GOAL 15: Seaplanes: Facility and Service
Key Issues
Design Funding Construction 1. Obtain permits 2. DECISION: Funding and Design 3. Complete construction 4. Ribbon-cutting and 1st Flight
Responsibility: City Engineer
10/22 10/22 TBD TBD
September 2022 Update