Upper Control Arm Installation
3.Put ball joint stud through the spindle. Install nut finger tight then use a torque wrench and torque nut to 60ft-lbs. You may need to use a 3/8” wrench to keep the stud from spinning until nut is seated.
4.Re-attachABS wire to the tab on the side of the UCA. *Hole for the ABS bracket.
5. Check torque of ball joint bolts. (Torque to 13ft-lbs.)
6. Mount wheel and torque lug nuts.
7. Grease the ball joint with 3-4 pumps of lithium complex grease fortified with moly (molybdenum disulfide), until boot begins to swell. Grease the bushings with lithium complex grease fortified with moly (molybdenum disulfide) until you see grease pushing out from the bushing’s EZ lube ports.
8. Repeat on other side.
9. Reinstall the ECU and airbox in reverse order of removal.
10. Lower vehicle off of jack stand.