FACTS & FIGURES

Project Funds Expended to Date

$10,284,779.28

Percent Work Completed 68%

Percent Contract Time Elapsed 85% Number of Days Worked 227

Summer Expectations

The northern-most of the three underpasses under construction this season already has all the castin-place concrete finished and the initial back fill complete. The two other boxes will be formed up and have concrete poured before the end of July. All dirt work will be finished soon thereafter. Paving the three underpass locations will begin mid-August. Fence work will continue to move southward – progressing from underpass to underpass on each side of the highway – with the contractor anticipating completion just prior to the contract completion date of Oct. 31, 2023.