Time to complete:
30 days
Cost to complete:
no charge
Agency:
Moscomarchitectura
Comment:
On the Sketch No. 2 prepared by the Moscow Geological Institute, the Moscow Architecture Committee (MoskomArchitektura) draws the communication lines and power grids in accordance with the technical conditions obtained from the company.
Procedure
11
Request and obtain Sketch No. 2 from the Moscow Geological Institute
Time to complete:
30 days
Cost to complete:
RUB 20,000
Agency:
Moscow City Geological Unit
Comment:
Sketch No. 2 is prepared by the Moscow Geological Institute (Mosgorgeotrest).
Procedure
12
Request and obtain approval from MoskomArchitektura on engineering of the facility
Time to complete:
14 days
Cost to complete:
RUB 4,500
Agency:
Moscomarchitectura (Moscow Committee on Architecture and City Planning)
Comment:
Procedure
13
Request and obtain Regulation No. 2 and certificate of approval of Architectural City Planning Decision
Time to complete:
30 days
Cost to complete:
no charge
Agency:
Moscomarchitectura
Comment:
The following documents must be submitted to obtain Regulation No. 2 at the MoskomArchitektura: - Architecture and construction designs and drawings. - Approved (by all instances) designs and drawings of the general plan (as mentioned in previous procedures). - Approved design conditions. - Decision on construction.
Procedure
14
Request and obtain disposition of Prefect on the inception of construction design (decision on construction)
Time to complete:
30 days
Cost to complete:
no charge
Agency:
Prefecture 26