RENOVATION CLEAN ROOM

INNOVATION & SCHEDULE ADHERENCE

The project schedule was fast tracked. HEAPY created pre-purchase equipment packages for fan filter units, cleanroom wall and ceiling systems, air handling units, condensing units, and dessicant dryer units to mitigate the impact of long lead times for equipment, allowing the project to stay on schedule and hit critical path milestones.

Advertisement

PRECISE TEMPERATURE & HUMIDITY CONTROL

Two of the cleanrooms required 72+/-2F and 50 +/- 5RH control, while one the rooms required 72+/-2F and 20%RH maximum control. Careful consideration to room pressurization cascade and vapor barrier for each space was required to ensure proper compliance to cGMP. As part of the design, HEAPY designed and coordinated the cGMP validated monitoring system for temperature, humidity, pressure, and particulate count, allowing for live, online trending and monitoring.

SERVICES

Mechanical, Electrical & Plumbing Design

Technology Design

Commissioning

LEED® Program Management

SIZE

115,000 SF

COST

$55,000,000