GENERAL UPDATE 29 MARCH 2012
NEW SU BUILD
/ THREE PHASE < March 2013
< July 2013
< September 2013
NEW SU BUILD
/ NEW LOCATION
NEW SU BUILD
• • • • •
/ OUR BUILDING
Social Engaging Reflect our purpose Sit comfortably in it’s surroundings Offer similar services to our current basis and enable us to improve on these services • Not to fall out-of-scope, bearing in mind the new campus masterplan
NEW SU BUILD
/ NEW LOCATION
NEW SU BUILD
/ BUILDING SHAPE
NEW SU BUILD
/ EXTERIOR
NEW SU BUILD
/ ARRANGEMENT
NEW SU BUILD
/ GENERAL ARRANGEMENT
NEW SU BUILD
/ GENERAL ARRANGEMENT
NEW SU BUILD
/ NATURAL LIGHT
NEW SU BUILD
/ OTHER FACTS
• Total budget is £8.8 million • Of which construction is £5.4 million • Internal size 3000 sq/m • 64% bigger than the space at Frenchay SU
NEW SU BUILD
/ KEY DATES
• Planning Application / 27th April 2012 – Can take 13 weeks to process
• Building Stars / 27th August 2012 • Move in / July 2013 • Official Opening / Freshers 2013
FEEDBACK www.uwesu.org/lets-build