Goose Lake to Etzikom Coulee Transmission Project - June 2012 open house booklet

Page 1

Welcome

Goose Lake to Etzikom Coulee Transmission Project Open Houses

Did you know? Alberta is an importer of electricity. In 2011, Alberta imported nearly thirty times the amount of power it exported. Alberta depends on its transmission connections with British Columbia and Saskatchewan to meet its demand for electricity.

Your input is important to us.


Electricity at a glance GENERATION Generation ATCO Power

Generating facilities convert various forms of energy into various forms of energy into electric power. electric power.

ATCOTransAlta Power TransAlta GENERATION ENMAX Energy Capital ATCOPower Power Corporation Wind turbines GENERATION various forms of TransAlta ENMAX Energy GENERATION ATCO Power energy into Wind turbines various forms ATCO Power TransAlta electric power.of ENMAX Energy various forms energy into of Transmission Cogeneration TransAlta GENERATION TRANSMISSION Wind turbinesplants

energy into the electric power. lines connect ENMAX Energy ATCO Power AltaLink electricproduced power.of various forms power ENMAX Energy Wind turbines TransAlta ATCO Electric energy into WindPower turbines GENERATION ENMAX (Calgary) Transmission TRANSMISSION electric power. ATCO Power ENMAX Energy EPCOR (Edmonton) lines connect AltaLink various formsthe of TransAlta Transmission AltaLink Wind turbines TRANSMISSION power produced ATCO Electric energy into Transmission lines connect the TRANSMISSION ATCOAltaLink Electric ENMAX Power (Calgary) electric power. lines connect the ENMAX Energy power produced SUBSTATION AltaLink ATCO Electric ENMAX Power (Calgary) EPCOR (Edmonton) power produced Wind turbines AltaLink Transmission ATCO Electric ENMAX Power (Calgary) TRANSMISSION points between EPCOR (Edmonton) ATCO Electric lines connect the ENMAX Power (Calgary) EPCOR (Edmonton) AltaLink transmission and ENMAX Power (Calgary) power produced EPCOR (Edmonton) ATCO Electric SUBSTATION Transmission EPCOR (Edmonton) TRANSMISSION ENMAXAltaLink Power (Calgary) systems.the lines connect SUBSTATION points between AltaLink EPCOR (Edmonton) ATCO Electric power produced SUBSTATION AltaLink transmission and ATCO Electric ENMAX Power (Calgary) AltaLink points between DISTRIBUTION AltaLink ATCO Electric ENMAX (Calgary) EPCORPower (Edmonton) carry electricity points between transmission and ATCO Electric ATCO Electric ENMAX Power (Calgary) systems. SUBSTATION EPCOR (Edmonton) to homes, farms transmission and ATCO Electric ENMAX Power (Calgary) EPCOR (Edmonton) AltaLink ENMAX Power (Calgary) andsystems. pointsbusinesses. between ENMAX Power (Calgary) EPCOR (Edmonton) ATCO Electric DISTRIBUTION EPCOR (Edmonton) systems. transmission and EPCOR (Edmonton) SUBSTATION carry electricity ENMAX Power (Calgary) AltaLink DISTRIBUTION to homes, farms EPCOR (Edmonton) ATCO Electric points between carry electricity systems. ATCO Electric DISTRIBUTION and businesses. ENMAX Power (Calgary) transmission and carry electricity to homes, farms ENMAX Power (Calgary) ATCO Electric EPCOR (Edmonton) to homes, farms and businesses. EPCOR (Edmonton) ATCO Electric ENMAX Power (Calgary) FortisAlberta DISTRIBUTION Retailers give systems. and businesses. RETAILERS carry electricity ENMAX Power (Calgary) EPCOR (Edmonton) ATCO Electric consumers a Direct Energy to homes, farms EPCOR (Edmonton) ATCO Electric choice of ENMAX (Calgary) and businesses. ENMAXPower (Calgary) DISTRIBUTION ENMAX Power (Calgary) electricity service EPCOR Energy (Edmonton) carry electricity Retailers give EPCOR (Edmonton) EPCOR (Edmonton) RETAILERS providers. Just Energy Alberta toconsumers homes, farms a ATCO Electric Direct Energy Rural Electrification Associations Retailers give and businesses. RETAILERS choice of ENMAX Power (Calgary) ENMAX (Calgary) Retailers give consumers a RETAILERS Direct Energy electricity service EPCOR (Edmonton) EPCOR Energy (Edmonton) consumers choice of a Direct Energy ENMAX (Calgary) providers. Just Energy Alberta Electricity choiceservice of electricity YOU Retailers giveis ENMAX (Calgary) EPCOR Energy (Edmonton) RETAILERS delivered electricity service providers. consumers to a EPCOR Energy (Edmonton) JustDirect Energy Alberta Direct Energy Energy homes, providers. choice farms of Just Energy Alberta ENMAX (Calgary) ENMAX (Calgary) and businesses. Retailers give electricity service Electricity is RETAILERS EPCOR Energy (Edmonton) YOU EPCOR Energy (Edmonton) consumers a providers. delivered to Energy JustDirect Energy Alberta Electricity is choice of Just Energy Alberta YOU homes, farms ENMAX (Calgary) Electricity is delivered to electricity service and businesses. EPCOR (Edmonton) City Energy ofYOU Lethbridge Utilities delivered to homes, farms providers. Just Energy Alberta homes, farms and businesses. Electricity is YOU and businesses. delivered to homes, farms Electricity is and businesses. YOU delivered to homes, farms and businesses.

Transmission

Transmission lines connect the power produced at generating facilities to substations.

Substations

Substations are the connection points between transmission and distribution systems.

Distribution

Distribution lines carry electricity to homes, farms and businesses.

Retailers

Retailers give consu mers a choice of electricity service providers.

You

Electricity is delivered to homes, farms and businesses.


Goose Lake to Etzikom Coulee Transmission Project The proposed transmission project includes a new transmission line from the existing Goose Lake Substation to the proposed Journault Substation. The proposed Journault Substation is part of the Etzikom Coulee to Whitla Transmission Project. AltaLink is currently completing public consultation for this project. AltaLink has identified two potential locations for the proposed Journault Substation. If approved, only one substation will be built. Discussions regarding the potential for a transmission line across the Blood Reserve are continuing with the Band.


Southern Alberta Transmission Reinforcement (SATR) The Southern Alberta Transmission Reinforcement (SATR) includes many proposed projects in southern Alberta that will provide Albertans with access to new wind generated power. Existing transmission lines and substations in the southern part of the province do not have the capacity to connect power generated from new wind farm projects to the electric system. To connect this wind power to you, a new transmission project is being proposed. The Alberta Electric System Operator (AESO) filed the need for the SATR with the Alberta Utilities Commission (AUC) in December 2008. The AUC held a public hearing to review the need for these projects in 2009 and approved the need later that year. The Goose Lake to Etzikom Coulee Transmission Project is part of the SATR.


Key players AltaLink AltaLink’s transmission system efficiently delivers electricity to 85% of Albertans. Dedicated to meeting the growing need for electricity, AltaLink connects Albertans to renewable, reliable and low-cost power. With a commitment to community and environment, AltaLink is ensuring the transmission system will support Albertans’ quality of life for years to come. Learn more at www.altalink.ca.

The Alberta Electric System Operator (AESO) The AESO is an independent, not-for-profit entity responsible for the safe, reliable and economic planning and operation of the Alberta Interconnected Electric System. The AESO determines the need for transmission reinforcement and directs Transmission Facility Owners, such as AltaLink, to submit a Facility Application for permitting and licensing to construct and operate transmission facilities. Find out more at www.aeso.ca.

The Alberta Utilities Commission (AUC) The AUC is a quasi-judicial agency that ensures the fair and responsible delivery of our utility services. The AUC is the provincial regulator responsible for reviewing Facility Applications. AUC approval is required before construction of facilities can occur. Learn about the AUC at www.auc.ab.ca.


Next steps 1 We will use the stakeholder input gathered to refine our preliminary routing. We will then consult with stakeholders again and collect input about the refined routes. 2 After our consultation process is complete, we will file a Facilities Application with the AUC.

3 The AUC will review our application through a process in which stakeholders can participate. The AUC can approve, approve with conditions or deny a Facilities Application.

Did you know? The average four-person family in Alberta today has 20 ‘instant-on’ electronics such as laptops, DVD players, music device chargers and cell phone chargers. This is in addition to the other appliances necessary to run a home – fridges, stoves, microwaves, washers and dryers – all of which require a reliable supply of electricity.


Anticipated project schedule Notify and consult with stakeholders about preliminary routes

Spring 2012

Notify and consult with stakeholders about refined routes

Summer 2012

File Facilities Application with the Alberta Utilities Commission

Spring 2013

Although we attempt to follow the anticipated project schedules they are subject to change. We will continue to provide you with updated schedule information as the project progresses.

Project cost The total estimated cost for the Goose Lake to Etzikom Coulee Transmission Project is approximately 300 million to 450 million dollars, which would be approximately 30 to 45 cents per month on the typical residential utility bill.


Public consultation AltaLink understands that landowners, occupants and residents have information we need to consider when evaluating potential routes. Input from stakeholders is very important to the process of selecting a solution with the lowest overall impact for this project. We will work with you to ensure your questions and concerns are understood and responded to in a timely fashion. A summary of stakeholder comments will be incorporated into the application we submit to the AUC. ONE-ON-ONE CONSULTATION We will contact occupants, residents and landowners who are on or directly adjacent to the proposed transmission line route options to gather their input. If you would like to schedule a one-on-one consultation please talk to an AltaLink representative.


What information do we need from you? When identifying route options, AltaLink takes several factors into consideration in an effort to find routes with the lowest overall impact. Some of the factors we take into consideration include:

Important Criteria Agricultural

• Impact on crop production • Reduced efficiency of field operations

Residential

• Proximity to residencies • Impact on developable lands and constraints on future development

Environmental

• Alteration of natural areas and impacts to environmental features

Cost

• Construction cost and land acquisition costs

Electrical

• Reliability and repairability of the lines

Visual

•V isual impact of structures and lines as seen from residences and recreational areas

Special considerations

• E lectrical interference with radio transmitting stations and other telecommunication equipment


Project details This proposed project includes:

a new 240 kV (240,000 volts) double circuit transmission line approximately 170 to 220 kilometres (105 to 136 miles) in length from the existing Goose Lake Substation to the proposed Journault Substation

Structure information A double circuit 240 kV steel lattice transmission structure is pictured below. A typical structure will have a: • • • • •

height of 44 to 60 metres (147 to 197 feet) width of 22 to 24 metres at the widest arm (72 to 79 feet) base of 10 by 10 metres, up to 14 by 14 metres (32 by 32 feet, up to 46 by 46 feet) distance between structures averaging 365 metres (1,198 feet) right-of-way width of 60 metres (197 feet) • A right-of-way refers to the strip of land required for the construction and operation of a transmission line. The right-of-way is subject to development restrictions to help ensure the safe and reliable operation of the transmission line.


Project details In addition to the main transmission line right-of-way, there are other workspaces we will require at some structure locations:

Additional required riGht-Of-Way: This is additional area beyond the transmission line right-of-way that we use to construct the structures and operate equipment.

OPtiOnal temPOrary WOrksPace: This is area beyond the transmission line right-of-way next to the transmission structures to help us build the line more efficiently. It allows us to easily store material, assemble and construct the structures.

access: This is additional area we require to access the transmission line right-of-way. Landowners will receive fair compensation for additional required right-of-way, optional temporary workspace and access.

This diagram shows an example of an optional temporary workspace.


843

520

New route crossing the Blood Reserve 23

GRANUM

PICTURE BUTTE

519

864

You received a project information package NOBLEFORD in April 2012 that indicated discussions were underway with the Blood Tribe for a transmission line route option845 across the Reserve.TABER

3A Peigan 25 811 BARNWELL 2 Timber A new route option crossing the Blood Reserve has recently been added for Limit "B" COALHURST 785 consideration and is included in the mapping products on display512 at this open house. COALDALE FORT 4 MACLEOD

510

Information and maps with this new route option are in the process of being sent to landowners near 3 the preliminary routing. LETHBRIDGE 810

Piikani Reserve (formerly Peigan IR No. 147)

786

PINCHER CREEK

520

2

505

811

519

3A

786

HILL SPRING 810

507

MAGRATH

503

800

506

Aetna

2

CARDSTON

504

62

STIRLING RAYMOND Craddock

Spring Coulee

WARNER

36

5

Leavitt GLENWOOD

HILL SPRING

Blood No. 148A 5 6

Stand Off

Blood No. 148

5 505

509

McNab

506

Spring Coulee 513

LETHBRIDGE

CARDSTON

New Dayton

864

COALDALE

512

STIRLING RAYMOND Craddock

TABER BARNWELL

845

25

4

511

Piikani Reserve (formerly Peigan IR No. 147)

PINCHER CREEK

Blood No. 148

COALHURST

800

6

NOBLEFORD

GLENWOOD FORT MACLEOD

3

MAGRATH

PICTURE BUTTE

36

5

Stand Off

23

785

510

509

843

507 GRANUM

Peigan Timber Limit "B"

511

513

New Dayton McNab

820

WARNER

501

504

62

503

Leavitt 2

Aetna

820

501

Blood No. 148A

U N I T E D S TAT E S O F A M E R I C A

U N I T E D S TAT E S O F A M E R I C A

LEGEND Potential Substation

Hamlet or Locality

Existing Substation

Road

Potential Transmission Line

First Nations Reserve

Hamlet or Locality

Water Body

Road

LEGEND

Potential SubstationUrban Area Existing Transmission Line Existing Substation

Potential Transmission Line

First Nations Reserve


Landowner compensation RIGHT-OF-WAY AGREEMENT PAYMENT The right-of-way agreement includes compensation for the interest in the land that we require to maintain and operate the transmission line. We provide fair market value per acre for the total area of the right-of-way crossing a landowner’s property. The landowner retains ownership of the land. The one-time right-of-way agreement payments for the preferred route include: • $10,000 early access and routing consent payment: allows AltaLink to complete preconstruction surveys and is paid to landowners who sign an agreement prior to the AUC decision • $250-5,000 per title entry fee payment: amount depends on the number of acres required for the transmission line • $1,500 minimum general disturbance payment • $2,500 (per titled unit) land damages payment: ($2,500 pre‑construction; post construction paid if applicable) With the exception of the $10,000 early access payment and a $50 signing fee, all other one-time payments are subject to the AUC’s approval of this project.

Annual Structure Payments (ASPs) Steel lattice structures • $1,300 per structure per year on cultivated land • $520 per structure per year on uncultivated land Factors we take into consideration when determining ASPs include: • • • • • • • •

the loss of use of the area enclosed by the structure once operational the inconvenience and additional costs associated with weed control additional time required to operate equipment around transmission structures additional seed required overlap of pesticide/herbicide and fertilizer used when farming around the structure effects on cultivation potential impacts to irrigation systems potential impacts to aerial spraying


Electric and Magnetic Fields (EMF) AltaLink recognizes that people have concerns about exposure to Electric and Magnetic Fields (EMF) and we take those concerns very seriously. Everyone in our society is exposed to EMF from many sources, including: • • • •

power lines and other electrical facilities electrical appliances in your home building wiring the earth’s natural magnetic field

National and international organizations such as the World Health Organization and Health Canada have been conducting and reviewing research about EMF for more than 40 years. Based on this research, these organizations have not recommended the general public take steps to limit their everyday exposure to EMF from high voltage transmission lines. We are here to answer your questions and help you get the information you need about EMF.


Environmental Evaluation An Environmental Evaluation identifies environmental features within the project area through existing data and field surveys. Additional information is gathered from consultation with provincial and federal regulators, landowners and the public. This information is used to assist in route development. Potential effects from the project are identified, so that mitigations can be developed to minimize or eliminate these effects. Information within the Environmental Evaluation typically includes: • • • •

wildlife and vegetation inventories wetland, watercourse and groundwater assessments threatened and endangered species identification terrain and soil evaluations


Thank you for attending our open house To learn more about this project, please visit www. altalink.ca/projects or contact us: Phone: 1-877-269-5903 (toll-free) Email: satrinfo@altalink.ca


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.