1 minute read

GOAL 13: Port Development

GOAL 13: Port Development: Re-Zoning Direction

Key Issues

 Land Use  Project Direction  Timing 1. Continue discussion with property owner(s) 3/22 2. Review draft proposal 3/22 3. Finalize proposal and land use changes 4/22 4. Planning Board Review 11/22 5. DECISION: 1st Reading 12/22 6. Submit to State 12/22 7. DECISION: 2nd Reading – Final Approval 1/23

Responsibility: Planning Director

September 2022 Update

Draft code (Zoning and Future Land Use designation) to be circulated to stakeholders after completion of outreach.

This article is from: