Risk Process Check Match the process to its description: ___Plan risk management

A. The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact

___Identify risks

B.

The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating the risk process for effectiveness throughout the project

___Perform qualitative risk analysis

C.

The process of developing actions and options to enhance opportunities and to reduce threats to project objectives

___Perform quantitative risk analysis

D

The process of defining how to conduct risk management activities for the project

___Plan risk responses

E.

The process of determining which risks may affect the project and documenting their characteristics

___Control risks

F

Process of numerically analyzing the effects of identified risks on overall project objectives

Šâ„— 2009-2013 Richard Perrin – Evolutionten: Project Risk Management