Doing Business in Russia 2011_World Bank Group

Page 29

Time to complete:

30 days

Cost to complete:

no charge

Agency:

Moscomarchitectura

Comment:

On the Sketch No. 2 prepared by the Moscow Geological Institute, the Moscow Architecture Committee (MoskomArchitektura) draws the communication lines and power grids in accordance with the technical conditions obtained from the company.

Procedure

11

Request and obtain Sketch No. 2 from the Moscow Geological Institute

Time to complete:

30 days

Cost to complete:

RUB 20,000

Agency:

Moscow City Geological Unit

Comment:

Sketch No. 2 is prepared by the Moscow Geological Institute (Mosgorgeotrest).

Procedure

12

Request and obtain approval from MoskomArchitektura on engineering of the facility

Time to complete:

14 days

Cost to complete:

RUB 4,500

Agency:

Moscomarchitectura (Moscow Committee on Architecture and City Planning)

Comment:

Procedure

13

Request and obtain Regulation No. 2 and certificate of approval of Architectural City Planning Decision

Time to complete:

30 days

Cost to complete:

no charge

Agency:

Moscomarchitectura

Comment:

The following documents must be submitted to obtain Regulation No. 2 at the MoskomArchitektura: - Architecture and construction designs and drawings. - Approved (by all instances) designs and drawings of the general plan (as mentioned in previous procedures). - Approved design conditions. - Decision on construction.

Procedure

14

Request and obtain disposition of Prefect on the inception of construction design (decision on construction)

Time to complete:

30 days

Cost to complete:

no charge

Agency:

Prefecture 26