Wembley Park construction newsletter Summer

Page 1

Construction Newsletter Issue 13 - Summer

Alive with

Construction

Business Administrator Apprentice & Engineer Apprentice with Quintain and Brent Works

Bursting with New Talent

Wembley Park: "Describe your average day."

Meet the Construction apprentices and some of the team behind the scenes.

Carpentry Apprentice: “Since joining, I have been exposed to a variety of carpentry jobs. My site manager is very helpful and was an apprentice himself so knows the process I’m going through. I can always approach him for advice.”

Quintain’s contractors at Wembley Park are committed to providing over 136 construction apprenticeship opportunities across site. We have delivered 25 apprenticeship opportunities to date, across different trades ranging from carpentry, engineering, business administration, hoist driving and traffic marshalling.

Brickwork Apprentice: “I have really enjoyed my time at Wembley Park so far. I have achieved high marks in two practical tests and building principle tests. I have learned a lot from colleagues and supervisors who are very helpful and encouraging.”

There are over 55 new apprenticeship opportunities coming up over this summer, specialising in bricklaying, electrics, drylining and carpentry. These opportunities are supported by the team at Brent Works who provide a tailor-made service to our contractors to support their upcoming apprenticeship vacancies and local employment offer.

Speaking on his experience working with the apprentice program Contract Manager, said "Our apprentice has been eager and conscientious from our first meeting, organised via Brent Works. His punctuality and attendance have been excellent since starting on site which is the basis for anyone interested in a successful career in construction.”

We caught up with some of Wembley Park's rising talent and here’s what they had to say:

About Brent Works The Brent Works service is aimed at supporting Brent residents to access apprenticeships and employment opportunities within the Borough and pan London.

Wembley Park: "What advice would you give to anyone who wants to get into the construction industry?" Civil Engineering Apprentice: "Be patient, ask as many questions as possible and be punctual. Try to learn as much as you can and progress." Carpentry Apprentice: “Go for it! Especially if you are someone who enjoys physically challenging work. There are loads of different trades that can be explored.”

Wembleypark.com

The tailored service provides apprenticeship candidates with a one-to-one service aimed at establishing individual needs and aspirations, matching the candidate with a suitable opportunity. The Brent Works team also assist Brent residents to secure and sustain employment opportunities created by regeneration projects and highvacancy sectors in the Borough, including

Customer voicebox: 0800 021 3245

Construction, Retail and Hospitality and Health and Social Care. Contact the team via: Telephone: 0208 937 6295 Email: brent.works@brent.gov.uk For current construction opportunities, visit: https://jobs.wembleypark.com

A

Apprentice Carpenter

@wembleypark


Progress & planned works Olympic Way

Boxpark

Regeneration of Olympic Way

Planning permission granted for Boxpark Wembley, which will house 27 food and beverage providers, a 20,000 sq ft events space and 2,000 person capacity venue.

Contractor: Volker Fitzpatrick

Progress to date includes: - The completion of upgrades to the first section of Olympic Way - Installation of new bespoke light columns and banners - New paving and services including useable kiosk space for events - New trees from around the globe - New fence lines and interfaces with adjacent buildings - Relocation of services and installation of new infrastructure to serve Wembley Park - Early works relocating services to the next section of Olympic Way Key works taking place this quarter: - Installation of new benches and bins along Olympic Way - Public WiFi expansion - A new audio system along Olympic Way - Continuation of the Northern section of Olympic Way - Upgraded security systems

Contractor: RG Group

Progress to date includes: - Planning approval granted on 14 February 2018 - RG Group appointed as the Principal Contractor and works have commenced - Site compound to be established Key works taking place this quarter: - Ground works to progress further - Service connections to commence - Steel frame to be erected Completion - Winter 2018

NW07 & NW08

Contractor: Wates CCS Score: 44/50 Construction underway to deliver 361 residential units, retail, community space and public realm. Progress to date includes: - Concrete frame now complete - All offsite manufactured bathroom pods delivered and installed - All blocks are now watertight with brickwork nearing completion - Utility connections complete and the buildings now energised Key works taking place this quarter: - Scaffold to be removed and balconies installed on remaining residential blocks - Internal residential fit-out ongoing - External paving works outside of the side boundary are underway - Public realm works within the site boundary to be complete Completion - Phased September December 2018

Completion - Late 2019 CGI of Boxpark

W03

Contractor: McLaren Construction CCS Score: 42/50 Works continue to deliver 340 residential units and retail at ground floor level. Progress to date includes: - Concrete frame has now been completed - All bathroom pods have now been delivered to site and are being installed across all floors - Two benchmark apartments have been completed - Fitting out works including partitions, mechanical and electrical progressed to floor ten Key works taking place this quarter: - All windows to be installed - Continuation of internal fit out - Continuation of envelope installation which will help give the building a full waterproof seal - Continuation of installation of waste disposal system Completion - September 2019

W06

South West Lands (SWL)

Progress to date includes: - Completion of concrete lift and stair core - District Heating works completed and continuing throughout site - Installation of the rubbish disposal system on Wembley Park Boulevard including completion of tunnel under the Spanish Steps

Progress to date: - Frame of the first building now complete - Frame of the second building has reached the 7th floor and frame to third building has now started - Brickwork to SW03A is well underway and has started on SW03B - Internal fit out is progressing and a first sample apartment has been delivered - Buildings now linked to Envac waste system and District Heating Network - Welfare area in Red Car park in use and a bridge has been installed over South Way

Contractor: McLaren Construction CCS Score: 43/50 The site will comprise of two buildings, one being 150 homes and the second consisting of a 126,000 sq ft office block. The site will be working later, from 6pm - 7pm for an initial period of one month. Works of a quiet nature will be undertaken to lift materials with the crane.

Key works taking place this quarter: - Continuation of the concrete frame, constructing the floor slabs - Commence nvelope enstallation for the glazing support system and glazing - Further installation of the waste disposal system Completion - February 2020

Wembleypark.com

Customer voicebox: 0800 021 3245

Contractors: McAleer & Rushe CCS Score: 45/50 Construction work continues on site, which will consist of approx. 900 homes.

Key works taking place this quarter: - Last crane to be erected - Ongoing work on concrete frame - Ongoing brickwork and windows - Work to build temporary heating source adjacent to South Way/Red Car Park Completion - Phase One - Autumn 2019 Phase Two - Autumn 2020

@wembleypark


E01/ E02

Contractor: O'Keefe Construction Ltd CCS Score: 40/50 The site will consist of 633 apartments, car parking bays, commercial, podium gardens, MUGA and a Nursery.

E03 – Canada Gardens

Progress to date incudes: - All four tower cranes are now set up - Block 1 core now completed - Site cabins in place

Construction underway to deliver 743 apartments, 91 space coach park, retail space along with a podium garden and community outdoor amenity space.

Key works taking place this quarter: - Cores of Block 2 & 3 - Ground floor slabs ongoing - Fit out of site cabins

Progress to date includes: - Continuation of floor slabs on all blocks - Scaffolding commenced from Block G - Work under way on Block G Metsip inner wall panels - Commencement of installation of windows, insulation, and brickwork facades - Commencement of internal block works to Energy Centre - Handover of Energy Centre structure to a specialist installation contractor for fit out - Installation of Thermal Stores to Energy Centre - Early planting of Parkland 8 semi-mature trees - Commencement of delivery and installation of bathroom pods

Completion - October 2020

E05

Contractor: John Sisk and Sons CCS Score: 42 The scheme consists of 458 apartments, parking, commercial unit and gardens. Progress to date incudes: - Excavation and infrastructure works - Capping beam Key works taking place this quarter: - CFA piling - Ongoing excavation

E03 – Canada Gardens

Contractor: John Sisk and Sons Ltd CCS score: 45/50 Sisk have proudly achieved their highest CCS score, 45, for any of their projects to date.

Continued

Key works taking place this quarter: - Completion of the concrete on the podium transfer slab - Continuation of floor slabs to all blocks, with Block F & E scheduled to top out - Continuation of scaffolding to all blocks - Continuation of installation of Metsip inner wall panels in Block G-F-E-D - Continuation of installation of windows, insulation, and brickwork facades - Commencement of brickwork to external facades in Blocks G & F - Complete fit out of the Energy Centre - Commencement of internal fit out works to Blocks G & F - Commence weathering to terraces Blocks F&E - Handover of Energy Centre grey box to specialist installation contractor for fit out - Continuation of delivery and installation of bathroom pods Completion - September 2020

Completion - Summer 2021

Development plots Wembley Park Station

Quintain managed sites For any queries on Quintain managed sites please call the customer voicebox: 0800 021 3245

OLYMPIC WAY

Sites not owned by Quintain There are a number of sites around Wembley Park not owned by Quintain which are also being developed, and for clarity we’ve marked these on the map.

Boxpark NW07/NW08

Apex House Tide Construction Ltd 07415 486 148

Yellow Pavilion

Brent Civic Centre

Yellow Parking

ENGINEERS WAY

W03

E03

The SSE Arena AR

D

W06

Barratt 0208 795 7100/07766 470 762 Out of hours 0345 601 6084

UL

EV

London Designer Outlet

BO

E01/ E02

RK PA EY BL

W11

W

EM

SWL

Wembley Stadium

E05

Red Parking

Wembley Central Station

Wembleypark.com

Wembley Stadium Station

Customer voicebox: 0800 021 3245

@wembleypark


What's on in Wembley Park? Take Part in our Construction Workshops Each month, we offer exciting workshops teaching basic skills for members of the community. For more information, please visit: wembleypark.com/construction-workshops Basic Domestic Plumbing Date/Time : 15th August, 2018 5:45-8pm Location: Wembley Library, Brent Civic Centre, 32 Engineers Way HA9 0EG Basic Dry Lining Date/Time : 12th September, 2018 5:45-8pm Location: Wembley Library, Brent Civic Centre, 32 Engineers Way HA9 0EG More workshops will follow, including Wallpapering, Carpentry, and Bricklaying

Considerate Constructors Scheme As a Client Partner of the Considerate Constructors Scheme (CCS), Quintain is committed to promoting 'Construction Best Practice' by endorsing its principles and values across Wembley Park, with registration in the scheme being obligatory for all new contractors. Monitored on a daily basis, the CCS's code of practice focus on the following aspects: - Care about Appearance - Respect the Community - Protect the Environment - Secure everyone's Safety - Value their Workforce

The average combined scores from across the four framework contractor's sites are outlined below: - McAleer & Rushe 45/50 - McLaren 42/50 - Sisk 43/50 - Wates 44/50 Nationally only 27% of sites in the scheme scored 40 or more points, which is the benchmark for Wembley Park and is categorised as "Excellent" by CCS. All four contractors met this, and in some areas were marked as "Exceptional"

Safety Awards: June To reward and encourage our record of outstanding safety at Wembley Park, we are proud to host a monthly safety award. Our June winner is Shaukat from John Sisk and Sons Ltd. He was chosen for being extra vigilant on the security desk for dayto-day activities.

You can view the full CCS scoring system here: www.ccscheme.org.uk/siteregistration/site-scoring-2/

Quintain is transforming Wembley Park with the help of key contractors

Considerate Constructors & Build UK Wembley Park is a Client Partner of the Considerate Constructors Scheme which seeks to improve the image of the construction industry by promoting and achieving best practice. All of Quintain’s main contractors adhere to this code. www.ccscheme.org.uk

Wembleypark.com

Quintain is a partner of Build UK – a collective voice for the construction supply chain which provide valuable insight into construction markets and aims to improve industry practices. www.builduk.org

Customer voicebox: 0800 021 3245

This newsletter is delivered to local residents and businesses. Extra copies can be collected from the Yellow Pavilion. For construction jobs and apprenticeships visit: https://jobs.wembleypark.com