Part 6 – Project Timeline The planning proposal is to be finalised 12 months from the issue of the Gateway Determination issued by DPIE in October 2021. An indicative project timeline is provided below. Action

Anticipated Timeframe

Gateway determination

Received October 2021.

Revisions to PP in response to Gateway Determination conditions

January 2022 - May 2022.

Commencement and Completion dates for public exhibition period

Timeframe is 28 days as specified in Gateway Determination. Estimate May/June 2022.

Timeframe for consideration of submissions

Four weeks following completion of public exhibition, including two to three weeks to further consult with State Government and servicing authorities. Estimate July 2022.

Report to Council meeting

Preparation of Council report including leadin time to meeting. Estimate August 2022

Referral to the PCO for drafting

Estimate September 2022

Submission to DPIE for finalisation

Estimate October 2022

Submission to PCO for publication onto NSW Legislation website

Estimate October 2022

160 Burwood Road, Concord Bushells Redevelopment - Amended Planning Proposal v5-1 | LFA (Pacific) Pty Ltd

107


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
160 Burwood Rd Concord Amended PP v5 by cityofcanadabay - Issuu