Fire Resistance Testing Timeline

Page 1

Testing Application Review (TAR) meeting completed and test scope agreed

Sampling dates booked with Notified Body of choice

Quote and test date letter signed and returned by customer

Up to 8 weeks prior

Technical Specification form completed and returned by customer

Specimen drawings supplied in .DWG format

Material safety data sheets (MSDS) supplied by customer

4+ weeks prior

Specimen delivery scheduled for at least five working days ahead of test

Installation instructions supplied or installers booked in with your technical officer

Risk assessments and method statements supplied by customer

2+ weeks prior

You will receive an email one working day before your test, containing our online safety and COVID inductions. These need to be completed before your your arrival on-site

F I R E R E S I S TA N C E T E S T I N G T I M E L I N E

We advise you to complete a lateral flow test. Please do this no more than 24 ahead of your visit to our sites

1 working day prior to test

If we have received all required information, you will receive the first draft of the test report within this time frame Please arrive at least one hour before your test time

Your supplied comments will be incorporated into the report by your technical officer and sent to one of our technical authorisers for review, before applying their signature.

If any further information is required, we will be in touch

Once the report is signed off, the final will be sent to you

Within 8 weeks of comments

Your technical officer will have highlighted any areas where they would like your comments within the body of the report.

Welcome to Warringtonfire

Please feel free to add any of your own comments as well

Within 8 weeks post-test