ENI - drilling design manual

Page 212

ARPO

ENI S.p.A. Agip Division

IDENTIFICATION CODE

PAGE

212 OF 230

REVISION STAP-P-1-M-6100

0

17.3.2. Cluster/Platform Final Well Report Structure 1 CLUSTER/PLATFORM INFORMATION

2

1.1 GENERAL DATA 1.2 GENERAL RIG SPECIFICATION 1.3 BOP SKETCH 1.4 LIST OF MAIN CONTRACTORS 1.5 OPERATIONS ORGANIZATION CHART 1.6 LOCATION MAP 1.7 CLUSTER/PLATFORM WELL BAY LAY-OUT AND ORIENTATION GENERAL DRILLING & COMPLETION ACTIVITY REPORT 2.1

3

FINAL WELLS STATUS 2.1.1 Well Sketches 2.1.2 Wells Head Sketches And Elevations 2.1.3 Completion Schemes 2.1.4 General Cluster/Platform Time Vs Depth Diagram 2.2 DETAILED OPERATIONS HISTORY 2.2.1 Moving 2.2.2 Conductor Pipe Phase 2.2.3 Surface Phase 2.2.4 Intermediate Phases 2.2.5 Final Phase 2.2.6 Testing 2.2.7 Completion 2.2.8 Abandoning 2.3 PRESSURE AND TEMPERATURE GRADIENTS 2.4 DRILLING PROBLEMS AND RECOMMENDATIONS 2.5 COMPLETION REMARKS DATA ANALYSIS

4

3.2 CASING DATA 3.3 CEMENTING DATA 3.4 DRILLING FLUIDS 3.5 BIT AND HYDRAULIC DATA 3.6 BOTTOM HOLE ASSEMBLY 3.7 DIRECTIONAL DRILLING 3.8 WELL TESTING DATA 3.9 COMPLETION DETAILS 3.10 TIME ANALYSIS ATTACHMENTS (Service companies must be requested to supply copies of their own reports as this enhances the quality of the information contained in the report).


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.