3 minute read

Port Hedland road-rail safety improvements continue

The first package of works on the Port Hedland Road and Rail Safety improvement project is now complete.

Stage 1 has been officially opened, which includes the construction of a bridge over BHP's rail line at Buttweld Road.

Advertisement

The 34-metre-long bridge was constructed by Highway ConstructionAlbem Operations Joint Venture as part of the $31.48 million BHP funded Stage 1 works.

Construction of two roundabouts on Powell Road at the intersections of Dalton and Hamilton roads were also completed as part of Stage 1 in June 2022.

Construction has begun on the $76 million second package of works, which has also been awarded to Highway Construction-Albem Operations Joint Venture.

The project involves the realignment of approximately 4.75 kilometres of the Great Northern Highway (north of the Port Hedland International Airport and the Walkabout Village), including the construction of new access roads due to the realignment.

A second bridge over the BHP rail line will also be constructed, eliminating the existing level crossing.

This second package of works is jointly Government Minister Catherine King said, “This is an important package of improvements that will bring major safety and economic benefits to Port Hedland.

“The Australian Government is pleased to partner with BHP and the WA Government to support these important upgrades."

WA Transport Minister Rita Saffioti said, “This project is a fantastic example of governments working closely with industry to deliver better outcomes for the local community, and while we're at the halfway point of this project, it is already delivering improved road safety.

“Removal of these rail crossings will eliminate the risk of accidents, and the need for vehicles to be stuck at rail crossings for long periods of time, whilst long freight trains pass by.

State Pilbara MLA Kevin Michel commended Main Roads and the contractors for their work to date, and the delivery of this project in our heated construction environment.”

Construction is expected to take just over 12 months, with work estimated to be completed in late-2023

funded by the Australian Government ($50.2 million), the Western Australian Government ($12.54 million) and BHP ($13.26 million).

Construction is expected to take just over 12 months, with work estimated to be completed in late-2023, and will be managed by Main Roads WA with support from project partner BHP.

Federal Infrastructure, Transport, Regional Development and Local

WA OWNED AND RUN

WA’s premier brake and clutch specialists proudly servicing the states industrial clutch and brake applications.

From major truck workshops, heavy haulage, cranes, the mining industry and more… our team of knowledgeable and qualified technicians share over 100 years combined experience and focus on delivering prompt service alongside the supply of top name brakes and clutches - throughout Australia and Asia. With over 20 years in the industry we have a well-earned reputation for the development, manufacture and supply of quality standard and customised designs to suit a wide range of applications. For the best advice and friendly service contact us today. +61 8 9353 4411 ■ sales@knightbrakeandclutch.com.au

knightbrakeandclutch.com.au 24 HR / 7 DAY ACCESS

3 MINUTE EXPRESS WASH • Road train friendly • Full chassi rinse standard • Credit card facility • Fleet accounts available

QUICK DRIVE THRU FULLY AUTOMATED TRUCK WASH

www.twepicton.com.au

Roadtrain / truck & dog $140 inc gst

Semi $110 inc gst 6 Wheel Trucks / Bus $88 inc gst

2 Nicholson Road, East Picton T: Darren 0417 909 128 | E: info@twepicton.com.au