Clifford L. Allenby Building E-blast Volume 1, Issue 4

June 2019

Introduction In this month’s E-blast, learn about the construction progress on the Clifford L. Allenby Building and how you can get involved with the new childcare facility. Also, discover how the building is designed to fill your workspace with fresh air, creating a comfortable and healthy indoor environment.

Concrete placement for level 3 shear walls and install of level 4 deck on east half of building.

Moving edge of deck working platform from level 3 to level 4.

Project Look-Ahead Work in June will include the completion of walls and columns to level four, constructing the level four deck, and installing masonry walls on the lower level.

Concrete placement for level 3 slab on the west half of the building.

Construction Update We are nearly finished placing the concrete slab, shear walls, and columns between levels three and four, and we are beginning to construct decking on the east side of level four. Layout and installation of door frames and preparation for masonry walls for the lower level is in progress. Also, installation of the construction man-lift is under way.

We welcome your questions, comments, and suggestions for topics for future E-blasts. Please submit to OStreet@chhs.ca.gov

Level 3 column and shear wall formwork being installed at West side of building.

Questions, comments, suggestions? Please submit to OStreet@chhs.ca.gov

Clifford L. Allenby Building E-blast_Volume 1_Issue 4_June 2019