Surveyor Bill Edge (above left and middle) and his team lay out for a new relieving platform consisting of 18” H-pile. Tony Sheppard, Lead Man, cuts off existing sheet pile wall (bottom left) to grade.

Caleb Johns, Laborer, excavates for placement of new tie back rods (below).

Welder Alex Dey splices a 36” pipe pile from the platform while Scott Brunette, Superintendent, and Westly Diotte, hook up a vibratory hammer (above right) to drive the pile.

The vibratory hammer is moved into place (middle right) by David Miller, Crane Operator.

Florida Yacht Club

Hal Jones was hired by the Florida Yacht Club in Jacksonville, FL to replace the existing docks that have become nearly unusable over the years.

The photos above and right show crews removing the existing metal railing from the docks. Once detached, the crane will move it to the barge (top right) to be hauled away. With the railing removed, crews will begin replacing the old dock.