GOAL 6: 13th Street Upgrade
GOAL 6: 13th Street Upgrade: Direction and Funding (North and South)
Key Issues
Project Costs: $10 million Funding Source Grant Opportunities Federal Infrastructure North - Design 1. Identify initial funding options – South Ongoing 2. Incorporate in CIP Update 12/22 3. Updated Plan Completed 1/23
Responsibility: City Engineer
November 2022 Update 13th Street (Georgia Avenue to Orange Avenue)
• Request proposal to update plans and specifications for bidding to be accomplished by
December 2022. • Continue to search for funding opportunities.