GOAL 11: King’s Landing Development
GOAL 11: King’s Landing Development: Site Plan and Preparation
Key Issues
Site Plan 1. DECISION: Site Plan Approval Complete 2. DECISION: Land Conveyance Complete 3. Initiate site preparation work 2023
Responsibility: City Manager
November 2022 Update
Audubon began the subsurface debris removal process with a contribution from the FPRA and DEP approval has been obtained.
Audubon must meet the following deadlines for Phase I as outlined in the agreement:
• Closing date: April 7, 2022 (date deed recorded in OR Book 4804, Page 2930) - COMPLETE • Deadline to submit application for building permit: August 22, 2022 - COMPLETE • Commence construction of Phase 1: September 20, 2023 • Complete construction of Phase 1: February 5, 2026