Texas A&M University Agriculture Headquarters Weekly Report: 7/12/10-7/16/10

North View of HQ

Elevator Installation

North View of VC Columns

Cistern Columns

Removed west exit and installed the new exit off lot 97.

Erected cistern canopy supports.

Completed the stone installation on the north exterior VC columns.

Insulate all chill water lines and medium pressure duct.

Installed the gates on the service yard..

Elevator installation is ongoing.

Waterproofing the exterior walls on the VC is 95% complete.

Installation of window frames and glass at the 1st and 2nd floor VC is complete.

Continue to hang and tape/float sheetrock through out the HQ.

Brick/stone installation on the HQ is coming to a completion.

Service Yard Gates & Louvers

Cistern Columns Delivery