Vice Commodore Report
PAUL ARKWRIGHT Vice Commodore Again another hectic month, and we have multiple projects approved by GenCom and coming online soon.
Masterplan and lease renewal We have now signed the contract with Knight Frank to help the Club with the submission to Lands Department to get the required lease modification for the Regatta Deck underway ASAP. Once we have the approval, we can then demolish the unauthorised tent and build the new Regatta Deck. Once we’ve demolished the tent, we can also reactivate the lease modification for the existing Boat Racks. We are also working out the planning and logistics for the builds of the access lift and new storage areas for the kitchen & garden bar.
Advertisement
Seawall repairs update GenCom has approved the engagement of a contractor to proceed with repairs to the existing sloping seawalls. This will include the reconstruction of existing sloping seawall adjacent to the car park, digging up rutted asphalt in the boatyard and restatement of concrete pavement, reconstruction of concrete slipway—near Marine office/tender moorings and reconstruction of concrete slipway—near the Restaurant.
Marina pile long-term replacement project GenCom has approved a construction contractor’s engagement to conduct the Ground Investigation (GI) works in preparation for the complete replacement of the marina piles.
Boat rack safety walkways The contractor will prepare a mock-up for inspection by Matthew and the boatyard team before the full rollout of the build in December 2021.
Changing rooms projects After completing the designs for the complete refurbishment of the Club changing rooms and their ventilation system, we are now accessing tenders for the works. At the same time, GenCom has approved the purchase of a temporary mobile shower and toilet block needs to be purchased before the renovation, so everyone has somewhere to shower and use the washrooms during the refurbishment. This refurbishment will be phased starting with the female washrooms, followed by the disabled washroom, and finally the male washrooms.
Solar power project We are finalising the contract with Amosola to ensure proper liability coverage, including property damage, third-party injury, and public material liability. Due to the structural strength of the existing roof of the clubhouse, we are also exploring the use of lightweight solar panels for this project.
Air-conditioning system reinstallation The appointed contractor, ProfitGo, will be placing the order of the VRV system with Daikin. Daikin has indicated the need for a complete shutdown of both the inner and outer restaurant for around two weeks in January 2022, and we will work out alternative dining arrangements for this period, which might well include a BBQ frenzy fortnight.
I am looking forward to helping oversee these projects from a much more operational perspective shortly after returning from Australia.
又是忙碌的一個月。目前有多個項目獲得執行委員會的批准,即將上線和各位會員 見面。
總體規劃和租賃更新 本會已與萊坊測量師行簽訂合同,協助本會向地政總署提交關於租賃更新的文件,以 加快建造新甲板的進程。一旦獲批,我們就可以拆除花園酒吧帳篷,建造新甲板。拆除 了帳篷之後,本會著手處理現有艇架的租賃更新事宜。至於入口安置升降機、廚房新 儲存室和花園吧貯物區等工程仍在規劃階段。
海堤修理工程 執行委員會已核准一家承建商維修海堤,該工程的修葺項目包括修復毗鄰停車場的 海堤、重鋪船塢上混凝土路面、修復船區附近混凝土船台及會所餐廳附近的混凝土 滑道。
碼頭樁柱長期替代項目 執行委員會已批准承建商進行場地勘察,為該項工程做前期準備。
船架安全通道 承建商將在2021年12月之前建造一條模擬通道,供 Matthew 和船廠工作人員參考。
本會更衣室和洗手間的翻新項目 在完成本會更衣室及其通風系統的翻新設計後,我們現正展開該工程投標的程序。執 行委員會已批准購置臨時淋浴和廁所設施,在工程進行期間,大家仍能使用相關設施。 是次翻新工程將分階段完成,先是女洗手間,然後是殘疾人士洗手間,最後是男洗手 間。
太陽能發電項目 我們正在與Amosola商討合約細節及釐定責任範圍,包括財產損失、第三者遇事責任 和公共財務損失責任。考慮到會所現時屋頂的結構強度,該項目可能會取用更輕身的 太陽能電池板。
重新安裝空調系統 承建商ProfitGo將購置Daikin公司的VRV系統,根據Daikin建議,本會的餐廳需在2022 年1月期間關閉約兩週,本會將儘快公佈期間的用餐安排,燒烤或許是不錯的選擇。
我即將前往澳洲,在旅程結束之後,將回歸本位,繼續跟進、監督上述工程和項目 進展。