min. 12mm thick on Trusses to be clad in Accoya (or similar approved) to achieve approved) to maximise drainage to timber 200 below top of G.R.P. membrane. below of G.R.P. membrane. Vegetation barrier. Width as per green Vegetation barrier. Width as per green beam B2 bolted to Columns C1. Refer 12 9. Timber slats installed to underside of canopy and extending totop curved timber end piece. appropriate for installation). packers fixed to I beam. hopper. Top of earth/gravel min. 50mm 18mm Duraply plywood (or similar Biodiverse Substrate Biodiverse 100mm x 50mm "fin" with truss hidden. Timber packer (depth as required). roof manufacturer recommendation. manufacturerSubstrate recommendation. to Structural Design for roof connection 200 below top of G.R.P. membrane.Allow for pea gravel (or similar approved) to all visible external faces of Bauder filter fleece against AL150 Bauder filter against AL150 5. 18mm Duraply plywood (orfleece similar approved) covering over timber form-work. Allow for pea gravel (or similar details. Biodiverse Substrate Gravel the structure. 18mm exterior grade plywood. Edge/Drainage trim orxas perx 51 UB (Galvanised). Edge/Drainage or as per Laid to fall (min.s 1:60) to vegetation trim barrier. approved) to maximise drainage to approved) to maximise drainage to 18mm exterior grade plywood laid to 356 171 Steel Bauder filter fleece against AL150 manufacturer recommendation. manufacturer recommendation. 18mm exterior grade plywood. hopper. TopRefer of earth/gravel min. 50mm of earth/gravel min. 50mm falls min. 1:60 of softwood firrings. 6. GRP to be installed over top of parapet and terminated athopper. edge ofTop cover strip. beam B2 bolted trim to Columns Gravel Edge/Drainage or as perC1. 200 below top of G.R.P. membrane. below top of G.R.P. membrane. to Structuralrecommendation. Design for connection Timber packer (depth as required). 50mm x 50mm arris rail (or as required 47mm x 195mm C24 Timber Joists. Timberdepth fixing plate. Min 12mm thick on Biodiverse Substrate, manufacturer varying Biodiverse Substrate, varying 18mm Duraply plywood (or similar Biodiverse Substrate Duraply plywood (or similar details.depth for G.R.P. roofing18mm membrane). 7. Vegetation barrier. Width as pertogreen roof manufacturer recommendation. Centres to be confirmed with S.E. timber packers fixed to I beam. from min. 100mm to max. 150mm. from min. 100mm max. 150mm. approved) to all visible externalapproved) faces of to all visible external faces of Bauder filter fleece against AL150 Bauder filter fleece against AL150 Biodiverse Substrate, varyingasdepth Timber packer (depth required). Allow for pea gravel (or similar approved) to maximise drainage to hopper. Top Gravel the structure. Additional timber fixing plate (as the structure. Edge/Drainage trim or as per Edge/Drainage trim or as per Exterior grade plywood to form hopper. from min. of earth/gravel min. 50mm below Board top ofTimber G.R.P. membrane. DES40 Drainage Board (use100mm spec. to max. 150mm. DES40 Drainage (use spec. packer (depth as required). required. Min. 12mm thick on timber manufacturer recommendation. manufacturer recommendation. Timber fixing plate. Min. 12mm thick on 12 12 8. Biodiverse Substrate, varying depth from min. 100mm to max. 150mm. appropriate for installation). appropriate for installation). Apply G.R.P. to internal faces of hopper. packers fixed to I beam. 356 x 171 x 51 UB (Galvanised). Steel timber packers fixed to Ispec. beam. 50mm x 50mm arris rail (or as required DES40 Drainage Board (use and outlet to RWDP. Biodiverse Biodiverse Substrate, varying depth 9. Bauder Filter Fleece beam B2 bolted to Columns C1. 12 Substrate, varying depth forRefer G.R.P. roofing membrane). appropriate for installation). from min. 100mm to max. 150mm. from min. 10. DES40 Drainage Board (Refer the specification for the correct board100mm to be to max. 150mm. pea gravel (or similar approved) to x 171 x 51 UBto(Galvanised). Structural Design 18mm exterior grade to plywood laid to 356 Steelfor connection Apply Glass Reinforced Plastic roof Additional timber fixing plate (as used) above Bauder Protection Mat. maximise drainage from hopper. details. falls min. 1:60 of softwood firrings. beam B2 bolted to Columns C1. Refer covering (or similar appropriate lining to DES40 DES40 Drainage required. Min. 12mm thick on timber 18mm exterior grade plywood laid to Drainage Board (use spec. 11. Accoya (or similar approved) timber battens 50mm x 30mm) to underside of Board (use spec. to Structural Design for connection 47mm x 195mm timber trimmer. green roof bed)falls by hand lay-up. 50mm x 50mm timber firrings. packing. appropriate for installation). 12 50mm x 50mm timber packing. appropriate for installation). 12 47mm x 195mm C24 Timber packers fixed to I beam. min. 1:60 of softwood canopy structure. In line with angled timbersJoists. of curved canopy. Battens full length 220 details. Centres to be confirmed with S.E. 12 of canopy u/s. 47mm18mm x 195mm C24 grade Timberplywood. Joists. Timber fixing plate. Min 12mm thick on exterior 18mm exterior grade plywood. Timber packer (depth as required). Exteriorgrade gradeplywood. plywood to form hopper. 18mm exterior grade plywood laid to Centres to be confirmed withApply S.E. Glass Reinforced Plastic roof 12. 18mm exterior timber packers fixed to I beam.356 x 171 x 51 UB (Galvanised). Steel 18 falls min. beam B2 bolted to Columns C1. Refer Timber fixing plate. Min. 12mm thick on 13. 47mmApply x 195mm C24 Centres be confirmed withtimber S.E.1:60 of softwood firrings. covering similar appropriate lining to Accoya approved) timber (ortosimilar approved) Exterior grade plywood to form hopper.(or G.R.P. toTimber internalJoists. facesAccoya of hopper. 18mm exterior grade plywood laid(or tosimilar to Structural Design for connection timber packers fixed to I beam. green roofofbed) by hand lay-up. 14. 18mm exterior grade plywood laid to falls min. 1:60 of softwood firrings. Timber packer (depth as required). Plastic (or cast iron) gulley cover above battens 50mm x 30mm) to underside battens 50mm x 30mm) to underside of C24 Timber Joists. 47mm x 195mm and outlet to RWDP. falls min. 1:60 of softwood firrings. 220 details. Apply G.R.P. to internal faces of hopper. opening to RWDP. Ensure opening canopy structure. In line with angled canopy structure. In line with angled Centres to be confirmed with S.E. pea gravel (or similar approved) to outletcanopy. to RWDP. 47mm x 195mm C24 Timber Joists. Timber packer (depth as required). sufficient to allow water through but not 247 timbers ofand curved Battens full timbers of curved canopy. Battens full maximise drainage from hopper. Exterior grade plywood to form hopper. Centres 5to be confirmed with(or S.E. gravel. length of canopy u/s. length of canopy u/s. pea gravel similar approved) to 5 255 Timber fixing plate. Min. 12mm thick on 47mm x 195mm timber trimmer. maximise drainage from hopper. 50mm x 50mm timber packing. Timber to timber joist hanger. Apply G.R.P. to internal faces of hopper. 18mm exterior grade plywood laid to timber packers fixed to I beam. Connection to below ground drainage: and outlet to RWDP. 318 falls min. 1:60 of softwood firrings. 47mm x 195mm 12 timber trimmer. 12 50mm x 50mm timber packing. 18mm exterior grade plywood. Allow for the connection of new surface pea gravel (or similar approved) to 47mm x 195mm C24 Timber Joists. 18 18 water drainage to existing sewer 18 18 12 maximise drainage from hopper. 18mm exterior grade plywood. Centres to be confirmed with S.E. system. Existing Inspection Chamber Accoya (or similar approved) timber 18 47mm x 195mm timber trimmer. located on driveway to front of property. Plastic (or cast iron) gulley cover above 50mm x 50mm timber packing. Timber to timber joist hanger. battens 50mm x 30mm) to underside of (or similar Contractor to assess condition of opening to RWDP. Ensure opening canopy structure. Accoya In line with angled approved) timber Plastic (or cast iron) gulley cover above 12 12 x 30mm) to underside of existing below ground drainage timbers and 18mm exterior grade plywood. sufficient to allow water through but not 247 of curved battens canopy.50mm Battens full opening to RWDP. Ensure opening canopy structure. In line with angled connections for suitability gravel. 18 18 length of canopy u/s. 5 of connection sufficient to allow water through but not 255 timbers of curved canopy. Battens full (or similar approved) timber to new.247 All connection works to be Accoya gravel. length of canopy u/s. approved by relevant Water Authority 5 Plastic (or cast iron) gulley cover above Connection to below ground drainage: battens 50mm x 30mm) to underside of 255 318 (as required) and Part H of the Building rev. opening to RWDP. Ensure opening Allow for the connection of new surface canopy structure. In line with angled Connection to below ground drainage: Regulations/ Officers 247 318 Building Control 18 sufficient to allow water through but not water drainage to existing sewer timbers of curved canopy. Battens full Allow for the connection of new surface approval. PROPOSED HOPPER SECTION gravel. system. Existing Inspection Chamber length of canopy u/s. 5 18 255 water drainage to existing sewer located on driveway to front of property. 0mm 100mm 200mm Scale 1:5 at A1 system. Existing Inspection Chamber Contractor to assess condition of Connection to below ground drainage: 318 located on driveway to front of property. existing below ground drainage and Allow for the connection of new surface Contractor to assess condition of 18 connections for suitability of connection water drainage to existing sewer Project: High Weald House, ShipStreet, RH19 4ED existing below ground drainage and to new. All connection works to beEast Grinstead. system. Existing Inspection Chamber 18mm Exterior grade plywood connections for suitability of connection approved by relevant Water Authority located on driveway to front of property. 1:10 at A1 Scale: to new. All connection works to be (as required) and Part H of the Building Contractor to assess condition of approved by relevant Water Authority Issue date: Regulations/ 06/09/2023 18mm Duraply plywood (or similar approved) Building Control Officers existing below ground drainage and (as required) and Part H of the Building approval. connections for suitability of connection PROPOSED HOPPER SECTION PROPOSED HOPPER SECTION Drawn by: JMP Regulations/ Building Control Officers to new. All connection works to be approval. PROPOSED0mm HOPPER SECTION 0mm 100mm 200mm Scale 1:5 at A1 Scale 1:5 at 8 Formwork timber in elevation/section approved byA1relevant Water Authority NOTES: (as required) and All measurements and site conditions are to be checked prior to the preparation of drawings or Part H of the Building 0mm 100mm 200mm Scale 1:5 at A1 Regulations/ Building Officers commencement of works. This drawing belongs to James Patterson Architects Ltd. and is protected byControl the approval. Copyright, Designs and Patents Act, 1998. PROPOSED HOPPER SECTION 18mm Exterior grade plywood 18mm Exterior grade plywood Timber packer (depth as required).
237.5
Green roof: Contractor to supply and install BauderGREEN green roof system up to substrate in bed created by secondary structure. Vegetation to be supplied and installed by others. Build up as per following specification: - 150mm (min. 125mm) BauderGREEN SUB-BM UK substrate; - BauderGREEN FV 125 100 filtration layer; - 40mm BauderGREEN DSE 40 drainage layer; - BauderGREEN FSM 600 protection layer.
60
13
Min. 50
12
Min. 2,050mm a.f.f.l.
11
2
171.5
3034
171.5 Green roof: Contractor to supply and install BauderGREEN green roof system up to substrate in bed created by secondary structure. Vegetation199.5 to be supplied18 and installed by others. Build up as per following specification: - 150mm (min. 125mm) BauderGREEN SUB-BM UK substrate; - BauderGREEN FV 125 100 filtration layer; - 40mm BauderGREEN DSE 40 drainage layer; - BauderGREEN FSM 600 protection layer.
418
538
Cantilevered beam (timber clad) in elevation
3396
Green roof bed/tray w/proofing: Apply Glass Reinforced Plastic roof covering (or similar appropriate lining to green roof bed) by hand lay-up. Min. overlap of 50-75mm between mats. Note: Boards laid to falls towards down-pipe adjacent to post.. Min. Falls of 1:60. With standard square edge boards allow 3mm gaps between adjoining boards for expansion. GRP to be installed over and terminated at edge of cover strip. If necessary overlap cover strip/trim by 50-75mm and apply Polyurethane Adhesive to seal. Cover strip/trim and all junctions between OSB3 boards to be fibreglass bandaged/taped.
Min. 50mm
80
2 Curved timber in elevation
120
8 800 237.5
10
80
Curved timber in elevation
7200
6
5 varies
50
30344 varies
10
Green roof bed/tray w/proofing: Apply Glass Reinforced Plastic roof covering (or similar appropriate lining to green roof bed) by hand lay-up. Min. overlap 200 of 50-75mm between mats. Note: Boards laid to falls towards down-pipe adjacent to post.. Min. Falls of 1:60. With standard square edge boards allow 3mm gaps between adjoining boards for expansion. GRP to be installed over and 18 18 terminated at edge of cover strip. If necessary overlap cover strip/trim by 50-75mm and apply Polyurethane Adhesive to seal. Cover strip/trim and all junctions between OSB3 boards to be fibreglass bandaged/taped.
518
3
1
200
420
Refer to detail 2 for upstand design
800
re bolts to be 8.8 bolts unless otherwise stated by Str steelwork to be galvanised. Steelwork connections St 18 and supplied by the Structural Engineer/Steel Fab St Structural Engineer before fabrication. All setting o te any discrepancy reported1to the Structural Enginee bo ste Roof structure: Supply and install 47mm x 195mm an steels B1 and B2 at min. 400mm centres. Allow fo St 1:60 to column C1 (adjacent to existing steps). an
OSB (internal/non-visible): Supply and install 11m Ro to size as required) OSB 3 boards to form bed/tray ste membrane. Allow for all associated timber-framing 1:6 including curved elements outside of steel beams elsewhere). Allow for forming hopper above rwdp OS to OSB (external/visible): Supply and install 12mm x me Refer to detail 2 for upstand design size as required) Duraply plywood (or similar appr inc faces of the structure, inc. posts. Allow for fixing o els sub-structure. All fixings to be hidden (where pract 200 allow for stainless steel. OS 237.5 siz Green18 roof bed/tray w/proofing: Apply Glass Reinf 18 18 fa similar appropriate lining to green roof bed) by han 181.5 su 18 50-75mm between mats. Note: Boards laid to falls all to post.. Min. Falls of 1:60. With standard square e between adjoining boards for expansion. GRP to b Gr terminated at edge of cover strip. If necessary ove sim 50-75mm and apply Polyurethane Adhesive to sea 50 junctions between OSB3 boards to be fibreglass b to be Green roof: Contractor to supply and install Baude te to substrate in bed created by secondary structure 50 and installed by others. Build up as per following s jun - 150mm (min. 125mm) BauderGREEN SUB-BM U - BauderGREEN FV 125 100 filtration layer; Gr - 40mm BauderGREEN DSE 40 drainage layer; to - BauderGREEN FSM 600 protection layer. an -1 Gravel border: Contractor to supply and install gra -B system. NOTE: This item may be omitted and und 2 -4 -B Painting: Canopy soffit to be decorated (before ins 18 item 10.01 above). Contractor to fill all surface def 10 Gr sand to a smooth surface. Allow for the repair/repl sy 2 defects with suita 171.5 to match existing. Fill all surface smooth 18surface. Ensure all timber is properly, thor Pa 199.5 coats applied. Surfaces to receive 1no. mist coat ( ite coats. Allow for Dulux trade suitable for external u sa confirmation. to sm Railings: Contractor to supply and install Stainless co canopy structure (above existing retaining wall). A co posts 30mm dia. With hozizontally installed stainle co 99mm vertical gaps between) on tensioners to eac
50
Formwork timber in elevation/section
varies 3396
520
varies
50
Min. 50mm
OSB (external/visible): Supply and install 12mm x 2,440mm x 1220mm (cut to size as required) Duraply plywood (or similar approved) to all visible external faces of the structure, inc. posts. Allow for fixing of all curved elements to sub-structure. All fixings to be hidden (where practical). Where screws are used allow for stainless steel. Refer to detail 2 for upstand design
518
18mm Duraply plywood (or similar approved)
420
falls to vegetation barrier
18mm Exterior grade plywood
520
10
Min. 50
9
318
including curved elements outside of steel beams (external cladding to be costed elsewhere). Allow for forming hopper above rwdp within base of tray.
+/- 150mm
Formwork timber in elevation/section 8
7
Floor level (finished): +0,000
50
6
3034
420
3396
538
400mm
18mm Duraply plywood (or similar approved)
200
199.5
538
200mm
Min. 50
0mm
Scale 1:10 at A1
30
318
OSB (internal/non-visible): Supply and install 11mm x 2,440mm x 1220mm (cut 90mm dia. Rain water down-pipe in to size as required) OSB 3 boards to form bed/tray below water-proofing stainless steel (t.b.c.). membrane. Allow for all associated timber-framing for the forming of the bed/tray,
60
A
PROPOSED SECTION
18mm Exterior grade plywood
1:60 to column C1 (adjacent to existing steps).
Structural Engineer's design and temporary support during installation. All steelwork to be grade S355 and all calculations for connection details. bolts to be 8.8 bolts unless otherwise stated by Structural Engineer. All external steelwork to be galvanised. Steelwork connections and splices to be designed and supplied by the Structural Engineer/Steel Fabricator Refer to detail 2and for agreed upstandwith design Structural Engineer before fabrication. All setting out to be confirmed on site and any discrepancy reported to the Structural Engineer and Architect. 200 Roof structure: Supply and install 47mm x 195mm C24 timber joists between 237.5 steels B1 and B2 at min. 400mm centres. Allow for firrings above joists at falls of 1:60 to column C1 (adjacent to existing steps). 18 18 18 181.5 18 OSB (internal/non-visible): Supply and install 11mm x 2,440mm x 1220mm (cut to size as required) OSB 3 boards to form bed/tray below water-proofing membrane. Allow for all associated timber-framing for the forming 3396 of the bed/tray, including curved elements outside of steel beams (external cladding to be costed 3034 elsewhere). Allow for forming hopper above rwdp within base of tray.
1
318
60
stainless steel (t.b.c.).
400mm
518
200mm
518
Min. 2,050mm a.f.f.l.
inished): +0,000800
0mm
Scale 1:10 at A1
High Weald House, ShipStreet,
Scale:
1:10 at A1
Issue date:
06/09/2023 -
0
Drawn by:
JMP
Pr
Sc NOTES: All measurements and site conditions are to be checked prior t Iss commencement of works. This drawing belongs to James Patt Copyright, Designs and Patents Act, 1998.
Dr
James Patterson Architect's Ltd. info@jp-architects.co.uk
18mm Duraply plywood (or similar approved)
Formwork timber in elevation/section
Formwork timber in elevation/section
1
Stage 4 exploded model showing layers of construction extract from detailed design document
NO All co Co
Ja inf
18mm Exterior grade plywood
18mm Duraply plywood (or similar approved)
P
Project:
18mm Duraply plywood (or similar approved)
Formwork timber in elevation/section
D
James Patterson Architects info@jp-architects.co.uk 01273 443978
09
Final design night time visualisation showing extent of lighting
Rear extension Hove, East Sussex On-site £150k
project location work stage budget
Lead Designer
role
Planning application Construction drawings package Draft Schedule of Works Tender and negotiations On-site management
Ridge level: +10,600
RIBA Stage 3 Developed concept design into planning application drawings Confirmed outline specification for key elements Planning submission & monitoring Discussed cost plan opportunity with clients Initiated conversations with prospective contractors
Ridge level: +10,600
Slate tiles
Slate tiles Eaves level: +7,235
RIBA Stage 4 Compiled all necessary specification information Formed comprehensive set of technical design drawings Coordinated & integrated structural design into drawings Prepared Schedule of Works Issued all tender documentation to prospective contractors Compare returned tenders Draft JCT Minor Works 2016 building contract
Eaves level: +6,800
Loft level: +7,060 220
First floor ceiling: +6,840
Eaves level: +6,800
Brick
Render detail to cornice to match design of decorative coping on front elevation. First floor FFL: +3,640 Render
290
290
First floor FFL: +3,640
Ground floor ceiling: +3,350
First floor ceiling: +6,840
3420
3420
220
Loft level: +7,060
Approx. outline of neighbouring structure
Render
Ground floor ceiling: +3,350
Render detail above doors. 730
Double doors
Single storey rear extension extending 3,250mm from furthest rear wall. Masonry construction in materials to match existing.
Existing terrace and brickwork posts to be demolished. Planting to create screening between properties.
Steel framed, thermally broken double doors. See elevations for heights. Black frames with double glazed inserts.
Planting
Ground floor FFL: +0,000
Planting
External ground level: -0,550
850
Timber slatted fence screening to obstruct view back towards neighbour.
3350
Brick
4729
Double doors
850
550
Brick
Boundary wall detail to be confirmed and coordinated with Party Wall Surveyor.
Render
Ground floor FFL: +0,000
Double doors
3879
RIBA Stage 5 Site inspections & build quality assurance Response to site queries Monitor progress according to construction programme
1800
3350
1000 Existing conservatory structure to be demolished.
External ground level: -0,850 455
1
PROPOSED FRONT ELEVATION Scale 1:50 at A1
0mm
10
1,000mm
2,000mm
8315
PROPOSED REAR ELEVATION Rear elevation drawing extract from planning submission Scale 1:50 at A1
0mm
3 1,000mm
2,000mm
D C B A / Rev:
03.03.22
Planning amendments
JDE
08.11.21
Issued to client for comment
JMP
04.11.21
Issued to client for comment
JMP
21.10.21
Issued to client for comment
JMP
08.10.21
Issued to client for comment
Date:
Notes:
JMP Drawn by:
19 DENMARK VILLAS HOVE
030-3-101-D PROPOSED ELEVATIONS SCALE: 1:50 AT A1 DRAWN BY: JMP STATUS:
FOR PLANNING
Stage 4 model following planning approval
NOTES: Do not scale from this drawing, use given dimensions. All measurements and site conditions are to be checked prior to the preparation of drawings or commencement of works. This drawing belongs to James Patterson Architects Ltd. and is protected by the Copyright, Designs and Patents Act, 1998.
980.0
8030.0
DRAWING NOTES: Numbered key: 1. New foundations Foundations to structural engineer's detail/specification. Mass concrete trench fill foundations. Depth to suit ground conditions/proximity of trees. Taken min. 150mm into sound, undisturbed stratum or min. 600mm below any roots. All foundations to have a minimum depth of 1,000mm below natural ground level. Depths to be confirmed on site with Building Control officer. Width of foundation to be min. 450mm as per structural engineer's design/specification. All foundations to be GEN 3 concrete. 2. New floor - 0.18W/m2K max U-value: 25mm timber boards and slip mat 75mm concrete screed with 25mm thick insulated separating layer to perimeter of entire screed (Celotex GA4000 or equal PIR insulation) 90mm Celotex GA4000 (or equal approved) on 1,200 gauge polythene damp proof membrane (dressed up inner wall leaf and lapped over top of blockwork) 150mm beam and block floor designed by specialist with 100mm deep dense block infill. Min. 250mm ventilated void. 3. External walls (extension) - 0.18W/m2K max U-value: 102.5mm brick 100mm cavity comprising 50mm clear cavity with 85mm Celotex GA4000 (or equal approved) Ancon ST1 225mm wall ties (or equal approved) in staggered pattern 100mm Thermalite Turbo block (or equal approved) 12.5mm Gyproc Wallboard plasterboard Skim coat and wall finish 4. New extension flat roof - 0.15W/m2K max U-value: GRP waterproofing 18mm plywood 150mm Celotex GA400 or equal DuPont Tyvek Supro Plus breather membrane or equal approved New 47mm x 170mm C24 timber rafters to structural engineer's spec 12.5mm laminated plasterboard (with vapour barrier) Skim coat and ceiling finish 5. Internal stud walls: 12.5mm Gyproc Wallboard plasterboard 100mm timber studs 600mm c/c with 100mm Celotex GA4000 or equal between 12.5mm Gyproc Wallboard plasterboard Skim coat and wall finish
030-4-102 Property boundary
250.0 250.0 250.0
1000.0
250.0
250.0
250.0
250.0
A
1 750.0
Property boundary
030-4-201
3085.0
030-4-202
3
1585.0
800.0
030-4-202
3
530.0
Timber slatted fence screening to obstruct view back towards neighbour
1800.0
8315.0 890.0
1585.0
890.0
1585.0
890.0
1585.0
890.0 1000.0
TERRACE
L1 Catnic CG type standard duty cavity wall lintel
rwdp
Roof-light in roof of extension structure above.
030-4-202
Single storey rear extension extending 3,262.5mm from furthest rear wall. Masonry construction in materials to match existing.
Roof-light above
1
3
D01 Steel framed, thermally broken double doors. See elevations for heights. Black frames with double glazed inserts.
D02
D03
L1 Catnic CG type standard duty cavity wall lintel
L1 Catnic CG type standard duty cavity wall lintel
Roof-light above
Roof-light above
620.0
270.0
730.0
rwdp Approx. outline of neighbouring structure
1
030-4-202
AREA = 16.8m²
New free-standing unit to kitchen specialist's design (shown indicatively). Layout to be coordinated with mechanical and electrical requirements. 3262.5
Roof-light in roof of extension structure above.
DINING
2
AREA = 25.4m² FFL - U/C = 3,350mm
3837.5
Floor tiles (spec tbc) to be laid with 3mm grout and 10mm metal trim to timber floor edge.
G/05
B1 (inner) and B1 (outer) bolted to each other using M12 (8.8) bolts at max. 400mm c/c. Min. 150mm end bearings onto new engineering brick pier.
Brick slips installed to internal wall face. This wall only. Specification TBC. B1 (outer) 203 x 102 x 23 UB
Existing beam B1 (inner) 203 x 133 x 30 UB
Island
G/04
KITCHEN
AREA = 12.9m² FFL - U/C = 3,350mm
No proposed works in area other than making good minor affected areas
3021.0
New kitchen to specialist's design (shown indicatively). Layout to be coordinated with mechanical and electrical requirements.
2544.0
Floor tiles (spec tbc) to be laid with 3mm grout and 10mm metal trim to timber floor edge.
Rebuild pier as min. 125 x 215 mm engineering brick pier in 1:1:6 mortar as per Structural Engineer's design and calculations. To be absorbed within kitchen joinery.
030-4-106
1
This drawing forms part of the 'Contract Documents' referred to in the -Contract' between Employer and Contractor.
G/06
860.0
D/W 640.0
Steel frame side-hung door, full-height with glazing. Approx. 625 x 3150mm. Fixed steel frame glazing side panel above counter top. Approx. 625 x 2250mm.
640.0
150.0
964.0
SITTING ROOM
1167.5 817.0
1167.5
361.0 132.5
AREA = 18.7m² FFL - U/C = 3,350mm
815.0
Project reference: 030-19 Denmark Villas Initialed (Employer): Initialed (Contractor):
132.5
D06
F/F
449.0
Floor tiles (spec tbc) to be laid with 3mm grout and 10mm metal trim to timber floor edge.
FD30
W01
2 3110.0
D05
New bespoke joinery unit to house fridge-freezer and storage. See drawing 030-4-106 with further details to follow.
5
L2 100mm (w) x 110mm (d) Naylor S4 prestressed concrete beam lintel
030-4-103
4
030-4-103
D04
Rev:
Date:
Notes:
Drawn by:
19 DENMARK VILLAS HOVE BN3 3TD
G/02
PANTRY
G/03
AREA = 3.9m² FFL - U/C = 3,350mm
WC
New door to guest w.c. within existing wall as per structural engineer lintel design. Door to match existing.
030-4-001
AREA = 2.8m² FFL - U/C = 3,350mm
GROUND FLOOR GA PLAN Concrete beam lintel min. 150mm end bearings onto sound existing masonry.
10
SCALE: 1:25 @ A1 DRAWN BY: JE STATUS:
Wall to form pantry and guest w.c. Insulated for acoustic performance. Provide 10 thk sheathing ply to both sides for durability.
NOTES:
1
A
030-4-201
New built-in-joinery to Pantry. Detailed drawings to follow.
FOR COMMENT
G/03 030-4-004
G/01
ENTRANCE
2
AREA = 12.0m² FFL - U/C = 3,350mm
N
G/07
LIVING ROOM
PROPOSED GROUND FLOOR PLAN Scale 1:25 at A1
0mm
500mm
1,000mm
Do not scale from this drawing, use given dimensions. All measurements and site conditions are to be checked prior to the preparation of drawings or commencement of works. This drawing belongs to James Patterson Architects Ltd. and is protected by the Copyright, Designs and Patents Act, 1998.
AREA = 19.2m² FFL - U/C = 3,350mm
3
Stage 4 general arrangement plan extract from construction drawings package
Existing wall fill
Site photos of ongoing construction
LDING CONTRACT
6.02
New beam and block floor build-up Terrace: Contractor to supply and install new beam and block floor system to the rear extension structure (G/04 Kitchen and G/05 Dining area) as per Structural Engineer’s design and specification. 150mm deep prestressed concrete beam and block floor designed by specialist with 100mm deep dense block infill as required by Structural Engineer over min. 250mm ventilated void. Supply and install 50mm reinforced concrete screed (to satisfy BS 8204) on separating layer above insulation. Depth of floor build-up to allow for proposed floor finish (tiles)to finish at the same level as new G/04 Kitchen and G/05 Dining floor. Allow for connection to new extension.
£4,401.76
6.06
£2,387.05
10
4
3
2 030-4-202
£880.00
G/05
DINING Timber slatted fence screening.
Note: Installation of cavity trays to be confirmed with Building Control and once exploratory works have been carried out to establish extent of cavity walls.
6.03
Extension external walls: External masonry and block cavity wall to rear extension. Contractor to form new external walls to rear extension (forming openings for Extract from Schedule of Works externally opening doors) as per Architect's drawings and Structural Engineer specification: - External masonry leaf brick-work to match existing (allow for London Stock brick); - 135mm cavity comprising 50mm clear cavity and; - 85mm Celotex CW4000 (or equal performing). - Ancon ST1 225mm wall ties (or equal) installed in staggered pattern. - Internal blockwork leaf min. 3.6N blocks. - 12.5mm Gyproc Wallboard plasterboard. - Skimmed and decorated. - Weepholes installed at 450mm centres. - Allow for 135mm cavity closers. - All external walls to achieve a U-value of 0.18 W/m2k or better. 6.04 Terrace walls: External masonry and block cavity wall to rear terrace. Contractor to form new walls to rear terrace as per Architect's drawings and Structural Engineer specification: - External masonry leaf brick-work to match existing (allow for London Stock brick); - 100mm cavity (to rear terrace wall only, single skin brickwork to sides); - Ancon ST1 225mm wall ties (or equal) installed in staggered pattern. - Internal blockwork leaf min. 3.6N blocks. 6.05 Cavity trays (as required): Contractor to supply and install new Type E Cavitrays for insertion into existing masonry skin by Cavity Trays of Yeovil Somerset or equal performing cavity tray design (to be approved by Building Control and/or Architect). Lap up waterproofing membrane through external wall leaf and beneath cavity tray.
Ground floor ceiling: +3,350
Structural steel support: Contractor to supply and install all new structural steel support as per Structural Engineer’s design and calculations. Refer to DCS Structural Design drawing e22020-001 and associated structural calculations. Including (but not limited to) new inner and outer beams B1 bolted to each other using M12 (8.8) bolts at max. 400mm c/c (as per e22020/001) to support existing rear wall above G/04 Kitchen (including associated works). All new lintels for internal and external door openings. Allow for all padstones, connections and temporary support during installation. Unless noted otherwise, all steels are to be lined with one layer of 15mm Gyproc Fireline plasterboard or 2 layers of 12.5mm Gyproc Wallboard plasterboard with taped joints and a plaster skim coat to allow 30 mins fire protection and to BS5492 1990 Code of Practice for Internal Plastering. Plasterboard price included in item 7.01.
£1,859.41
Item 6 SUB-TOTAL:
£40,389.85
2 Ground floor FFL: +0,000 Beam and block terrace floor with 50mm screed and paving laid to min. 1:80 falls.
Ventilation
Ventilated void Ventilation
150.0 min. 250
2016
First floor FFL: +3,640
75.0
6.05
£3,335.13
3250.0
1800.0
New beam and block floor build-up G/04 Kitchen & G/05 Dining: Contractor to supply and install new beam and block floor system to the rear extension structure (G/04 Kitchen and G/05 Dining area) as per Structural Engineer’s design and specification. 150mm deep prestressed concrete beam and block floor designed by specialist with 100mm deep dense block infill as required by Structural Engineer over min. 250mm ventilated void. Supply and install 90mm Celotex GA4000 or equal PIR insulation on 1,200 gauge polythene damp proof membrane (dressed up inner wall leaf and lapped over top of blockwork) with 25mm thick insulated separating layer to perimeter of entire extension. Supply and install 75mm reinforced concrete screed (to satisfy BS 8204) with underfloor heating system installed to manufacturer's instructions (underfloor heating system cost to be included in item 13.03 below) on © The Joint Contracts Tribunal Limited 2016 separating layer above insulation. Depth of floor build-up to allow for proposed floor finish (tiles)to finish at the same level as the existing. Condition of remaining buildup/substrate to be assessed pre-removal and concerns to be discussed with architect/client. Allow for connection to existing floor.
Sandstone coping detail per Detail 2 on drawing 030-4-202.
90.0
6.01
Terrace walls: External masonry and block cavity wall to rear terrace. Contractor to form new walls to rear terrace as per Architect's drawings and Structural Engineer specification: - External masonry leaf brick-work to match existing (allow for London Stock brick); - 100mm cavity (to rear terrace wall only, single skin brickwork to sides); - Ancon ST1 225mm wall ties (or equal) installed in staggered pattern. - Internal blockwork leaf min. 3.6N blocks. Cavity trays (as required): Contractor to supply and install new Type E Cavitrays for insertion into existing masonry skin by Cavity Trays of Yeovil Somerset or equal performing cavity tray design (to be approved by Building Control and/or Architect). Lap up waterproofing membrane through external wall leaf and beneath cavity tray. Cavity trays to be installed at all junctions where existing cavity walls are breached with new structure (i.e. above beam B1).
3927.0
6.04
2835.0
£6,782.17
£20,744.33
900.0
New foundations: Excavate and cart away removed material to form new foundations for the proposed single storey rear extension and raised terrace structures. Foundation depth and width to comply with Part A (2E3/2E4) of the National Building Regulations. Allow for 450mm wide trench with a depth of min. 1,000mm below ground level. Allow for all steel reinforcement (if required) and concrete infill as per Structural Engineer’s specification and bending schedules. Also allow for connection to existing ground floor foundations. Where possible excavated materials to be re-used on site.
First floor ceiling: +6,840
External ground level: -0,850 min. 150
6.00
Loft level: +7,060
min. 150
Note: The Contractor shall be responsible for the installation of structural support as shown on the Structural Engineer's drawings and calculations (and Architect's drawings where applicable). Works to include all associated building works and making good. All steelwork to be protected with ‘Fireline’ plasterboard and/or intumescent paint to satisfy Building Control Requirements. Engineer to be consulted regarding connections/tying into existing structure. Lintels, where specified (above windows etc.) are included within the wall build up specification below.
Extension external walls: External masonry and block cavity wall to rear extension. Contractor to form new external walls to rear extension (forming openings for externally opening doors) as per Architect's drawings and Structural Engineer specification: - External masonry leaf brick-work to match existing (allow for London Stock brick); - 135mm cavity comprising 50mm clear cavity and; - 85mm Celotex CW4000 (or equal performing). - Ancon ST1 225mm wall ties (or equal) installed in staggered pattern. - Internal blockwork leaf min. 3.6N blocks. - 12.5mm Gyproc Wallboard plasterboard. - Skimmed and decorated. - Weepholes installed at 450mm centres. - Allow for 135mm cavity closers. - All external walls to achieve a U-value of 0.18 W/m2k or better.
min. 1000
© The Joint Contracts Tribunal Limited 2016
min. 1000
Amended from published version. Comparison must be provided.
6.03
£2,387.05
4752.0
2016
MINOR WORKS BUILDING CONTRACT work/primary structure Item: 6. Ground
New beam and block floor build-up Terrace: Contractor to supply and install new beam and block floor system to the rear extension structure (G/04 Kitchen and G/05 Dining area) as per Structural Engineer’s design and specification. 150mm deep prestressed concrete beam and block floor designed by specialist with 100mm deep dense block infill as required by Structural Engineer over min. 250mm ventilated void. Supply and install 50mm reinforced concrete screed (to satisfy BS 8204) on separating layer above insulation. Depth of floor build-up to allow for proposed floor finish (tiles)to finish at the same level as new G/04 Kitchen and G/05 Dining floor. Allow for connection to new extension.
min. 250
6.02
220.0
MWD 2016
Minor Works Building Contract s changed from the published with contractor's design 2016 arison document must be
£4,401.76
3420.0
This document has changed from the published version. A comparison document must be provided.
New beam and block floor build-up G/04 Kitchen & G/05 Dining: Contractor to supply and install new beam and block floor system to the rear extension structure (G/04 Kitchen and G/05 Dining area) as per Structural Engineer’s design and specification. 150mm deep prestressed concrete beam and block floor designed by specialist with 100mm deep dense block infill as required by Structural Engineer over min. 250mm ventilated void. Supply and install 90mm Celotex GA4000 or equal PIR insulation on 1,200 gauge polythene damp proof membrane (dressed up inner wall leaf and lapped over top of blockwork) with 25mm thick insulated separating layer to perimeter of entire extension. Supply and install 75mm reinforced concrete screed (to satisfy BS 8204) with underfloor heating system installed to manufacturer's instructions (underfloor heating system cost to be included in item 13.03 below) on separating layer above insulation. Depth of floor build-up to allow for proposed floor finish (tiles)to finish at the same level as the existing. Condition of remaining buildup/substrate to be assessed pre-removal and concerns to be discussed with architect/client. Allow for connection to existing floor.
290.0
161495104
850.0
MWD 2016 19/07/2023 16:12 UTC Minor Works Building Contract with contractor's design, 2016 Edition
3350.0
6.01
161495104
450.0
A-A
PROPOSED SECTION
1
335.0
1
450.0
030-4-202
Stage 4 general arrangement plan extract from construction drawings package Scale 1:25 at A1
£20,744.33
£3,335.13
0mm
500mm
1,000mm
Ventilated void
Ventilation
Trafalgar Place, Brighton East Sussex BN1 4DU
A
The project Design Brief below has been prepared in response to our initial discussions. However, it’s prudent to continue developing the brief during the initial stages of the project to ensure that the
This feasibility study will explore ideas for how to extend the ground floor kitchen/dining space. The rear of the house has role design spatialmore outcomes an eastern orientation which benefits from early morning sun through to the afternoon butand is perhaps shadedalign in the with your requirements. evening. The current configuration of the main part of the house is typically traditional but the new additions to the rear make less good use of the space. Following our meeting we understand the design brief to include:
Paving
This document will also look at ideas for extending the first floor outrigger and internal reconfigurations on both the first and - Internal layout upgrade: second floors.
RIBA Stages 0-1 Initial contact client meeting with colleague Discussed fee proposal internally Defined design brief Created feasibility study document Precedent study Planning policy analysis Presented ideas to clients Discussed procurement strategies with clients
Raised bed
Pre-employment client meeting Draft fee proposal Feasibility study Planning application Construction drawings package Draft Schedule of Works Tender and negotiations
AM
051-1-101
Rearrangement of existing internal layout at ground floor level Rearrangement of existing internal layout at first floor level Rearrangement of existing internal layout at second floor level
3
RWP
- Extension Design of side infill extension at ground floor Design of rear extension (two storey) over existing kitchen/living area
IC
G/05
WC / UTILITY AREA = 4.6m² FFL - U/C = 2,190mm
Extract from fee proposal Flowerbed
Lead Designer
1. Design Brief
051-1-201
Side extension with extensive joinery package project Hove, East Sussex l o c a t17th i oJune n 2022 Tender (on-site summer 2024) w o r k s t a g e Introduction £150k budget Description and analysis
Shed
DH:1970 Shower
Store
H:1970
G/04
KITCHEN
RIBA Stage 2 Developed design ideas in response to client feedback Finalisation of design brief Consolidation of aesthetic preference Discussed sustainable design & eco-friendly technologies Discussed third-party professional consultants
AREA = 6.6m² FFL - U/C = 2,280mm
Extend kitchen/ dining/living space
SVP
Canopy above
RIBA Stage 3 Developed concept design into planning application drawings Confirmed outline specification for key elements Planning submission & monitoring Discussed cost plan opportunity with clients Initiated conversations with prospective contractors
G/03
DINING
Gravel
AREA = 10.4m² FFL - U/C = 2,500mm
H:2230
PM G/02
PLAY ROOM AREA = 11.6m² FFL - U/C = 2,730mm
DH:2000
H:2050
H:2520
10of 10
H:2730
G/01
H:2520
LIVING
AREA = 14.8m² FFL - U/C = 2,720mm
1 051-1-101
Simple Rhino massing models showing possible extension works
Site analysis plan from feasibility study
A
H:2540
051-1-201
13
Cupboard
Hatch
RIBA Stage 4 Compiled all necessary specification information Formed comprehensive set of technical design drawings Coordinated & integrated structural design into drawings Prepared Schedule of Works Issued all tender documentation to prospective contractors Compare returned tenders
4
051-1-102
2
051-1-102
SVP
4
051-1-102
RWP
13
Images of concept idea 1 contained within feasibility study
Images of concept idea 2 contained within feasibility study
Images of concept idea 3 contained within feasibility study
13
6
Idea 2a
4
Kitchen / Dining Integration
Idea 2a
Study / Home Office
Full-height kitchen cupboards
Kitchen to be designed
Pantry / utility pod
Central dining table and kitchen island
Stage 2 3D model revealing flow through spaces Two work spaces
Stage 2 sketch plan drawing
Display shelves
Rooflights
Extension
Art / lighting
Display shelves
Stage 2 sectional model through multi-purpose circulation space within extension
Gardening area
Internal view from existing house to extension showing flow around central utility pod
13
Stage 2 images created using Rhino and Twinmotion
adow Study
mer
ning feedback: Initial concern regarding materiality (nothing further) No concern in principle with depth of side extension or outrigger Main concern is the height of side extension, claimed it would overshadow no. 103 detrimentally - reduction in height and/or depth would be acceptable Concern regarding height of extension above cill of new outrigger window
Existing
Proposed
Additional Shadowing
Reduced 500mm
9am
12pm
3pm
13
James Patterson Architects
info@jp-architects.co.uk Extract from document prepared for clients to illustrate planning officer’s concerns which was subsequently submitted with amendments to reduce depth of extension 01273 443978
Shed
External sink
Paving
051-3-101
051-3-101
1
1 1840
3225
RWP
1000
Deep window reveal with built-in seating Extent of neighbour's lean-to 130
Extent of neighbour's lean-to
Openable flat rooflight
READING AREA
Rooflight above
AREA = 6.2m² FFL - U/C = 2,190mm
Glazed roof with timber 'fins' under
Replace existing flat roof with new parapet roof
Extent of neighbour's outrigger
Extent of neighbour's outrigger
Ridge: +10,050
DINING
AREA = 17.8m² FFL - U/C = 2,280-2,500mm
Bench / study area
Shelves
Assumed location of new beams
BEDROOM 3 AREA = 10.7m² FFL - U/C = 2,360mm
Remove existing chimney
Bespoke kitchen - layout TBC
Bespoke full-height pantry storage - joinery element
Eaves: +6,880
Wardrobe Remove existing chimney
KITCHEN
AREA = 20.0m² FFL - U/C = 2,280-2,500mm
Large kitchen island with breakfast bar
Second Floor FFL: +5,960
BATH
H:2400
2
H:2100
H:2230
Parapet behind
UTILITY
Wet and dry storage
Bespoke understair storage - joinery element
WC
AREA = 3.3m² FFL - U/C = 2,730mm
AREA = 1.3m² FFL - U/C = 2,730mm
First Floor FFL: +3,020 Timber cladding
First Floor (Bath) FFL: +2,600
051-3-102
Hatch above
4
051-3-102
2
F/F
051-3-102
Neighbour's outrigger (103 St Leonard's Road)
4
051-3-102
Render
AREA = 3.8m² FFL - U/C = 2,410mm
Openable flat rooflight
Rooflight above
BEDROOM 2 AREA = 11.6m² FFL - U/C = 2,700mm
H:2700
Parapet behind White render finish DH:2000
Glazed timber frame door with solid panel and fan light above
Timber frame window with solid panel 2200
Ground Floor FFL: +0,000 Ground Floor FFL (Rear): -0,160
DH:1970
H:2520
H:2050
New timber frame glazed bi-fold doors
1570
H:2730 2780
1750
3835
H:2520
LIVING
1440
BEDROOM 1 AREA = 18.0m² FFL - U/C = 2,700mm
3
PROPOSED REAR ELEVATION Scale 1:50 at A1
0mm
2815
AREA = 14.8m² FFL - U/C = 2,720mm
1,000mm
2,000mm
Extract from submitted planning drawings
H:2540
3
3
13 258
ry
117
Surge
2680
1600
2700
DH:1970
2650
3500
STUDY
AREA = 11.5m² FFL - U/C = 2,730mm
Lean-to
051-3-101
051-3-101
LOCATION/BLOCK PLAN LEGEND : SITE BOUNDARY LINE : SHARED SITE BOUNDARY LINE : MAIN BUILDING : EXTENSIONS : NEIGHBOURING BUILDINGS
Scale 1:50 at A1
0mm
PROPOSED FIRST FLOOR PLAN
Existing wall fill
Proposed wall fill
Extract from submitted planning drawings
1,000mm
2,000mm
Scale 1:50 at A1
Existing wall fill
Proposed wall fill
0mm
31.01.23 Planning amends
JE
Date:
Drawn by:
Notes:
101 ST LEONARD'S RD
N
N
PROPOSED GROUND FLOOR PLAN
A Rev:
1,000mm
2,000mm
101 ST LEONARD'S ROAD HOVE BN3 4QQ
051-3-001 PROPOSED GF & FF PLANS
107
SCALE: 1:50 @ A1 DRAWN BY: JE STATUS:
FOR PLANNING NOTES:
+5,960
Roof Space
Roof Space
Neighbour's outrigger (103 St Leonard's Road)
1/04
1/04
BATH
Solid roof section with rooflight
BATH 9
14
9
False high-level units to conceal ventilation ducting
410
375
18mm MDF cupboard doors with oak veneer
False high-level units to conceal ventilation ducting
375
410
False high-level units to conceal ventilation ducting
410
465
L: +2,600
18mm MDF shelving with oak veneer
G/04
KITCHEN / DINING
1955
375
Kitchen worktop and splashback TBC
65mm kickplate recess to match kitchen joinery
13
910
380 410
Kitchen built with Howdens carcasses and new doors/drawers made from 18mm MDF finished with oak veneer
6
Understairs storage TBC
4
65mm kickplate recess to match kitchen joinery
140
910
Kitchen worktop and splashback TBC Kitchen built with Howdens carcasses and new doors/drawers made from 18mm MDF finished with oak veneer
2525
1970
Tall kitchen units built using Howdens carcasses and new doors made from 18mm MDF finished with oak veneer
1770
3
375
Glazed timber internal door to match rear windows/door
140
+0,000
Hallway
Extracts from tender drawings showing sections through extension and part of joinery package including kitchen B-B
PROPOSED SECTION Scale 1:25 at A1
0mm
500mm
1,000mm
Existing wall fill
3. External walls (along neighbour's outrigger): Contractor to form new timber frame wall along neighbour's outrigger of new side extension as per Architect's drawings and Structural Engineer specification: - 150mm timber frame comprising 50mm clear cavity and; - 100mm Kingspan Kooltherm K112 (or equal performing) between timbers; - Kingspan Kooltherm K118 37.5mm (12.5mm plasterboard internal finish); - Skimmed and decorated. - All external walls to achieve a U-value of 0.18 W/m2k or better.
6. Ground bearing slab: Contractor to form new ground bearing slab throughout G/04 Kitchen/Dining including the new side extension structure as per Structural Engineer’s design and specification. - 125mm thick slab with A393 anti-crack mesh on sand blinding and hardcore as required by Structural Engineer; - 90mm Celotex GA4000 or equal PIR insulation on 1,200 gauge polythene damp proof membrane (dressed up inner wall leaf and lapped over top of block-work) with 25mm thick insulated separating layer to perimeter of entire screed; - 75mm reinforced concrete screed (to satisfy BS 8204) with underfloor heating
BUILDING CONTROL NOTES: Structural steelwork: to be grade S355 and all bolts to be 8.8 bolts unless otherwise stated by structural engineer. All external steelwork to be galvanised. Structural steelwork to be encased to provide min. 1 hour (60 mins) fire resistance. PROPOSED SECTION All lintels to structural engineers design/specification and installed as per 0mm Scale 1:25 at A1 manufacturer's recommendations (where pre-fabricated). Steelwork connections and splices to be designed and supplied by the steel fabricator and agreed with structural engineer before fabrication.
A-A 500mm
1,000mm
Existing wall fill
Cavities: to be closed at top and bottom and fire-stopped at party wall junctions with approved cavity fire-stops. Cavity Barriers: to be provided at the junction between an external cavity wall and a Rev: Date: Notes: compartment wall that separates buildings. 15mm Gyproc Multi-board screw fixed at 300mm centres onto 75mm x 50mm timber stud framework with studs at 600mm Externalas walls (external Contractor to install new external insulation to centres with Rockwool insulation to the4.perimeter necessary. Toinsulation): provide at least existing rear extension as per Architect's drawings and Structural Engineer 30 min. fire resistance. specification: 101 ST LEONARD'S ROAD - 10mm polymer render external finish; Cavity trays: to be installed as per Building Control Officer requirement. - 50mm Kingspan Kooltherm K112 (or equal performing) fixed to existing blockwork; HOVE Fire detection and fire alarm systems: to be designed and installed by a BN3 4QQ 2 max U-value:to be 9. Flat roof Smoke - 0.15W/m competent person to comply with BS 5839-6:2004. and K heat detectors - GRP waterproofing mains supplied and connected to an independent circuit at the distribution board. All - 18mmAll plywood detectors to include a battery back up system. smoke detectors, sounders etc. to - 150mm Celotex L2 GA400 or to equal fire officer and BCO approval and satisfaction. Category system be installed.
BUILDING CONTROL NOTES: Drawn by:
101 ST LEONARD'S RD
Structural steelwork: to be grade S355 and all bolts to be 8.8 bolts unless otherwise stated by structural engineer. All external steelwork to be galvanised. Structural steelwork to be encased to provide min. 1 hour (60 mins) fire resistance. All lintels to structural engineers design/specification and installed as per manufacturer's recommendations (where pre-fabricated). Steelwork connections and splices to be designed and supplied by the steel fabricator and agreed with structural engineer before fabrication. Cavities: to be closed at top and bottom and fire-stopped at party wall junctions with approved cavity fire-stops. Cavity Barriers: to be provided at the junction between an external cavity wall and a
Rev:
Date:
Notes:
Drawn by:
13
Finishes Note: Contractor to confirm all areas/square meterage noted. For painted finishes refer to item 16.
Item: 13.00
G/04 Kitchen/Dining floor finishes: Microtopping® applied floor finish from The Micro Cement company. 2-4mm thick trowelled finish, installed as per specialist recommedation. Standard colour from Micro Cement's 'Classic Standard Colour' range. Approx. 41.9m.sq. Floor/surface preparation as required by supplier/installer.
Amount:
Unit:
Quantity:
Amount:
Notes:
£0.00
sq.m.
0
£6,500.00
+£3,000
G/04 Kitchen/Dining floor finishes (tiled installation): Contractor to provide alternative cost for installation (only) of tiled flooring to G/04 Kitchen/Dining room. Include all required preparation of existing substrate i.e. brushing down, install 'Ditra' matting (or equal approved), Mapei grout (colour to be confirmed) and all adhesive/trims (trims as required). Item only relevant as alternative to item 13.00 above.
£100.00
sq.m.
42
£0.00
£5,400 Microcement alternative (-£1,100)
13.01
G/03 WC/Utility floor finishes: Supply. Contractor to allow for the supply of new tiled floor finishes to G/03 WC/Utility approx. 4.8m2. Specification of tiles not confirmed at time of tender. Allow £50/m2 for supply costs.
£50.00
sq.m.
5
£600.00
-£350 (£50/m2)
13.02
G/03 WC/Utility floor finishes: Installation. Contractor to allow for the installation of new tiled floor finishes. Include all required preparation of existing substrate i.e. brushing down, install 'Ditra' matting (or equal approved), Mapei grout (colour to be confirmed) and all adhesive/trims (trims as required).
£0.00
sq.m.
0
£460.00
13.03
1/04 Bath floor finishes: Supply. Contractor to allow for the supply of new tiled floor finishes to 1/04 Bath approx. 7.3m2. Specification of tiles not confirmed at time of tender. Allow £50/m2 for supply costs.
£50.00
sq.m.
8
£960.00
13.04
1/04 Bath floor finishes: Installation. Contractor to allow for the installation of new tiled floor finishes. Include all required preparation of existing substrate i.e. brushing down, install 'Ditra' matting (or equal approved), Mapei grout (colour to be confirmed) and all adhesive/trims (trims as required).
£0.00
sq.m.
0
£560.00
13.05
1/04 Bath wall finishes: Supply. Contractor to allow for the supply of new tiled wall finishes to 1/04 Bath to height of 1500mm and within shower enclosure. Specification of tiles not confirmed at time of tender. Allow £50/m2 for supply costs.
£25.00
sq.m.
17
£1,800.00
13.06
1/04 Bath wall finishes: Installation. Contractor to allow for the installation of new tiled wall finishes. Include all required preparation of existing walls i.e. brushing down, Mapei grout (colour to be confirmed) and all adhesive/trims (trims as required).
£0.00
sq.m.
0
£260.00
13.05
Ground floor floorboard finish: Contractor to allow for sanding and painting of existing floorboards throughout remainder of ground floor, i.e. G/01 Living, G/02 Study and hallway. Paint specification TBC.
£0.00
sq.m.
0
£1,000.00
13.00a
Post-planning 3D image
Item 13 Sub-total: Item 13 Increase: Item 13 Possible Saving:
Extract14 from Schedule Joinery of Works Note: This section relates to all built-in-joinery. Free-standing joinery items shall be client supplied and not included within the contract.
13
-£560 (£50/m2)
-£1,375 (£25/m2)
£12,140.00 £3,000.00 -£3,385.00
Stage 4 model using Sketchup and Lumion
Remodelling of former school house Iford, East Sussex Planning (submitted) £300k
project location work stage budget
Lead Designer
Pre-employment client meeting Draft fee proposal Feasibility study Heritage research Developed design Planning application Preliminary cost analysis
role
RIBA Stages 0-1 Initial contact client meeting with colleague Discussed fee proposal internally Defined design brief Created feasibility study document Precedent study Planning policy analysis Heritage analysis Presented ideas to clients Discussed procurement strategies with clients RIBA Stage 2 Developed design ideas in response to client feedback Finalisation of design brief Consolidation of aesthetic preference Discussed sustainable design & eco-friendly technologies Discussed third-party professional consultants RIBA Stage 3 Developed concept design into planning application drawings Confirmed outline specification for key elements Planning submission & monitoring Conducted cost plan analysis Initiated conversations with prospective contractors
16
Photographs of existing house and site
Stage 1 3D visuals showing various initial concept ideas
16
Stage 1 visualisation of interior concept ideas
Stage 2 visualisation of interior developed design ideas
16
Stage 3 visualisations submitted with planning application
residential - development
17
18
19
20
Office to residential units
Former bank to mixed use
New build on micro-plot
New build on micro-plot
Multi-unit new build
Airspace development*
RIBA stages 1-3
RIBA stages 1-3
RIBA stages 1-3
RIBA stages 1-2
RIBA stage 1
RIBA stages 1-3
23
24
25
26
Feasibility study Developed design Planning application
Feasibility study Developed design Planning application
Feasibility study Developed design
22
Feasibility study
Feasibility study Developed design Planning application
27
28 Smoking / vape area
Feasibility study Developed design Planning application
21
BBQ storage area
LONGSTONE YARD FF
FF
WM
WM
800
1350 770 litre bin
800
1350
FF
WM
WM
FF
FF
WM
WM
FF
FF
WM
WM
FF
770 litre bin
800
1350 770 litre bin
Smoking / vape area
Storage for 20no. bicycles on vertical swivel hinges
WM
Apt. 20
BBQ storage area
Plan:
GROUND FLOOR PLAN Scale - 1:100
UKPN Cup'd
800
1350 770 litre bin
800
1350
N
770 litre bin
Storage for 20no. bicycles on vertical swivel hinges
800
1350 770 litre bin
1350 800
Apt. 20
770 litre bin
800
Post boxes
1350 770 litre bin 1350 800
UKPN Cup'd
770 litre bin
1350 800
Post boxes
800
1350 770 litre bin
770 litre bin
800
1350 770 litre bin
Plan:
GROUND FLOOR PLAN Scale - 1:50
N
ASHFORD YARD
BIN/BIKE PLAN
LONGSTONE ROAD
104
110
1-24 BERWICK COURT
98c
102
98a
90
96
88
93a
102a
CAVENDISH PLACE
LONGSTONE YARD
112
93 95
95a ASHFORD YARD
157
No.'s 1-20 Ashford Yard
129
143
97
ASHFORD ROAD
Elevation:
Scale - 1:50
N
FRONT (ASHFORD ROAD)
149
Plan:
LOCATION PLAN Scale - 1:1250
0mm
10,000mm
20,000mm
30,000mm
40,000mm
ASHFORD YARD APARTMENTS 1-20 145a ASHFORD ROAD EASTBOURNE EAST SUSSEX BN21 3UA
50,000mm
AUGUST 2023
Multi-unit extension*
Multi-unit new build
Airspace development*
Backland development
Backland development*
Airspace development
RIBA stages 2-3
RIBA stages 1-2
RIBA stages 1-3
RIBA stage 1
RIBA stages 1-4
RIBA stages 1-3
Developed design Planning application
Feasibility study Developed design
Feasibility study Developed design Planning application
Feasibility study
Feasibility study Developed design Planning application Construction drawings package
Feasibility study Developed design Planning application
*Assistant to lead designer
Multi-unit new build development Brighton, East Sussex Feasibility £1m Lead Designer Feasibility study
project location work stage budget role
RIBA Stage 1 Defined design brief Created feasibility study document Precedent study Planning policy analysis Heritage analysis Presented ideas to clients Discussed procurement strategies with clients Cost plan analysis
21
EXI S T I N G
Or i g i na l te r ra c e
(approx. areas)
120 - 124 VALE AVEN UE
HI STO R I C M A P O F A B E R GAV E N N Y E STATE
M A P O F PATC HA M A N D I TS SU R R O U N DS
DE SI GN CO NTE XT
HI S TO RI CA L C O N T E X T
SITE CONTEXT
•
Two-and-a-hal f storey bu i l di ng compris ing three hou ses
•
Ho us e s we re b uilt a s fa r m wo r ke r ’s c o t ta g e s fo r t he A b e rg ave nny E s ta te
•
Red bri ck wi th stri ng cou rse and pi tche d t ile roof
•
•
Sy mmetri cal desi g n
The c e nt ra l ho us e inc o r p o ra te s t he m o no g ra m ‘A’ fo r A b e rg ave nny a nd is d a te d 1909
•
Set back from the road behi nd g rass b a nk
•
The A b e rg ave nny E s ta te ow ne d much o f t he la nd in a nd a ro und Pa t cha m , hav ing a s ig nific a nt im p a c t o n t he a re a ’s d eve lo p m e nt
•
B uilt a t a t im e o f a g r ic ult ura l d e cline m e a ning t his is a ra re exa m p le o f fa r m wo r ke r ’s c o t ta g e s o f t his p e r io d
3B / 4P 8 0 m2
3B / 4P 9 0 m2
3B / 4P 8 0 m2
UN DEV ELOP ED S I T E (approx. areas)
•
O ut s id e t he Pa t cha m C o ns e r va t io n A re a b ut d o e s c o nt r ib ute to t he cha ra c te r o f t he v illa g e
•
N e a r by ro a d link s to Lo nd o n a nd c e nt ra l B r ig hto n
•
S o ut h D ow ns to t he N o r t h w it h p o te nt ia l v iew s f ro m up p e r flo o r s
•
Lo c a l b uild ing m a te r ia ls a nd c o ns t r uc t io n te chniq ue s includ e clay b r ick s, g la ze d b r ick s, clay t ile s, flint , a nd b ung a ro o s h a m o ng s t o t he r s
To tal si te area 1 7 0 0 m2
Bui lt area 1 2 0 m2
U ndevelo ped area 1 5 8 0 m2
Site analysis extract from feasibility study document
5
4
Co n text P rojec t: 120 - 124 Va le Avenu e, Patcham C li ent: Ri cha rd C a r r
Co n c e p t 1 - Units P roj e c t : 1 2 0 - 124 Val e Ave nue, Patch am C li e n t : R i ch a rd Car r
SITE INF ORMATION
C O N C E PT
•
9no. total uni ts (net addi ti onal 6no. uni ts)
•
11no. parki ng spaces
•
B i ns and bi ke storage provi ded
•
All garden si zes between 40m 2 and 75m 2
Or igin a l ter ra c e
( approx. areas)
3B / 4P 90m2
3B / 4P 80m2
3B / 5P 95m2
3B / 6P 110m2
3B / 5P 95m2
Mews cottages
Mode rn ter ra c e
3B / 4P 80m2
3B / 5P 95m2
3B / 5P 95m2
21
3B / 5P 95m2
CONCEPT SITE PLAN
Mews-style concept idea extract from feasibility study document
6
C o n c e p t 1 - Si te C o n c e p t P ro j e c t : 1 2 0 - 1 2 4 Va l e Ave nu e, Pa t ch am C l i e n t : R i ch a rd C a r r
SITE INF ORMATION
C O N C E PT
•
7no. total uni ts (net addi ti onal 4no. uni ts)
•
11no. parki ng spaces
•
B i ns and bi ke storage provi ded
•
F ront proper ti es garden si zes between 40m 2 and 75m 2
•
Large 6-bed si ngle dwelli ng to rear
Or igin a l ter ra c e
( approx. areas)
3B / 4P 90m2
3B / 4P 80m2
3B / 5P 95m2
3B / 6P 110m2
3B / 5P 95m2
Man or
Mode rn ter ra c e
3B / 4P 80m2
6B / 8P 180m2
21
CONCEPT SITE PLAN
Manor-house-style concept idea extract from feasibility study document
9
C o nc ept 2 - Site C o ncept P ro ject: 1 2 0 - 1 2 4 Vale Avenu e, Patcham C lient: Rich ard C arr
COST PLAN Issue date:
17/11/2018
CONCEPT 1
Summary
(approx. co sts)
£
C ONCEPT 1
CONCEPT 2
CONCEPT 2
( a p p rox . c o sts)
( a p p rox . c o sts)
(approx. cost s)
OPTION 1 Mews Cottage x 3
466,289.57
Modern Terrace x 3
490,831.13
External Communal & Private Areas
110,029.34
Utilities
30,000.00
TOTAL OPTION 1
1,097,150.04
OPTION 2 Large Single House
318,258.68
Modern Terrace x 3
490,831.13
Modern terrac e
External Communal & Private Areas
110,029.34
TOTAL OPTION 1
£490k
M o d e r n te r ra c e
M£o4d9e0rkn te r ra c e
4 6s6 kC o t ta g e s M£ew
£466k
Manor
M£a3n2o0rk
E x ternal C om mu nal & P ri vate A rea s
1 1r n 0 ka l Co m mu n a l & Pr i va te A re a s Ex£te
£110k
Ex te r n a l Co m mu n a l & Pr i va te A re a s
1 1r n 0 ka l C o m mu n a l & P r i va te A re a s E x£te
U ti l i ti es
Ut i £ li 3 t i0 eks
£30k
Ut i li t i e s
U t i£ li3 t i0 eks
£ 1 . 1 To mita l l ilo n
£ 1 . 1 mi l l i o n
To ta l
To£950k ta l
Mew s C ottages
Utilities
M£o4d9e0rkn te r ra c e
30,000.00
949,119.14
Total
Illustration of cost plan information extract from feasibility study document
Exclusions: Asbestos removal Contaminated materials Inflation Legal fees Land purchasing Architect design fees Cost consultancy fees Project Management consultancy fees Planning application fees Structural design fees
Extract from document supplied by third party specialist
21 Issued 17/11/2018
10
Co sts do no t include th e fo llow ing :
C o sts d o n o t i n clu d e the fo llow i n g :
C o sts d o n o t i n clu d e the fo llow i n g :
Cost s do not i ncl u de t he fol l owi ng:
•
Wo rks to extisting terrace
•
Wo rk s to ex ti sti n g te rra c e
•
Wo rk s to ex ti sti n g te rra c e
•
Works to ext i st i ng terrace
•
Asbesto s removal
•
A sbe sto s re m ova l
•
A sbe sto s re m ova l
•
Asbestos removal
•
Co ntaminated materials
•
C o n ta m i n a te d m a te ri a ls
•
C o n ta m i n a te d m a te ri a ls
•
Contami nated materi al s
•
Inflatio n
•
In fla ti o n
•
In fla ti o n
•
Infl at i on
•
Leg al fees
•
Le g a l fe e s
•
Le g a l fe e s
•
Legal fees
•
Land purch asing
•
La n d p u rcha si n g
•
La n d p u rcha si n g
•
Land pu rchasi ng
•
Arch itect desig n fees
•
A rchi te c t d e si g n fe e s
•
A rchi te c t d e si g n fe e s
•
Archi tect desi gn fees
•
Co st co nsultancy fees
•
C o st c o n su lta n c y fe e s
•
C o st c o n su lta n c y fe e s
•
Cost consu l tancy fees
•
Pro ject M anag ement co nsultancy fee s
•
P ro j e c t M a n a g e m e n t c o n su lta n c y fe e s
•
P ro j e c t M a n a g e m e n t c o n su lta n c y fe e s
•
Project Management consu l tancy fees
•
Planning applicatio n fees
•
P la n n i n g a p p li c a ti o n fe e s
•
P la n n i n g a p p li c a ti o n fe e s
•
Pl anni ng appl i cat i on fees
•
Structural desig n fees
•
S tru c tu ra l d e si g n fe e s
•
S tru c tu ra l d e si g n fe e s
•
St ru ct u ral desi gn fees
Costings C o st i n g s P ro j e c t: 1 2 0 - 1 2 4 Va l e Ave nu e, Pa tch P ro am j e c t : 1 2 0 - 1 2 4 Va l e Ave nu e, Pa t ch a m C l i e n t: R i ch a rd C a r r C l i e n t : R i ch a rd C a r r
10
1 of 5
Created by RF Construction Consultants Ltd
End of terrace extension for multiple units Hastings, East Sussex Planning approved £1m
project location work stage budget
Assistant designer
Detailed developed design Planning application
role
RIBA Stage 2 Investigated various apartment layouts Assisted development of 3D model Produced material for developed design document RIBA Stage 3 Coordination of obtaining appropriate third-party information Assisted creation of planning application drawings Helped monitor planning application
23
3D visualisations submitted with initial planning application
Approx. site boundary (varies)
Site boundary Retain existing chimney breast at loft level and stack above roof level.
Extension roof to match pitch and levels of existing roof. Ridge line to be extended at same height.
Ridge level: +8,607 u/s/ ridge (internal): +8,229
Tiles
Top of bay rige level: +7,980
Front bay element to have similar scale and massing to existing dwelling. Materials to match.
Redecorate existing fascia and soffits.
3129
Skylights x2no. above bedroom and storage for natural light and ventilation.
Timber clad (white)
Retain existing eaves level as existing. Black uPVC guttering to match.
Eaves level: +5,653 Replace existing fenestration with same design, detail and material as propopsed.
2300
8229
8607
250
Loft floor FFL: +5,100 First floor ceiling: +4,850 Gabled wall (as per existing structure) to be constructed in brickwork to match existing. Fenestration to existing and proposed structures to be of the same design, detail and material.
5653
Brick
250
First floor FFL: +2,550
2300
New front door within existing archway.
675
GF cill level: +0,675
Ground floor ceiling: +2,300
Landscaping to front gardens to create visual barrier between extension structure and road. New boundary wall to match design of wall facing Eversley Road and follow incline of site topography.
Brick
Ground floor FFL: +0,000 Brick
New boundary wall to match design of wall facing Eversley Road and follow incline of site topography.
Extent of existing building
Scale 1:50 at A1
1945
6853
1331
Extension building line set back approx. 1,950mm from boundary.
Extent of proposed extension
1,000mm
2,000mm
Window
Retain existing chimney breast at loft level and stack above roof level.
Ridge level: +8,607
u/s/ ridge (internal): +8,229
Skylights x3no. above bedroom and bathroom for natural light and ventilation.
0mm
Entrance to Units 1, 3 and 4
External ground level: -700
1
PROPOSED FRONT ELEVATION
Approx. site boundary (varies)
Extension roof to match pitch and levels of existing roof. Ridge line to be extended at same height.
Entrance to Units 5, 6 and 7
Eversley Crescent
Site boundary
23
Front elevation extract from submitted amended planning drawing
Brick
6606
23 Eversley Road
700
Top of boundary wall: +0,000
Tiles
Drawing notes:
062-3-101
14983
3 6803 6453 2780
Retain existing brickwork wall to the perimeter of parking area.
14
Existing building line (bay projection)
Additional planting and foliage to perimeter of parking area (in addition to the existing) to provide visual and acoustic buffer between parking area and neighbouring properties.
1064
Rear gable structure similar in design to structure at 25 Eversley road.
UNIT 2
2b/3p - 61.0sq.m.
Walls to extension structure in brickwork to match adjacent building. No. 25 Eversley Road. Laid in stretcher bond.
2 New boundary wall to match design of wall facing Eversley Road and follow incline of site topography. Landscaping to perimeter of property to soften visual impact of new structure.
2500
6 5000
5
AREA = 11.5m² FFL - U/C = 2,300mm
5no. Parking bays 4
New window to side elevation to match size and design of existing window.
5000
BEDROOM 2
AREA = 7.6m² FFL - U/C = 2,847mm
10583
BEDROOM 2925
2500
u2/04
2932
AREA = 0.65m²
u6/02
x5no car parking spaces 2,500mm x 5,000mm.
14no. bins 8 7
AREA = 26.2m² FFL - U/C = varies
1
u2/05
KITCHEN/LIVING
AREA = 15.7m² FFL - U/C = 2,847mm
9
Landscaping
u1/04
KITCHEN/LIVING
STORE
Paving to perimeter of extension structure.
2
Entrance door to Unit 2 accessed from Eversley Crescent.
New timber acoustic fence on top of existing brick wall at 2,000mm above external ground level to provide aan acoustic barrier between the parking area and 23 Eversley Road.
1
u6/01
BEDROOM 2
AREA = 4.4m² FFL - U/C = 2,300mm
2150
2
BATHROOM
AREA = 8.4m² FFL - U/C = 2,300mm
3
2
600
23117
u2/02
062-3-101
u2/03
18643
AREA = 4.5m² FFL - U/C = 2,847mm
4
BATHROOM
5
4
12500
1
Entrance to Unit 2
2162
Replace existing window with double doors to provide external access and fire escape.
062-3-101
u2/01
HALL
AREA = 5.2m² FFL - U/C = 2,300mm
1260
AREA = 0.45m²
New bathroom in location of existing bathroom (at first floor level) to utilise existing drainage routes.
Existing tree
3
AREA = 2.0m²
Infill existing doorway with brickwork to match existing.
14no. bins.
1718 2483
2600 Demolish portion of existing, internal structure to create additional space.
Built-in-storage within bedroom and also within hallway 1.1 sq.m. total..
3
UNIT 6
1b/1p - 39.0sq.m.
3661
Replace windows with new to provide ventilation and improve thermal performance of existing structure.
4
Existing building line
New timber closed fence on top of existing brick wall at 2,000mm above external ground level to provide a visual barrier between the parking area and Eversley Crescent.
13
Hard landscaping
Replace existing doors and windows with new to provide ventilation and improve thermal performance of existing structure.
Existing tree
12
Rear doors to allow access to rear garden.
Existing tree
Existing trees and foliage to be retained where practical.
11
Rear garden
Landscaping to rear gardens to create visual barrier between extension structure and car parking.
10
Hard landscaping
Rear garden to be part paved part grassed. Refer to Landscaping drawings for further information.
5
Rear garden
Soft landscaping
5no. Bicycle bays
Soft landscaping
6152
3255
6152
4840
1118 1883
14983
u5/03
u5/02
u1/03
u1/02
BATHROOM
BEDROOM AREA = 10.5m² FFL - U/C = 2,300mm
AREA = 0.37m²
u5/01
SHOWER
Retain existing load-bearing wall to maintain structural stability of existing building.
23 Eversley Road
25 Eversley Road Parking area
Eversley Crescent
Landscaping
AREA = 4.4m² FFL - U/C = 2,300mm
Built-in-storage 0.37 sq.m. plus storage below stairs totals 1.12 sq.m.
4500
AREA = 5.1m² FFL - U/C = 2,847mm
6000
SHOWER
AREA = 10.7m² FFL - U/C = 2,847mm
6000
3930
BEDROOM
2684
Demolish existing chimney breasts to create additional space.
AREA = 2.2m² FFL - U/C = 2,847mm
STORE AREA = 1.5m²
New cross-over. Storage below new stairs min. 1,500mm height above finished floor level.
3198
STORE
7500
4495
AREA = 0.75m²
UNIT 1
u1/01
HALL
1b/1p - 37sq.m.
8060
UNIT 5
23 Eversley Road
1b/1p - 39sq.m.
AREA = 4.2m² FFL - U/C = 2,300mm
4036
u5/04
u1/04
KITCHEN/LIVING AREA = 16.2m² FFL - U/C = 2,847mm
Communal entrance area
up
Demolish portion of existing rendered brickwork wall to provide vehicular access to the parking area.
10no. bicycle parking bays 1,800mm x 750mm.
3622
New staircase from ground to first floor level to comply with Part K of the Building Regulations.
New boundary wall to match design of wall facing Eversley Road and follow incline of site topography.
KITCHEN/LIVING
up
AREA = 16.8m² FFL - U/C = 2,300mm
Communal entrance area
Landscaping to perimeter of property to soften visual impact of new structure. 4854
New front door within existing archway.
5755
Existing building line
up
6
1945
up
Existing building line (bay projection)
Entrance to Units 5, 6 and 7
Hard landscaping
Entrance to Units 1, 3 and 4
Hard landscaping
N
PROPOSED GROUND FLOOR PLAN Scale 1:50 at A1
0mm
2250 1,000mm
2,000mm
Existing wall fill
Proposed wall fill
23
6606
Front garden Soft landscaping
Ground floor plan extract from submitted amended planning drawing
3903 6853
Front garden
1 062-3-101
Soft landscaping
Landscaping to rear gardens to create visual barrier between extension structure and road.
PLANNING Proposed ground plan
060-3-001
rev.
7
Soft landscaping
Soft landscaping
Hard landscaping
Hard landscaping
A
Project:
25 Eversley Road, Hastings, St. Leonards-on-Sea. TN37 6QD
Scale:
1:50 at A1
Issue date:
13/07/2023 - Rev.A (bay amended for planning)
Drawn by:
JMP
1970
Extension building line set back approx. 1,950mm from boundary.
NOTES: All measurements and site conditions are to be checked prior to the preparation of drawings or commencement of works. This drawing belongs to James Patterson Architects Ltd. and is protected by the Copyright, Designs and Patents Act, 1998. James Patterson Architect's Ltd. info@jp-architects.co.uk 01273 006069 www.jp-architects.co.uk
Parking & amenity space plan extract from submitted amended planning drawing
1945
Backland new build development Hastings, East Sussex Feasibility £500k
project location work stage budget
Lead Designer Feasibility study
2
role
Site Strategy Analysis
An unusual feature of the site is the railway line which runs underneath via a tunnel. This provides a construction problem, so to avoid this we have assumed no construction is to be carried out past the building line of the host property. In fact, this might aid our argument in Planning. Allowing for a buffer to the host building will also be necessary and currently we have given a minimum of 5m. This distance can be discussed further. The area of garden remaining is what we’ll use to situate the proposal. If we assume the entrance will be from the northern elevation, the back of the proposal will be mostly south-facing. This orientation is preferable for outlook and quality of light, but also particularly important if we go down an eco construction technology route as we would obtain a heating effect from the solar gain. This idea will be explored further in this document.
RIBA Stage 1 Defined design brief Created feasibility study document Precedent study Planning policy analysis Heritage analysis Discussed sustainable design & eco-friendly technologies Presented ideas to clients Discussed procurement strategies with clients
26
Church Road
Railway line below
PM
g line of
Buildin
55
operty
host pr
AM
5m buffer
3
Site Strategy
Development representation N site ranging in size and scale. Of these options, 4 have been explored There are various options for the development of the here in this massing exercise. They vary in unit numbers, storeys and configuration. Example floor plans will be shown on EXISTING SITE PLAN the pages that follow. Scale 1:150 at A3
0mm
2,000mm
4,000mm
James Patterson Architects info@jp-architects.co.uk 01273 443978
Site analysis defining possible construction area extract from feasibility study 1 • • • •
1 Unit Single storey 3-bedroom Internal courtyard
2 • • • •
2 Units Single storey 1-bedroom Rear courtyard
3 • • • •
2 Units Two storey 3-bedroom Rear courtyard
4 • • • •
2 Units Two storey 3-bedroom Raised terrace
Site massing study extract from feasibility study James Patterson Architects info@jp-architects.co.uk 01273 443978
26
ENTRANCE TOTAL AREA = 76.0m²
BATH
AREA = 3.5m²
GARDEN AREA = 9.2m²
BEDROOM
BEDROOM
AREA = 8.7m²
AREA = 8.4m²
Concept Idea 1 plan extract from feasibility study
N
PROPOSED FLOOR PLAN Scale 1:50 at A3
0mm
1,000mm
2,000mm
Concept Idea 1 3D visualisation extract from feasibility study
BEDROOM AREA = 11.6m²
KITCHEN / LIVING / DINING AREA = 33.0m²
26
ENTRANCE TOTAL AREA = 37.0m²
BEDROOM
KITCHEN / LIVING / DINING
AREA = 11.5m²
AREA = 16.9m²
BATH
KITCHEN / LIVING / DINING
BEDROOM AREA = 11.5m²
AREA = 16.9m²
AREA = 3.8m²
Concept Idea 2 plan extract from feasibility study
N
PROPOSED FLOOR PLAN 0mm
TOTAL AREA = 37.0m²
BATH
AREA = 3.8m²
Scale 1:50 at A3
ENTRANCE
1,000mm
2,000mm
Concept Idea 2 3D visualisation extract from feasibility study
26
• Raised terrace - first floor living • 5.6m buffer to host property
ENTRANCE
ENTRANCE
TOTAL AREA = 76.0m²
N EXISTING SITE PLAN Scale 1:150 at A3
0mm
TOTAL AREA = 84.2m²
ENTRANCE
2,000mm
4,000mm
Scale 1:150 at A3
TOTAL AREA = 84.2m²
BATH
TOTAL AREA = 76.0m²
EXISTING SITE PLAN
N
ENTRANCE
Proposed Site Plan
0mm
AREA = 3.5m²
KITCHEN / LIVING / DINING
KITCHEN / LIVING / DINING
AREA = 34.4m²
BEDROOM
KITCHEN / LIVING / DINING
AREA = 9.0m²
GARDEN AREA = 9.2m²
BEDROOM
BEDROOM
BEDROOM
AREA = 8.7m²
AREA = 8.4m²
AREA = 12.7m²
AREA = 9.0m²
AREA = 34.4m²
BEDROOM
GARDEN AREA = 9.2m²
AREA = 12.7m²
BEDROOM
AREA = 11.6m²
BEDROOM
AREA = 8.7m²
BEDROOM
AREA = 8.4m²
BATH
AREA = 11.6m²
BEDROOM
AREA = 3.8m²
AREA = 9.0m²
RAISED TERRACE
RAISED TERRACE
AREA = 17.1m²
AREA = 17.1m²
Concept Idea 3 ground & first floor plans extract from feasibility study
Proposed First Floor Plan
N
Scale 1:50 at A3
PROPOSED GROUND FLOOR PLAN Scale 1:50 at A3
0mm
0mm 1,000mm
N 1,000mm
2,000mm
2,000mm
Concept Idea 3 3D visualisation extract from feasibility study
AREA =
BEDROOM
BEDROOM
AREA = 3.8m²
PROPOSED FLOOR PLAN
KITCHEN / DINI
AREA = 9.0m²
AREA = 33.0m²
BATH
BEDROOM
N
4,000mm
BATH
AREA = 3.5m²
Proposed Ground Floor Plan
2,000mm
N
PROPOSED FLOOR PLAN 0mm
Scale 1:50 at A3
PROPOSED FIRST FLOOR PLAN Scale 1:50 at A3
0mm
1,000mm
2,000mm
1,000mm
2,000mm
James Patterson Architects info@jp-architects.co.uk 01273 443978
Construction Strategy Energy efficient design extract from feasibility study document
Using Passivhaus as the gold standard of energy efficient design, we have investigated the case for using such a construction technology. Passivhaus focuses predominantly on mechanical ventilation and heat recovery, airtightness, thermal bridging, and insulation. It is estimated that a home designed to Passivhaus standard can consume 90% less energy than the average UK home. In a climate where energy bills are spiralling out of control, this could become a very attractive selling point in the housing market going forward. Evidence on whether achieving a Passivhaus standard actually increases the value of a property is unclear, perhaps due to there having been a limited number of Passivhaus homes on the market to date. However, there is some evidence that increasing the energy efficiency of a home is valuable on the market. Improving from an EPC rating of C to A/B could increase the property’s value by 4% according to a Government report published in 2013. Almost a decade later, estate agent and property consultant, Knight Frank, estimates that moving up two EPC bands from E to C can increase property value by almost 9%. The construction cost uplift in achieving Passivhaus standard is around 10% but in considering the potential value increase of the property, the initial increase in costs could be worthwhile. Also, while we are exploring the viability of Passivhaus, some of it’s core principles could be adopted without needing to achieve this highest level of energy efficiency, where costs may not allow. The environmental argument for energy efficient buildings is obvious but perhaps there is economic opportunity, too. The diagram, right, shows what might be possible.
Department of Energy and Climate Change, 2013
£500k Build cost
+20%
£300k / unit 3-bedroom
+10%
£150k
+8.3%
£550k Passivhaus Premium
+14%
£325k / unit 3-bedroom
Profit
£100k
Profit
£100k
+7.7%
£350k / unit 3-bedroom
26 bere:architects, 2022
An economic case for eco-friendly construction technologies extract from feasibility study document
Profit
£150k
other
29
30
Community development
Shipping container office
Berinsfield, Oxfordshire
RIBA stages 1
Infrastructure development plan Presentation to community
31
Feasibility study
32 “On this day 100 years ago, a drastic transformation began on the Phoenix Industrial Estate, as it was known then. Initially, with declining industry, disused and underused warehouses, factories and ancillary structures were demolished with reusable materials salvaged. Then, much of the mass concrete ground, which had been holding and slowly leeching harmful contaminants into the River Ouse, was excavated, broken down and stored to be recycled on-site.”
Competition
MArch final project
LFA - City Benches
University of Brighton
Braille Bench Dickens-inspired Inclusive urban environment
Design of new structural system Masterplanning site & time Precedent interrogation Research institute Posthumanism
Architecture in the Posthuman Threshold 31.05.2122 - article by @postArchitect (fictional character)
Architecture in the Posthuman Threshold A Prototype for Carbon Positivity
“Nowadays, we Architects are bound to designing buildings that positively effect our environment. We are bound by legislation enforcing carbon positivity. We are bound by our desire for a continued human existence. And we are bound by the journey we have taken in the last 100 years. “The catalyst for this journey can be attributed to an experimental project in the East Sussex town of Lewes. Here, foundations were laid for our carbon positive future on a site with a history immersed in industry, critical to servicing its local and wider communities. However, for two centuries the site we now know as Phoenix Wood consistently consumed energy, produced carbon and damaged its environment. Things were different then, our priorities have changed. We have one now; our planet. “Today, the site is 40 years into its reclamation by nature following the European Ash Research and Development Institute’s planned closure. A concept we are now familiar with in architecture but that was innovative of its time. Today, we understand why legislation is in place restricting the sourcing radius for construction materials. No longer do we demand speed and economic value, rather we are patient with lengthy building programmes focused on protecting and enhancing our precious environment.
AIM705 : Master Thesis Project Jack Elliott : Studio 4
“Today, the site is 40 years into its reclamation by nature following the European Ash Research and Development Institute’s planned closure. A concept we are now familiar in architecture with but that was innovative of its time. Today, we understand why legislation is in place restricting the sourcing radius for construction materials. No longer do we demand speed and economic value, rather we are patient with lengthy building programmes focused on protecting and enhancing our precious environment.”
“The catalyst for this journey can be attributed to an experimental project in the East Sussex town of Lewes. Here, foundations were laid for our carbon positive future on a site with a history immersed in industry, critical to servicing its local and wider communities. However, for two centuries the site we now know as Phoenix Wood consistently consumed energy, produced carbon and damaged its environment. Things were different then, our priorities have changed. We have one now; our planet.”
31.05.2122 - article by @postArchitect “Nowadays, we Architects are bound to designing buildings that positively effect our environment. We are bound by legislation enforcing carbon positivity. We are bound by our desire for a continued human existence. And we are bound by the journey we have taken in the last 100 years.” *@postArchitect is a fictional character.
“On this day 100 years ago, a drastic transformation began on the Phoenix Industrial Estate, as it was known then. Initially, with declining industry, disused and underused warehouses, factories and ancillary structures were demolished with reusable materials salvaged. Then, much of the mass concrete ground, which had been holding and slowly leeching harmful contaminants into the River Ouse, was excavated, broken down and stored to be recycled on-site.”
“On this day 100 years ago, a drastic transformation began on the Phoenix Industrial Estate, as it was known then. Initially, with declining industry, disused and underused warehouses, factories and ancillary structures were demolished with reusable materials salvaged. Then, much of the mass concrete ground, which had been holding and slowly leeching harmful contaminants into the River Ouse, was excavated, broken down and stored to be recycled on-site.
European Ash Research and Development Institute
Construction Strategy
Ground Floor Plan 1:200
European Ash in Construction Reasearch and Development Institute
River Ouse
External spill out areas
Workshops
Meadow
“Material cultivation, industry generation, research and development, and rewilding all occurring on-site over the course of 100 years. The concept has been replicated up stream near Haywards Heath at the Bluebell Industrial Estate, and in Uckfield at Bellbrook Industrial Estate. These former failing industrial sites are soon to see construction commencing following their timber growing period.
32
“Not only does this project interrogate ‘the threshold’, and not only is it set within the posthuman threshold, but in itself it represents the threshold of an architecture that looks first to the planet we live on, and aspires to give itself back to the natural environment that built it.”
Stage 3 • Reinforced concrete slab on central first floor area. • Reinforced shuttered concrete walls to create first floor spaces (internally insulated between timber studs with plasterboard and skim coat for inhabited rooms). • Timber floor walkways installed above work areas with glass balustrades. • Timber stairs and ramp.
Store
WCs
“Over the course of the next 50 years, forestry would become the predominant industry on the site as a forest of European Ash trees would be grown from seedling to full maturity. This period of time sets the premise of a new attitude towards the architecture that would be produced here at a later date. Growing the materials on-site intended for construction while developing the techniques to build with them. “Thanks to the digital historic re-modelling software, ReArch 3D (fictional software), we are able to see how this building stood before its reclamation by nature. In examining the plan, we can begin to understand the hierarchy of spaces within the buildings, or indeed the lack thereof due to the ambiguity of the thresholds between them. This ambiguity reminds me of a project in Nimes, Spidernethewood, among others. I visited this house as a young architecture student and was in awe of the Architect’s ability to combine public/private, internal/external, and the space between.
Stage 4 • Folded plate CLT roof structure installed onto modlar CLT structures. • Large CLT trusses installed spanning across curved wings. • Solid CLT curved roof installed onto structure. • Salvaged corrugated steel applied to roof to provide protection from weather.
Stage 2 • CLT modular structures manufactured onsite and set into pile foundations, secured with steel plates coated in zinc. • Glazing installed on outer faces of CLT structures.
WCs Kitchen
Dining room
Workshops
External spill out areas
Site Strategy
2055 European ash maturing forest
2022 Unused warehouses and ancilliary buildings demolished - corrugated steel salvaged
2022 Areas of mass concrete dug up and reused in concrete required for constructing research institute - replaced with earth and top soil in preparation for planting
Stage 1 • Reinforced concrete pile foundations coated in zinc placed in curved formation to support glazed end of CLT modular structures. • Reinforced concrete raft foundation with exposed concrete finish and concrete steps around perimeter. • Ground floor reinforced shuttered concrete walls with exposed finish (internally insulated between timber studs with plasterboard and skim coat for inhabited rooms).
“Not only does this project interrogate ‘the threshold’, and not only is it set within the posthuman threshold, but in itself it represents the threshold of an architecture that looks first to the planet we live on, and aspires to give itself back to the natural environment that built it.”
2072 European Ash in Construction Research and Development Institute
Programme timeline
Store
2025 European ash nursery and sapling development grove
“Thanks to the digital historic re-modelling software, ReArch 3D*, we are able to see how this building stood before its reclamation by nature. In examining the plan, we can begin to understand the hierarchy of spaces within the buildings, or indeed the lack thereof due to the ambiguity of the thresholds between them. This ambiguity reminds me of a project in Nimes, Spidernethewood, among others. I visited this house as a young architecture student and was in awe of the Architect’s ability to combine public/private, internal/ external, and the space between.” *ReArch 3D is a fictional software.