News
Ring Road contraflow extended by 7 weeks
T
he highly disruptive contraflow system the A4174 Ring road at Bromley Heath which was due to be lifted by 12th March after being in place for 33 weeks will now not be removed until the last weekend in April (seven weeks later than originally planned). Announcing the news on 5th February, just five weeks before the restrictions were due to be removed, and following numerous recent progress reports which had said the work was “on schedule”, South Gloucestershire Council blamed the delay on “unforeseen difficulties”. The contraflow is in place to allow essential repairs and strengthening work to be carried out on one of two viaducts which carry the A4174 over the River Frome at this location. A separate major project to provide a wider shared path and a protective barrier for cyclists and pedestrians
Aerial view of the contraflow and viaduct repair work (mid-February)
using the viaduct is being undertaken at the same time. The combined cost of both schemes was originally put at £5.9m with the contraflow lasting for 52 weeks, but the council was able to secure £2.8m of additional funding
from the West of England Joint Committee allowing the duration to be reduced to 33 weeks. The recently announced delay means that this 19-week saving has now reduced to 12 weeks. A council spokesperson said: “We’re now at the stage where
the nature of the work which is left to do must all be carried out consecutively and many of the tasks, such as concreting one of the parapets and plinths, waterproofing and resurfacing the new deck are all weather dependent.” “The original end date of March for the contraflow to be lifted on the A4174 ring road will need to be extended while work is completed and we would like to apologise in advance for any inconvenience this will cause. We are continuing to work seven days a week to complete the remaining work as quickly as possible so that the contraflow can be removed by the end of April.” “Due to the unforeseen issues we found, there will be some cost increases but these will be covered within the contingency budget for the project. No additional funding needs to be found to complete the project.”
YOU’RE ALREADY A CAREGiver, you just don’t know it yet.
Turn your passion into a career At Home Instead Senior Care, caring is our passion and it all starts with our CAREGivers. People like you, who love to help others, make excellent CAREGivers for Home Instead Senior Care. Turn your passion into a rewarding role and join our team. You will have our full support, excellent training and enjoy competitive rates of pay. Make new friends and give your skills a new sense of purpose.
For more information or a chat about the role please call 0117 989 8210 or visit www.homeinstead.co.uk/bristolnorth and watch the film made by our CAREGivers. To advertise in this magazine or on our websites, phone The Journal’s sales team on 01454 300 400