MassDEP Releases DRAFT CY2026 Clean Water & Drinking Water SRF Lists Totaling Over $1.162 Billion

• • •

MassDEP Delays Heavy-Duty Omnibus Rule Again; Question Remains Over Legality of CARB Rules A Slowly Stabilizing Insurance Market for the Water and Sewer Industry March is National Ladder Safety Month

Photo courtesy of C. C. Construction, Inc.


JOIN THE MOVEMENT www.letsmovewater.com

#letsmovewater


President CHRIS VALENTI

GVC Construction, Inc.

President Elect QUERINO PACELLA

UTILITY CO

ATION CI O

OFFICERS

EW

IN

N

C.

UCANE

OF

MARCH, 2026

TO RAC RS’ A SS NT

, ENGLAND

IN THIS ISSUE 3 President’s Message: Across the Commonwealth and Beyond, Water Infrastructure is Often Out of Sight and Out of Mind, Until it Isn’t

Secretary JUSTIN GOODHEART

5 Legislative Update: • MassDEP Delays Heavy-Duty Omnibus Rule Again; Question Remains Over Legality of CARB Rules • Healey-Driscoll Administration Provides Grants for River and Wetland Restoration • Massachusetts First State to Deploy ChatGPT Across Executive Branch • News in Brief

BOARD OF DIRECTORS

21 In Memoriam: Robert “Bob” Benard, C. N. Wood Co., Inc.

RJV Construction Corp.

Treasurer LISA FRENCH KELLEY

W. L. French Excavating Corp.

J. F. White Contracting Co.

MARCELLA ALBANESE

23 Legal Corner: Pre-Bid Questions in Bidder Responsibility Cases

GERRY CARNEY, JR.

27 MassDEP Releases Draft CY2026 Clean Water & Drinking Water SRF Lists Totaling Over $1.162 Billion

BRIAN COONEY

39 Under the Hard Hat: An Interview with Board Member Chris Walsh, W. Walsh Company, Inc.

JULIA D’ALLESSANDRO

41 UCANE’s 2026 Calendar of Events

Albanese Brothers, Inc. C. N. Wood Company, Inc. C. C. Construction, Inc.

D’Allessandro Corp.

JERRY GAGLIARDUCCI

43 New Salem and the Urgent Case for a Statewide Water Strategy

Gagliarducci Construction, Inc.

46 Is a Statewide Water Plan Necessary?

MARCO GIOIOSO

47 UPDATED: No Easy Fix for Potomac River Sewage Spill, Now Estimated at $20M

P. Gioioso & Sons, Inc.

MARK LANGEVIN

Phoenix Communications, Inc.

WILLIAM LEONARD

53 Digging Smarter: Practical Lessons from Dig Safe’s February Training Breakfast 55 UCANE’s Safety Corner: March is National Ladder Safety Month

Aqua Line Utility, Inc.

59 UCANE’s 14th Annual Trade Show

KARIN MARSHALL

61 Save the Date: UCANE’s 47th Annual Golf Tournament

Boston Concrete Corp.

63

Pittsfield Seeks $28M Borrowing for Water and Sewer Infrastructure

J. Derenzo Co.

65

AMWA Testifies at Senate EPW Committee Hearing on Cybersecurity

RYAN McCOURT

66 UCANE’s Employee Safety Manuals Now Available

JOHN McGRATH

67 Insurance Perspective: A Slowly Stabilizing Insurance Market for the Water and Sewer Industry

MIKE McCARTHY

McCourt Construction Company Methuen Construction Co.

MICHELE NORTON

71 UCANE’s 2026 Scholarship Applications Now Available

HUB International New England

RICHARD PACELLA, JR. R. M. Pacella, Inc.

FRED ROGERS

Scrap It, Inc./Minichiello Bros., Inc.

MARK SZELA

Insituform Technologies LLC

CHRISTOPHER WALSH

Editor: Joseph F. Nolan; Magazine Designer/Associate Editor: Sherri Klayman; Associate Editor: Suzanne Hatch; Writer: Brandon Ward Construction Outlook Chair: Chris Valenti Editorial Board: Chris Valenti, Querino Pacella, Lisa French Kelley, and Justin Goodheart CONSTRUCTION OUTLOOK published monthly by the Utility Contractors’ Association of New England, Inc., 300 Congress Street, Suite 101, Quincy, MA 02169; Tel: 617.471.9955; Fax: 617.471.8939; Email: jnolan@ucane.com; Website: www.ucane.com. Statements of fact and opinion are those of the authors alone and not necessarily those of UCANE and the Construction Outlook editorial board and staff. Subscriptions are included in dues payments for UCANE members. Presorted Standard postage paid at Brockton, MA. POSTMASTER, please send form #3579 to Construction Outlook, Crown Colony Office Park, 300 Congress Street, Suite 101, Quincy, MA 02169.

W. Walsh Company, Inc.

JOSEPH NOLAN

Executive Director

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

1


JOINING FORCES TO BETTER SERVE YOU The Jack Farrelly Company, Putnam Pipe and HR Prescott have united, as part of the Core & Main family. • W. Boylston, MA 508-835-4431

• Hopkinton, MA 508-435-3090

• Norwood, MA 781-407-9133

• Bloomfield, CT 860-769-6760

• North Haven, CT 203-777-5548

• Taunton, MA 508-880-8736

• East Lyme, CT 860-739-5457

• Westbrook, ME 207-464-0585

• Worcester, MA 508-752-7473

• New Britain, CT 860-826-0517

• N. Billerica, MA 978-459-6701

• Loudon, NH 603-263-7350

• New Milford, CT 860-210-6262

• Springfield, MA 413-732-8400

• Johnston, RI 401-725-0140

We’re still the dependable experts you’ve always known, but now as one team, continuing to handle all your water, wastewater, fusible, and storm drainage material needs.

Service Work Available. Give us a call at 860-243-9714. Scan the QR Code to Learn More.

2

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Across the Commonwealth and Beyond, Water Infrastructure is Often Out of Sight and Out of Mind, Until it Isn’t Recent discussion in the Boston Globe about the need for a statewide water strategy highlight something UCANE members have long understood: access to clean, reliable water is not guaranteed. From small rural communities to fast-growing suburban regions, many municipalities face aging systems, supply constraints, and rising regulatory demands.

A

s one-time federal funding from the Infrastructure Investment and Jobs Act (IIJA) begins to sunset in 2026, the Commonwealth must confront a critical question: what comes next? Over the past several years, federal infrastructure dollars have provided a meaningful boost to long-delayed water, wastewater, and stormwater projects. These investments supported local jobs, improved system reliability, and helped communities begin addressing lead service line replacement and PFAS treatment. But these funds were always temporary. The need, however, is permanent. In our ongoing discussions with legislative leaders, we recognize that infrastructure funding now faces additional competing priorities. Increased investment in lead service line removal following the Flint, Michigan crisis and the enormous costs associated with PFAS mitigation are both necessary and urgent. However, their resolution cannot, and must never, come at the expense of maintaining and investing in our increasingly aged core water and sewer infrastructure. Water pipes are underground, out of sight and out of mind until the next collapse — as we have seen recently here in Winthrop and nationally in Washington, D.C. Massachusetts faces tens of billions of dollars in water infrastructure needs over the coming decades as systems continue to age. Planning discussions are important, but planning without sustained funding will not solve the problem. Nor will funding without a clear strategy that prioritizes public health, economic growth, and cost-effective investment. UCANE believes the path forward requires both. First, the Commonwealth must protect and strengthen the State Revolving Fund (SRF) program — the backbone of water infrastructure financing. Cuts to federal SRF allocations and uncertainty in state matching funds threaten to stall projects just as communities are preparing for long-term investment

MARCH, 2026

cycles. A real investment in SRF funding is not optional; it is essential. Second, we must continue working closely with local, state, and federal leaders to ensure water infrastructure remains a priority even as some federal stimulus programs wind down. Water systems support housing production, economic growth, and public health. The administration has correctly made major policy initiatives to support much-needed affordable housing across the Commonwealth. Funding and zoning may pave the way for housing, but it will not be built without investing in the water, sewer, and utility infrastructure needed to make that housing possible. Solutions will differ by region. Some communities may benefit from expanding the MWRA service area, while others may need treatment upgrades, new wells, or modernized distribution infrastructure. A thoughtful statewide strategy can help guide these decisions, but it must be paired with sustained capital investment and practical regulatory policies that allow projects to move forward. UCANE’s members, union and open shop contractors alike, build and maintain the systems that keep our Commonwealth running. We see firsthand what deferred maintenance costs, and we also see what smart investment delivers: stronger communities, reliable infrastructure, and long-term economic stability. As your President, I am committed to continued outreach and engagement with policymakers and stakeholders to ensure that water and utility infrastructure investment does not fall victim to short-term budgeting cycles. UCANE’s continued efforts to ensure that water, sewer, and utility infrastructure investment do not wane, may never be more important.

Clean, reliable water is foundational. It deserves long-term vision — and long-term investment. Thank you for helping us carry this critical message to our leaders locally and nationally. n

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

3


Highest Level of Quality, Greatest Level of Skill

Dagle Electrical Construction Corp.

Construction: • • • • • • •

Other Services:

Heavy Industrial Commercial Multi-Unit Residential Design Build Ground Up Renovation Pumping Stations

• • • • • • •

Tel/Data Fiber Optic Fire Alarm Stand By Power Systems Sports Lighting Marine Power Installations Special Event Lighting & Power

Transportation: • • • • •

Traffic Signal Systems Highway & Street Lighting Systems Intelligent Transportation Systems Parking & Snow Melt Systems Rail Transit Installation

Alternative Energy: • Wind Turbine • Photo Voltaic • Green Technology

WBE Certified

68 Industrial Way • Wilmington, MA 01887-3434 T: 800.379.1459 • F: 781.937.7678 • Email: dec@deccorp.com

www.deccorp.com


Mark Molloy, Esq.

MassDEP Delays Heavy-Duty Omnibus Rule Again; Question Remains Over Legality of CARB Rules

T

he Massachusetts Department of Environmental Protection (MassDEP) scheduled a virtual public hearing on Monday, March 16, 2026, at 10:30 a.m. and again at 5:00 p.m., to receive testimony on proposed amendments to 310 CMR 7.40, the regulation governing the Commonwealth’s Advanced Clean Trucks (ACT) and HeavyDuty Omnibus (HDO) requirements. These proposed amendments impact manufacturers, dealers, fleets, and end users of medium- and heavy-duty (MHD) vehicles operating in Massachusetts. The proposal makes two principal changes. First, MassDEP is seeking to delay the implementation of the Heavy-Duty Omnibus (HDO) standards by one year, shifting the start date from Model Year 2026 to Model Year 2027 (MY27). In its background materials, the Department notes that manufacturers have indicated they do not have sufficient MY2026 HDO-compliant engines and vehicles available for many applications and would otherwise need to restrict sales to comply. MassDEP states that manufacturers anticipate adequate compliant availability beginning in MY27, and the proposed delay reflects that reality. While modest in duration, the one-year extension is intended to provide supply chain stability and reduce market disruption during the transition. Second, MassDEP proposes to adopt recent amendments made by the California Air Resources Board (CARB) to the Advanced Clean Trucks (ACT) rule. Among the most notable changes is an expansion of manufacturer compliance flexibility by extending the “deficit makeup” period from

MARCH, 2026

one model year to three model years, allowing manufacturers to balance required electric truck sales across a multi-year period rather than annually. The amendments also align certain reporting and compliance provisions with California’s updated framework. From a regulatory standpoint, the proposed revisions are designed to mirror California’s most recent ACT adjustments and provide additional compliance flexibility within the existing mandate structure. For dealers and end users, the amendments present a nuanced and evolving policy landscape. The proposed HDO delay offers near-term regulatory relief and acknowledges the operational constraints associated with equipment availability and certification timelines. At the same time, the ACT amendments continue to move forward electric truck sales requirements during a period when infrastructure buildout, grid interconnection timelines, and charging capacity remain significant concerns for many fleets. In addition, stakeholders continue to raise questions about electric vehicle costs, operational feasibility in certain vocational applications, range and payload constraints, and cold-weather performance. These practical considerations are unfolding alongside ongoing federal litigation concerning the United States Environmental Protection Agency’s (EPA’s) waiver authority and Clean Air Act implementation, adding further uncertainty to the broader regulatory environment. Nevertheless, Massachusetts law requires alignment with California’s continued on page 7

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

5


SITECH NORTHEAST

GRADE CONTROL COMPACTION CONTROL DRILLING/PILING/SHEETING POSITIONING SURVEY/LAYOUT TOOLS PRODUCT TRAINING DRONE SERVICES SITE POSITIONING PAVING CONTROL SOFTWARE SOLUTIONS COMPONENT REPAIR TECHNOLOGY RENTAL

00

YOU DO THAT?

Offering you a complete range of services to help you save time, money and resources. Visit www.sitechnortheast.com to find your representative or call 855-748-3244.

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

OCTOBER, 2017


Legislative Update continued from page 5 vehicle emission standards, and the Commonwealth continues to move forward under that statutory framework. MassDEP will accept oral testimony at the March 16 virtual hearings and written comments through 5:00 p.m. on March 26, 2026. Written comments may be submitted by email to Ngoc Hoang at the Bureau of Air and Waste (ngoc.hoang@mass.gov) or by mail to MassDEP at 100 Cambridge Street, Suite 900, Boston, MA 02114. Given the long-term implications of ACT and HDO implementation for the MHD market in Massachusetts, stakeholder engagement remains critical. The upcoming hearing provides an important opportunity for industry participants to weigh in on the proposed delay, the adoption of California’s ACT amendments, and the broader path forward for achieving emissions reductions in a manner that is operationally feasible and economically sustainable for the Commonwealth’s transportation sector. To register for the MassDEP public hearings, please visit: https://www.mass.gov/doc/aq-lev-notice-english/download. continued on page 9 We improve the lives of our partners, and our family by going beneath the surface to build America’s essential infrastructure. While we’re capable of taking on any trenchless construction project across the U.S., we’re bestsuited for the hard jobs no one else wants to touch.

SAND & STONE CORP. 192 Plain St. North Attleboro, MA 02760 (508) 699-1922 www.borocorp.com

Bettering lives from the ground up

We are proud to offer an array of trenchless construction methods to choose from to perfectly fit every job. Partner with us on your next project.

. Jack and Bore . Hand Mining . Micro-tunneling . Conventional Tunneling . Horizontal Directional Drilling . Rehabilitation Learn more at miswestmole.com

6814 W 350 N Greenfield, IN 46140 317.545.1335

MARCH, 2026

1101 Princess St Alexandria, VA 22314 317.545.1335

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

7


EFFICIENT, SAFE, RELIABLE SOLUTIONS. » HYDRO EXCAVATION » UTILITY LOCATES » POTHOLING » POLE + ANCHOR HOLES » & MORE!

MASSACHUSETTS

Maurice Anderson 617.721.1761 MASSACHUSETTS + NEW HAMPSHIRE

Joe MacEachern 508.450.7667

24 / 7 / 365 SUPPORT BADGERINC.COM 8

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Legislative Update continued from page 7

Healey-Driscoll Administration Provides Grants for River and Wetland Restoration

T

he Healey-Driscoll Administration announced over $1.4 million in grants to support river and wetland restoration. The funding, provided by the Massachusetts Department of Fish and Game’s (DFG) Division of Ecological Restoration (DER) was awarded to 12 communities, including eight projects through DER’s Priority Projects Program and one project through DER’s Culvert Replacement Training Site Initiative. These projects will help to strengthen resilience to climate change, reduce flood risks, improve water quality and public safety, and restore vital wildlife habitat. DER’s Priority Projects Program supports wetland and river restoration projects that benefit the state’s environment, community, and economy. Once designated as a DER Priority Project through a competitive process, projects are eligible to apply for funding opportunities and receive technical support and services from DER. DER’s Priority Projects restore freshwater wetlands, floodplains, streams, and coastal habitats, and remove aging and unsafe dams.

DER’s Culvert Replacement Training Site Initiative works to help cities and towns replace outdated culverts with new, improved crossings and aims to create a network of road managers with advanced experience implementing culvert replacements that meet the Massachusetts Stream Crossing Standards. Through project sites that serve as case studies, local road managers receive comprehensive training on how to assess, plan, and carry out these important resilience projects statewide. Through the Biodiversity Goals for the Commonwealth, the Massachusetts has committed to restore 75 percent of our most important habitats for wildlife, remove 10 percent of obsolete dams, and upgrade 2,500 culverts by 2050. Through the Mass Ready Act, the Healey-Driscoll Administration has proposed investments to accelerate progress towards these goals, including $40 million for river and wetland restoration and $20 million dedicated to advancing the Biodiversity Conservation Goals. continued on page 11

Confidence at every turn

™

Turn fragmented workflows into total project visibility. With Trimble, you’re not just managing data— you’re mastering the job site from estimate to execution.

Turn to Trimble

W W W.TRIMBLE.COM

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

9


Built on Experience, Focused on Results. With a track record of excellence and positive outcomes, our nationally recognized Construction & Public Contracts practice is committed to delivering results for you and your business. We understand construction and our clients’ needs and businesses. Our experienced attorneys thrive on addressing complex challenges by leveraging their extensive industry knowledge, partnering with industry leaders, and participating in a vast network of professional affiliations. Our comprehensive suite of services includes contract analysis, drafting, negotiation, procurement and bid protest issues, strategic project advice, crisis management, claims preparation, prosecution and defense, and all forms of dispute resolution, such as mediation, arbitration, litigation, and appeals. We also assist with compliance and investigations, OSHA investigations, insurance recovery, and risk management. We can help you navigate any phase of your project and protect your interests through practical advice and effective legal strategies.

www.hinckleyallen.com/construction CONNECTICUT | FLORIDA | ILLINOIS | MASSACHUSETTS | NEW HAMPSHIRE | NEW YORK | RHODE ISLAND © 2025 Hinckley, Allen & Snyder LLP. All rights reserved. Attorney Advertising.


Legislative Update continued from page 9 •

•

•

•

DER awarded funding to the following projects: Abbey Brook Restoration & Revitalization; Chicopee ($100,000). This project is removing two dams, replacing a culvert, and “daylighting” a 250-foot stretch of river to restore natural river processes, improve water quality, stormwater management, and stream connectivity, reduce flood risk, and protect area utilities. This award will support design work for Phase Two of the project. Bayview Cranberry Bogs Restoration; Yarmouth ($25,000). This project is restoring healthy, diverse wetlands on approximately 45 acres of abandoned cranberry farmland adjacent to the Cape Cod Hospital. This award will support planning, outreach, and community engagement. Childs River Restoration; Falmouth and Mashpee ($6,200). This project completed construction in 2021 and resulted in restoration of 40+ acres of wetlands and 1.5 miles of associated stream, improved fish and wildlife passage and ecological connectivity, and enhanced habitat and species diversity. This award will support post-construction invasive species management. Frost Fish Creek Restoration; Chatham ($120,000). This project is restoring tidal exchange and stream connectivity to an impaired upstream

•

•

•

•

salt marsh and a former cranberry bog to improve water quality and wetland health and function within Frost Fish Creek. This award will support data collection and development of flood mitigation designs. Nashawannuck Brook Restoration; Northampton ($154,650). This project is restoring floodplain connection, enhancing stream habitat, creating wetland habitat, and replanting the riparian corridor on a former golf course in Northampton. This award will support construction. South Meadow Wetland Reserve Easement Restoration; Carver ($177,000). This project is restoring 30+ acres of retired cranberry farmland to a self-sustaining natural wetland and stream system, enhancing habitat, biodiversity, ecological connectivity, and climate resilience and resistance. This award will support construction. South River Restoration/Temple Street Dam Removal; Duxbury ($150,000). This project is removing the Temple Street Dam to improve ecological processes and climate change resilience, restore aquatic connectivity, and eliminate an ongoing maintenance burden for the community. This award will support construction. Ware River Restoration/Wheelwright Dam Removal; Hardwick, Barre, and New Braintree ($600,000). This project is removing the Wheelwright continued on page 13

DigSafe.com or Call 811 Before You Dig It’s smart. It’s free. It’s the law. Follow these steps for a safe excavation: • Pre-mark the location of intended excavation using white stakes, paint or flags. • In MA, ME, NH, RI and VT, notify Dig Safe® at least 72 hours in advance, not including weekends and holidays.

• If a line is damaged, do not backfill. Notify the affected utility company immediately if the facility, its protective coating, or a tracer wire is damaged.

• Notify non-member facility owners.

• Call 911 in the event of a gas leak, or if a damaged facility poses a risk to public safety.

• Maintain the marks placed by underground facility owners.

• Know your state’s excavation requirements.

• Use caution and dig by hand when working within 18” of a marked facility.

• Go to digsafe.com for educational material and current laws.

DGS UCANE COM.indd 1

MARCH, 2026

7/18/24 5:04 PM

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

11


VIDEO PIPE INSPECTION • CCTV Live Video Feed • Large and Small Pipes

PIPE CLEANING SERVICES • High Pressure Jetting • Vactor Services

Southern New England’s

FOREMOST NAME Since 1940.

in Sewer and Drain Services

HI-RAIL VAC SERVICE • Hi-Rail Guzzler • Demo & installation

SEWER ACCEPTANCE SERVICES • Low Pressure Air Testing • Vacuum Testing of Structures

PodgurskiCorp.com

781.828.0821 Office@podgurskicorp.com 8 Springdale Ave • Canton, MA 02021 Commercial • Municipal • Residential

12

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Legislative Update continued from page 11 Pond Dam to restore natural riverine processes and reconnect 130 miles of high-quality freshwater habitat in the Ware River Watershed, 34 miles of which is coldwater fisheries habitat. Removal of the Wheelwright Pond Dam will be one of the largest and most significant dam removals in Massachusetts. This award will support phase two of construction. • Stoney Brook Culvert Replacement; Weston ($76,924). This project will remove two undersized culverts on Viles Street and Church Street over Stoney Brook, a Coldwater Fisheries Resource, to benefit stream and habitat connectivity as well as provide public access and safety benefits to the roadway and surrounding community. As part of the Culvert Training Initiative, the Town will also host one to two trainings led by DER to teach local roadway managers about culvert replacements in Massachusetts. This award will support field data collection activities. To learn more about the Culvert Replacement Grant Program, please visit: https://www.mass.gov/ how-to/culvert-replacement-training-site-grant-funding. For more information about the Priority Projects Grant Program, please visit: https://www.mass.gov/ how-to/priority-projects-program-advancement-grant. continued on page 15

We are BORING

HENNIKER DIRECTIONAL DRILLING

Over 20 years drilling in tough New England terrain HDDBORE.com | 603-428-6333 | daniellem@hddbore.com Visit us on FB and Instagram

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

13


If you can… then GRANITE CITY ELECTRIC has all your underground products IN STOCK! We have it and we’ll deliver it!

No job is too BIG!

Granite City Electric has all the inventory you need and the trucks to deliver it to your job site. Our distribution centers are fully stocked with all the underground products to complete your job.

All of our New England distribution centers provide Moffett Truck daytime delivery services. For your convenience, these trucks come with a forklift that attaches directly to the back of That means no more waiting for days to get your the delivery vehicle and go with the delivery to unload your products at the job site. Our products delivered to the job site. delivery services can support any combination Count on our inventory and superior service for of conduit, pipe, and enclosures you need. Best all your Underground Utility installation needs. of all, we unload it for you at the job site at no extra cost! Call today to schedule your next Moffett delivery!

1-800-850-9400

www.GRANITECITYELECTRIC.com

Scan the code to see how Granite City Electric has you covered with over 30 branches throughout the Northeast.


Legislative Update continued from page 13

T

Massachusetts First State to Deploy ChatGPT Across Executive Branch

he end of February saw Governor Maura Healey announce the launch of the ChatGPTpowered Artificial Intelligence (AI) Assistant for the state’s workforce, with the goal of making government work better and faster for people. The AI Assistant will be implemented as a phased approach across the executive branch and will provide a safe and secure environment that protects state data. Massachusetts will be the first state to adopt the technology for the entire executive branch, which includes nearly 40,000 state employees. Following a competitive procurement process, the state and OpenAI have agreed to a contract to deploy ChatGPT at scale across Massachusetts state government. The rollout will take a phased approach, starting with staff in the Executive Office of Technology Services and Security (EOTSS). Additional secretariats and executive branch agencies will be onboarded over the coming months. In conjunction with the rollout, the state is offering a series of optional training programs designed to provide employees using the Enterprise AI Assistant with a baseline understanding on best practices and strategic use of the tool. The rollout of ChatGPT will be within a walled-off, secure environment that protects state data and ensures that employee chat inputs do not train public AI models. Use of the tool is governed by terms and conditions set by the TSS Privacy Office, and regularly updated policies that govern the use and development of AI. While other states have launched limited pilot programs for ChatGPT, Massachusetts will be the first enterprisewide deployment of the tool. The launch of the Enterprise AI Assistant builds on the HealeyDriscoll Administration’s broader strategy to position Massachusetts as a global leader in applied AI. Through the Massachusetts AI Hub, the Administration is coordi-

MARCH, 2026

nating state support for the AI ecosystem, expanding access to critical infrastructure like compute resources, deepening partnerships with industry and research institutions, and ensuring Massachusetts remains the place where AI is developed, tested, and turned into real-world solutions across sectors like life sciences, advanced manufacturing, clean energy, and health care. More information on the tool, training and other Frequently Asked Questions can be found at mass. gov/ai. continued on page 17

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

15


Legislative Update continued from page 15

News in Brief •

Lewis Decides Against Seeking Re-Election; Lipper-Garabedian First to Announce Campaign. Massachusetts State Senator Jason Lewis, a Winchester Democrat and influential legislator behind the new millionaires tax on income over $1 million and the 2019 overhaul of the state’s school funding formula that directed an additional $2 billion to K-12 education, announced that he will not seek reelection in 2026, saying he is ready for the next chapter of his life. Over nearly two decades on Beacon Hill, Senator Lewis also helped raise the tobacco-buying age to 21 and was a primary negotiator on laws raising the minimum wage to $15 and creating paid family leave. His departure opens a seat in the Fifth Middlesex Senate district. Representative Kate Lipper-Garabedian, who has represented the 32nd Middlesex District (Malden, Melrose, and Wakefield) in the House of Representatives since March 2020, announced her intention to run for the seat im-

•

mediately following Senator Lewis’ announcement. Prior to serving in the House, Representative Lipper-Garabedian served as a Melrose City Councilor at-large, first elected in 2017. She also worked as the Chief Legal Counsel at the Massachusetts Executive Office of Education and as a public middle school teacher. Massachusetts Department of Revenue Alerts Taxpayers to New Timelines for Mail Postmarking. The Massachusetts Department of Revenue (DOR) is warning taxpayers, preparers, and child support customers about recent changes to United States Postal Service procedures that could delay postmark dates for mail. As of December 2025, mail received at post offices may not be postmarked on the day of receipt, unless specifically requested at the retail counter. To avoid any mailed tax return delays, taxpayers are encouraged to file and make payments electronically. MassTaxConcontinued on page 19

Business & Insurance Solutions

Insuring Contractors for Over 50 Years Providing tailored solutions in risk management, surety, claims and more to meet all your business needs.

Contact Us!

The information contained here is provided for information purposes only and should not be viewed as a substitute for any legal, regulatory or other advice on any particular issue or for any particular reason. The advice of a professional should always be obtained before purchasing any insurance product or service. Please contact your Acrisure representative or see Acrisure.com for details. 2026 © Acrisure, LLC. All rights reserved.

100 Unicorn Park Drive • Suite 201 Woburn, MA 01801 Paul Patalano | Jordan Tirone |

781-569-0146 781-569-0134

ACRISURE.COM

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

17


NORTHEAST

BIG. We Think

We Deliver

SOLUTIONS. flo w l e vel

PIPE RENEWAL OR REPLACEMENT, MANHOLE REHAB • Geopolymer Lining • Pipe Bursting • Manhole Rehabilitation

PIPE RELINING • CIPP Lining • UV CIPP Lining • Slip Lining

flo w l e

vel

flow l e

vel

fl o w l e

vel

INSPECTION, CLEANING & ASSESSMENT • Clean & CCTV • Multi-Sensor Inspection • Specialty Cleaning

Serving the municipal and industrial markets, you can count on Vortex Services Northeast for end-to-end trenchless rehabilitation services!

GROUTING • Leak Stoppage • Soil Stabilization • I&I Prevention

1-855-WHY-DIG1

www.vortexcompanies.com sales@vortexcompanies.com ©2025 Vortex Companies, LLC. All Rights Reserved.


Legislative Update continued from page 17

•

nect, DOR’s online system for filing returns and paying taxes, is available 24/7. Tax Year 2025 Massachusetts personal income tax returns are due by Wednesday, April 15, 2026. Extension payments must also be made by that date to qualify for the extended filing deadline of Thursday, October 15, 2026. At least 80% of the tax due must be paid by April 15, 2026, to qualify for an extension. For additional tax filing season resources and contact information, taxpayers are encouraged to visit the DOR website at https://www.mass.gov/info-details/ massachusetts-personal-income-tax-filingassistance. Matias Named Secretary of Housing and Livable Communities. Governor Maura Healey announced that Secretary of the Executive Office of Housing and Livable Communities Ed Augustus stepped down on February 27 after three years leading the state’s first housing secretariat in decades, during which he helped pass the $5.2 billion Affordable Homes Act and advance major production and affordability initiatives statewide. Mr. Augustus is leaving

L. GUERINI GROUP, INC. SINCE 1917

Material Placement Specialists

CONCRETE PUMPING EQUIPMENT “TELEBELT” MOBILE CONVEYORS STONE SLINGER SERVICE Pumps Up To 200 yds/hr • Booms Up To 142’ Reach Line Pumps • Grout Pumps Material Placement To 106’

34 Topalian Street PO Box 260187 Boston, MA 02126

(617) 296-0290 www.guerini.com

MARCH, 2026

•

to become CEO of UniBank, and Deputy Secretary Jennifer Maddox will serve as Interim Secretary until Juana Matias assumes the role on April 1. Ms. Matias, a former Massachusetts State Representative and most recently HUD Regional Administrator for New England, brings extensive federal and state housing policy experience, having overseen billions in housing investments and regional HUD operations. The Healey-Driscoll Administration praised Augustus’ leadership in establishing the secretariat and advancing housing production, while expressing confidence that Matias will continue efforts to expand supply, preserve affordability, and address the Commonwealth’s ongoing housing crisis. Ms. Matias holds a Bachelor of Arts in political science and criminal justice from University of Massachusetts Boston and a Juris Doctor from Suffolk University Law School. New Education Secretary Appointed to Replace Departing Tutwiler. As part of the election year turnover – often found before and right after a re-election campaign – Governor Healey announced that she is appointing Dr. Stephen Zrike Jr. as Secretary of the Executive Office of Education. Dr. Zrike is currently the Superintendent at Salem Public Schools and previously led the Holyoke and Wakefield Public Schools. Secretary of Education Patrick Tutwiler stepped down from his position on Friday, February 13 to assume the role of President and Chief Executive Officer of Walker Therapeutic & Educational Programs. Dr. Zrike previously worked at the Holyoke Public Schools as Receiver/Superintendent, where he led the turnaround of 11 chronically underperforming schools, improved academic outcomes, increased the graduation rate, and reduced chronic absenteeism. He also served as Superintendent of Schools in Wakefield, Massachusetts, Chief of Elementary Schools for the Pilsen-Little Village Network in the Chicago Public Schools, and Principal of both the William Ohrenberger Elementary School and John Philbrick Elementary School in Boston. He began his career as a fifth-grade teacher in Massachusetts’ Andover Public School District. Dr. Zrike holds a Bachelor of Arts degree in history from Dartmouth College and a master's degree and a doctorate in education from the Harvard University Graduate School of Education. n

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

19


BUILDING SUCCESS TOGETHER

Proudly Supporting UCANE Since 1974

leaner s Cleaner ewer C SSewer

Pipe Inspection Systems

Need Support? Call or Text... Parts: 800-557-0704 Service: 800-561-4939 Sales: 800-539-8905 Rentals: 800-560-3819

Hydro Excavation Trucks

Visit Our Website... www.cn-wood.com


I n M emoriam

Robert “Bob” Benard

I

C. N. Wood Company, Inc.

t is with profound sadness that we share the passing of longtime UCANE member and dear friend, Robert “Bob” Benard, who passed away peacefully at the age of 91 on Sunday morning, March 1, 2026, at his home in Burlington, surrounded by his loving family. Bob was truly an icon in the construction industry — a respected leader, generous supporter, and trusted friend to so many within our association. Bob and C. N. Wood Co., Inc. joined UCANE in 1974 and, for more than five decades, have remained steadfast and generous supporters of our work and mission. Born in Melrose to the late Frank F. and Rose E. (White) Benard, Bob was raised and educated in the Melrose school system and graduated from Melrose High School, where he developed both his strong work ethic and his lifelong love of football. Mechanically gifted from a young age, he worked alongside his older brothers repairing cars and stock cars, and later at a local filling station during high school. Those early hands-on experiences sparked a passion that would define his life’s work. After working at a heavy equipment dealership, Bob joined a small, struggling company with an agreement to become an owner — the beginning of what would become C. N. Wood Co., Inc. Within two years, Bob and his partner, Paul McCarthy, purchased the business outright. Over the next six decades, Bob transformed the company into one of the most respected construction equipment dealers in the Northeast. Under his leadership, C. N. Wood grew to nine locations across Massachusetts, Connecticut, Rhode Island, New York, and Maine, employing nearly 200 people. For 58 years, Bob guided the company with integrity, heart, and determination. He supported contractors and municipal clients with dependable equipment, sound advice, and unwavering commitment. Known for leading with compassion as much as business acumen, he built partnerships and friendships that spanned generations. A true embodiment of hard work, Bob could often be found at the yard on Saturdays — and sometimes Sundays — ensuring every machine leaving the lot was ready to perform. Beyond his professional accomplishments, Bob believed deeply in giving back. He supported trade or-

MARCH, 2026

ganizations through scholarships and educational opportunities, quietly assisted local charities, and was known throughout the Woburn and Burlington communities as a generous and often anonymous “Secret Santa.” His legacy of humility, service, and generosity continues to inspire all who knew him. Bob was a founding member of the NBM Highway Association and an active member of the Massachusetts Highway Association, UCANE, APWANE, and many other industry organizations. He was also a member of the Ancient and Honorable Artillery Company of Massachusetts and the Wyoming Lodge of Freemasons in Melrose. Despite his extraordinary professional life, Bob’s greatest pride was always his family. He shared a devoted marriage with the love of his life, Paula (Toomey) Benard. High school sweethearts, Bob and Paula built a life grounded in love, hard work, and shared purpose. He often credited Paula as his partner and strength in every success. Together, they raised their children with steady guidance and unwavering support. Bob cherished time spent with his family in the Lakes Region of New Hampshire, where he introduced three generations to boating, watersports, skiing, snowmobiling, and simply enjoying time together. Even in later years, he could be found operating his mini-excavator at his Alton, NH property, thoughtfully shaping the landscape into a natural retreat. He found joy in building, fixing, and creating — and he never lost his love of football, especially analyzing coaching strategy and play-calling. Bob was predeceased by his brothers, Ernest S. Benard and Edward H. Benard, and his brother-in-law, Levon Maserian. He is survived by his beloved wife, Paula; his daughters Debra Del Dotto and her husband Ronald, Paula Benard, and Cheryl MacIver and her husband Dana; his sister June Maserian; his grandchildren Paula Merva and her husband Martin, Kelly Piper, Eric MacIver and his wife Lauren, and Kristen MacIver and her fiancé Shawn Power; and his three great-grandchildren, Piper Rose Merva, Alton Robert Merva, and Hudson Arthur Merva. On behalf of UCANE, we extend our deepest sympathies to Paula and the entire Benard family. Bob’s legacy within our industry and our association will not be forgotten. n

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

21


22

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Construction & Public Contracts Group, Hinckley Allen, LLP

Christopher Morog Partner

Robert T. Ferguson Partner

Pre-Bid Questions in Bidder Responsibility Cases The Bid Unit of the Massachusetts Office of the Attorney General (“Bid Unit”) closed out February 2026 with a decision concerning an awarding authority’s power to determine bidder responsibility under M.G.L. c. 30, § 39M. The case illustrates the importance of reviewing the requirements of the bid documents and, where appropriate, submitting pre-bid questions to address potential issues or seek clarification in advance.

T

he case arose out of a municipal public works project for the revitalization of a landfill. In addition to general site work and grading and improvements to a nearby playground, the project scope of work also entailed landfill closure and capping. The awarding authority required prospective bidders to “Provide Three Service Appropriate References,” but did not define or otherwise elaborate on the meaning of the term: “service appropriate references.” It did not appear from the Bid Unit’s decision that any interested bidder submitted a prebid question concerning this requirement or project experience requirements. In its bid, the apparent low bidder identified three projects that it considered to be similar projects. The second-low bidder identified nine. After opening bids, the project designer proceeded to conduct reference checks. With respect to the apparent low bidder, the designer reported two positive reference checks. However, one of the apparent low bidder’s references stated that it had never worked with the apparent low bidder previously. After further investigation, the apparent low bidder admitted that its “most recent landfill experience was 10 years ago” and that it “had used the landfill experience obtained elsewhere by two of its employees.” The awarding authority rejected the apparent

MARCH, 2026

low bidder, determining that the apparent low bidder was “non-responsible and ineligible due to its apparent lack of landfill experience.” In further support of the rejection, the awarding authority also cited its own “poor” prior experience with the apparent low bidder on a project 13 years ago. The apparent low bidder filed a bid protest. The Bid Unit acknowledged that an awarding authority retains discretion when it comes to determining bidder responsibility, and that this determination “is not disturbed absent a showing of arbitrary or illegal action by the awarding authority.” On the facts of this case, the Bid Unit concluded that the awarding authority’s decision to reject the continued on page 25

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

23


For over 75 years, Shea Concrete Products has proudly served the New England construction market by providing industry leading product quality and service to our customers and industry partners. Our robust product line of precast concrete products provides solutions for all project types and our truck fleet ensures on-time delivery.

800.696.SHEA (7432) Nottingham

160 Old Turnpike Rd Nottingham, NH 03290

Wilmington

773 Salem Street Wilmington, MA 01887

Rochester

153 Cranberry Hwy Rochester, MA 02770

Amesbury

87 Haverhill Rd Amesbury, MA 01913


Legal Corner continued from page 23 apparent low bidder was supported by a rational basis. In reaching this conclusion, the Bid Unit rejected the apparent low bidder’s argument that “the City should have considered the landfill experience of [the apparent low bidder’s] employees when determining whether [the apparent low bidder], itself, had the experience necessary for the Project.” The Bid Unit stated that the awarding authority “was not obligated” to consider the apparent low bidder’s employees’ experience and instead, “elected – in a proper exercise of its discretion – to consider only the relevant experience of [the apparent low bidder] as a business entity.” Although the Bid Unit concluded that it was “inappropriate” for the awarding authority to partially rely on a “stale” project that the apparent low bidder had performed for the awarding authority 13 years ago, this did “not supplant the independent justification for rejecting [the apparent low] bid, which rests soundly upon [the apparent low bidder’s] lack of landfill capping experience.” The Bid Unit therefore denied the protest. As this case illustrates, bidder responsibility protests often rise and fall on the specific facts of each situation. In its decision, the Bid Unit noted a

disagreement between the parties concerning what percentage portion of the scope of work would be comprised of landfill closure and capping. The apparent low bidder asserted that landfill closure and capping only accounted for approximately one-third of the overall scope of work. In contrast, the awarding authority asserted that the landfill closure and capping work comprised upwards of “75-80%” of the Project. In addition, as noted, the bid documents “did not further describe what the City meant by ‘service appropriate references.’” In these circumstances, prospective bidders might have considered submitting pre-bid questions to address issues before the awarding authority made bidder responsibility determinations. For example, the apparent low bidder could have submitted a pre-bid question seeking clarification regarding the importance of prior landfill experience given the portion of work requiring landfill closure and capping. It also could have asked whether the awarding authority would consider relevant experience that employees gained during periods of prior employment. While an awarding authority can set experience requirements, those experience requirements typically cannot be so restrictive as to continued on page 26

BUILD WITH US After serving major contractors for more than 60 years, the Driscoll Agency truly understands the unique risks, insurance requirements, and surety demands of the construction industry.

781. 681. 6686 781. 681. 6656 141 LONGWATER DRIVE, SUITE 203, NORWELL, MA 02061

www.DriscollAgency.com MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

25


Legal Corner continued from page 25 inappropriately reduce fair and open competition. Sometimes, awarding authorities will expand or clarify experience requirements, which can benefit the public by increasing the size of potentially responsible and adequately experienced contractors. If an awarding authority elects not to loosen experience requirements, bidders may then consider filing a protest before bids are opened. This can sometimes afford the Bid Unit (or a court) an opportunity to determine whether the experience requirements are too restrictive of competition in violation of the purposes of the competitive bidding laws. However, once bids are opened and the awarding authority has made its determination with respect to bidder responsibility, a bidder challenging that decision typically must demonstrate that the awarding authority’s determination was arbitrary, capricious, or illegal. In these cases, the Bid Unit will undertake an “affirmative duty to seek out potential justifications for” the decision of the awarding authority. Participating in the pre-bid question and answer process can sometimes facilitate resolution of potential issues before they arise. n

The Biggest, Baddest Ditch Witch Hydrovac to ever hit the wild ... Introducing the most powerful Ditch Witch truck vac to ever hit the open road — the Warlock Series W12. With a 2,800 PSI water system, 12 cubic yard debris tank capacity, and a 5,000 CFM, 27″ Hg vac system, this beast-of-a-machine easily devours jobs of all shapes and sizes.

TRENCH SAFETY

PREVENTS CAVE-INS

SAVES LIVES EXPLORE OUR SERVICES AT SUNBELTRENTALS.COM OR CONTACT US AT 888-846-1078 TO SEE HOW WE CAN HELP

South Plainfield, NJ: Shrewsbury, MA: Lumberton, NJ: Beacon, NY: Deer Park, NY: Middletown, DE: Baltimore, MD

908-753-8080 508-719-0200 609-534-7477 845-831-1800 631-392-2605 302-376-0784 410-687-1700

CALL FOR A FREE DEMO!

Visit JESCO online at www.jescoditchwitch.us.

26

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


MassDEP Releases DRAFT CY2026 Clean Water & Drinking Water SRF Lists Totaling Over $1.162 Billion Charles D. Baker Governor

Matthew A. Beaton Secretary

Approximately $728.1 Million Offered for Clean Water SRF in 2026

Karyn E. Polito Lieutenant Governor

T

Martin Suuberg Commissioner

he Massachusetts Department of EnvironJanuary 26, 2016

The CWSRF is funded with federal funding received mental Protection (MassDEP) is pleased to through the EPA, which is supplemented by state present the Draft Calendar Year 2026 Intendmatching funds, repayment of loans, and interest To All Interested Parties: ed Use Plan (Draft IUP). The federal Water Pollution earned. Control Act (Clean Water Act) requires MassachuThe Draft IUPisdetails projects, toThe Massachusetts Department of Environmental Protection (MassDEP) pleasedthe to intended present the setts to annually prepare an IUP – a plan identifying tal project costs, and amount of funding 2016 use Intended Use in Plan projects, borrowers and amounts that will bebeing oftheFinal intended of funds its (IUP), Cleanwhich Waterdetails State the fered through the CWSRF. This year, MassDEP and financedFund through the Clean Water Revolving (CWSRF) loan program. The CWSRF is a Revolving (CWSRF). The StateState issues a Final Fund the Trust are offering $728 million in financial supjoint federal-state financing loan program that provides subsidized interest rate loans to improve or IUP annually after a public review and comment periport to wastewater projects across Massachusetts, water quality in the Commonwealth. od.protect The U.S. Environmental Protection Agency (EPA) subject to the availability of funding. Approximately must receive the Final IUP before it awards its annual $432 million is being offered to finance 30 new conAs noted inGrant Tableto 1, the Massachusetts $414 million$270 to finance clean water offered to Capitalization CWSRF. is offering approximately struction projects, million is being projects across the Commonwealth. Approximately $380 million will fund 35 new construction The CWSRF is a joint federal-state financing finance 12 previously approved multi-year projects, projects and an additional $15 millionand willthe beMasallocatedand towards funding previously approved program managed jointly by MassDEP $300,000 is 9being allocated to fund two Asset multi-year projects. $2 million has been allocated to the emergency set-aside account, and $3projects. Addisachusetts Clean Water Trust (Trust) that provides Management Planning (AMP) Grant million will be and directed to the Community Program to remediate failed septic allocasubsidized loans grants to improve and Septic protectManagement tionally, approximately $25 million in set-aside systems in participating communities. An additional $13.8 will fund 15 Draft planning water quality and public health in Massachusetts. tionsmillion are included in the IUP.projects.

The Water Resources Reform and Development Act of 2014 (WRRDA) amended the Clean Water Act resulting in important changes to the CWSRF Program that will affect most borrowers. The NEW PROJECTS primary changes to the program are the requirements for borrowers to develop and maintain a Fiscal Sustainability Plan, which is similar to an asset management plan and a certification that the cost and 2026 Rating Applicant SRF ID Project Project Cost andIUP Cost effectiveness of the project has been evaluated and that the project maximizes water efficiency energy conservation. The body of the IUP discusses these new WRRDA requirements in greater detail. The United States Environmental Protection Agency (EPA) has not yet determined the exact 2016 SRF grant allocations to the states. Based on the overall federal appropriation, MassDEP expects to receive an estimated $44 million federal grant to subsidize the CWSRF program. Under the Fiscal Year 2016 Omnibus Appropriations Bill, Congress is requiring that at least 10% of the federal grant be used to fund “green infrastructure”. The 2016 Final IUP lists 16 new “green infrastructure” construction projects. The exact monetary value of the green portion of these projects will be determined when project applications are submitted but are expected to be well in excess of 10% of the federal grant. This information is available in alternate format. Call Michelle Waters-Ekanem, Diversity Director, at 617-292-5751. TTY# MassRelay Service 1-800-439-2370 MassDEP Website: www.mass.gov/dep Printed on Recycled Paper

continued on page 29 FEBRUARY, 2025 JANUARY, 2023 MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK” “BUY IN CONSTRUCTION CONSTRUCTION OUTLOOK” “BUY FROM FROM THE THE ADVERTISERS ADVERTISERS IN OUTLOOK”

21 19 27


Multiquip’s Mikasa Plate Compactors are recognized as the industry standard for compacting granular soils and asphalt.

YOU NEED COMPACTION, WE’VE GOT THEM! ATS EQUIPMENT HAS FOUR CONVENIENT LOCATIONS BOSTON, MA, 33 Locust St. Tel: (617) 825-3600 AUBURN, MA, 487 Washington St. Tel: (508) 832-8500 REHOBOTH, MA, 51 Fall River Ave. Tel: (508) 379-6200 CANDIA, NH, 133 Raymond Rd. Tel: (603) 483-2100

WE CARRY A FULL LINE OF PLATE COMPACTORS.

www.atsequipment.com

The Connolly family and all the professional staff ATS look forward to serving you –

our friends!

PLUS...WE FIX THEM AND STOCK PARTS!


DEP/SRF continued from page 27 NEW PROJECTS (cont.)

Rating

Applicant

SRF ID

Project

TOTAL OF NEW PROJECTS (Count: 30) (Average Rating: 538.1)

2026 Project Cost

IUP Cost

$703,597,411 $423,273,175

continued on page 31

GENERAL CONTRACTOR Manufacturer and Installer of Bituminous Concrete Products 100 Wales Avenue-Rear Avon, MA 02322 Office: 508-583-2029 Plant: 508-587-6953

MARCH, 2026

www.tledwards.net

226 Nicks Rock Road Plymouth, MA 02360 Scale House: 508-732-9148 Asphalt Plant: 508-732-9140

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

29


IF YOU KNOW WHAT THIS IS YOU NEED TO KNOW WHO WE ARE RENTALS SALES ENGINEERING TRAINING

“THE TRENCH & TRAFFIC SAFETY SPECIALISTS”

SERVICE

BOSTON BRANCH 49 SILVA LANE DRACUT, MASSACHUSETTS 01826 PHONE (978) 475-0420 FAX (978) 475-4022

30

FOR MORE INFORMATION CALL (888) 234-9244 WITH A NATIONWIDE BRANCH NETWORK, WE’RE WHERE YOU NEED US TO BE

www.ntsafety.com

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


DEP/SRF continued from page 29 MULTI-YEAR CARRYOVER AND STATUTORY PROJECTS Applicant

SRF ID

Project

TOTAL OF MULTI-YEAR CARRYOVER AND STATUTORY PROJECTS (Count: 12)

Project Cost

2026 IUP Cost

$1,369,219,418

$270,248,117

continued on page 33

www.unitedconcrete.com

Your single source for precast concrete solutions

Pump Stations, Prefabricated Buildings

˚ Bridge Structures ˚ Pump Stations, Buildings ˚ Underground Tunneling ˚ Culverts/Arches ˚ Retaining Walls ˚ Prestress/NEXT Beams ˚ Custom Structures

Prestress (PCI (PCI Certified) Certified) Prestress

RCP

Box Culverts

MARCH, 2026

Toll Free: (800) 234-3119 Fax: (203) 265-4941 Jason Lindsey jlindsey@unitedconcrete.com Cell 203-464-7667

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

31


AGGREGATES • HOT MIX ASPHALT • CONSTRUCTION SERVICES

998 RESERVOIR ROAD LUNENBURG, MA 978-582-5200

875 PHENIX AVENUE CRANSTON, RI 401-942-7300

2140 BRIDGE STREET DRACUT, MA 978-454-7878

72 SO. MAIN STREET ACUSHNET, MA 508-992-3542

WWW.PJKEATING.COM MEMBER

32

UCARI

CIRI

MAAPA

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


DEP/SRF continued from page 31 MassDEP PRIORITY PROJECTS Applicant

SRF ID

Project Cost

2026 IUP Cost

TOTAL OF MassDEP PRIORITY PROJECTS (Count: 4)

$25,400,000

$25,400,000

TOTAL OF DRAFT INTENDED USE PLAN

$2,098,216,829

$727,921,292

continued on page 34

Sales • Rental • Service • Parts

Your full-line Case dealership. Sales. Rentals. Parts. Service.

With 71 years as a CASE dealer in NY, we are excited to be in New England serving Massachusetts, Rhode Island and Connecticut. And with our latest move from Worcester MA to Westborough we look forward to serving customers from our state-of-the art facility. Regardless of the brand you own, we are here to keep you doing your job.

*Westborough MA 97 Turnpike Road 508.845.4343

Woburn MA 192 New Boston Street 781.933.4217

Hartford CT 6 Sandra Drive 833.836.9800

We are a Certified Women’s Business – monroetractor.com *We’re bringing CASE back to Westborough! Stop by, we’re conveniently located for customers traveling Routes 495, 90, 30 and 20.

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

33


DEP/SRF continued from page 33

T

Approximately $434 Million Offered for Drinking Water SRF in 2026

he Massachusetts Department of Environmental Protection (MassDEP) is pleased to present the Draft Calendar Year 2026 Intended Use Plan (Draft IUP). The federal Safe Drinking Water Act requires Massachusetts to annually prepare an IUP – a plan identifying the intended use of funds in its Drinking Water State Revolving Fund (DWSRF). The State issues a Final IUP annually after a public review and comment period. The U.S. Environmental Protection Agency (EPA) must receive the Final IUP before it awards its annual Capitalization Grant to the DWSRF. The DWSRF is a joint federal-state financing program managed jointly by MassDEP and the Massachusetts Clean Water Trust (Trust) that provides subsidized loans and grants to improve and protect drinking water quality in Massachusetts. The DWS-

RF is funded with federal funding received through the EPA, which is supplemented by state matching funds, repayment of loans, and interest earned. The Draft IUP details the intended projects, total project costs, and amount of funding being offered through the DWSRF. This year, MassDEP and the Trust are offering approximately $434 million in financial support to wastewater projects across Massachusetts, subject to the availability of funding. Approximately $167 million is being offered to finance 16 new construction projects, $148 million is being offered to finance 13 previously approved multi-year projects, and $443,000 is being allocated to fund four Asset Management Planning (AMP) Grants. Additionally, more than $118 million in set-aside allocations are included in the Draft IUP.

Table 1 Drinking Water State Revolving Fund CY2026 Draft Intended Use Plan NEW PROJECTS

Rating Applicant SRF ID Project Project Cost

2026 IUP Cost

continued on page 35

34

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


DEP/SRF continued from page 34 NEW PROJECTS (Continued)

Rating Applicant SRF ID Project Project Cost

TOTAL OF NEW PROJECTS (Count: 16) (Average Rating: 526.00)

2026 IUP Cost

$354,199,224 $167,078,874

MassDEP PRIORITY PROJECTS Applicant

SRF ID

TOTAL OF MassDEP PRIORITY PROJECTS (Count: 3)

Project Cost

$118,391,514

2026 IUP Cost

$118,391,514

continued on page 37

3

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

35


CONSTRUCTION RISK SOLUTIONS

Starshep.com · 800-854-4625 36

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


DEP/SRF continued from page 35 MULTI-YEAR CARRYOVER AND STATUTORY PROJECTS Applicant

SRF ID

Project

Project Cost

2026 IUP Cost

TOTAL OF MULTI-YEAR CARRYOVER AND STATUTORY PROJECTS (Count: 13)

$649,594,335

$147,832,330

TOTAL OF DRAFT INTENDED USE PLAN

$1,122,185,073 $433,302,718

978.658.5300

900 Salem Street - Wilmington, Ma. www.beneventocompanies.com

Asphalt

MARCH, 2026

Concrete

Aggregates

Recycling

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

37


CRANE RENTAL • RIGGING • SPECIALIZED TRANSPORT

THE HEAVY LIFTING SPECIALISTS

(781) 858-7777 • www.nacranes.com LIKE US: facebook.com/northamericancrane

• • • • •

MOBILE CRANES CRAWLER CRANES TOWER CRANES INDUSTRIAL CRANES BOOM TRUCKS

• LOWBED SERVICE • INDUSTRIAL RIGGING

38

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


with UCANE’s Officers and Board Members For those who don’t know you, what is your professional background and how did you get started in the construction industry? I am one of three brothers that grew up in our family business. We three have been involved one way or another all our lives, and I have been formally employed at W. Walsh Company, Inc. full-time, since graduating college in 1989. What is your current role with W. Walsh Company, Inc. and what sets your company apart within the marketplace? I am President of W. Walsh Company. W. Walsh specializes in cleaning and cement-mortar lining of existing cast iron and steel water mains. Walsh handles all aspects of potable water utility construction associated with cleaning and cement-mortar lining projects, such as temporary water bypass system design and installations, valve operations, water main and water service installation, testing, and disinfection, along with performance of the actual cleaning and lining process.

UCANE Board Member Chris Walsh W. Walsh Company, Inc.

takes pride in our name. While growing up in this industry, we witnessed firsthand the hands-on approach that Bill Walsh had in making W. Walsh successful. He didn’t just wear many hats, he wore all of them at one time or another.

To what do you attribute your personal success, and what advice would you offer to other individuals looking to build a career in the construction industry?

You were recently appointed to the UCANE Board of Directors. How long have you been involved with UCANE and why did you decide to get involved? What do you see as UCANE’s most important role for its members?

I attribute my success to the work ethic instilled in us by my father, and the hard work of both of my brothers to understand the water industry and to protect the reputation of W. Walsh Company. I am fortunate to be in a business that still has family in it, and that family

This is my second time serving on the UCANE Board of Directors, and I have also served on the Safety Committee. I believe that UCANE’s most important role is keeping a watchful eye on the government regulations, continued on page 40

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

39


Under the Hard Hat continued from page 39

Est. 1926

PROTECTING YOUR ASSETS WHILE YOU BUILD YOUR FUTURE. legislation, and funding that directly affect the utility construction industry. Looking ahead to 2026, what do you see as the biggest opportunities and challenges facing your company and UCANE contractors more broadly? As an industry, we need to promote the importance of funding the maintenance of our underground infrastructure, which is both an opportunity and a challenge. Drinking water delivery and wastewater conveyance, handling, and treatment are not just conveniences, they are necessities for our society. It is surprising how much our utility systems are taken for granted. Part of that is because they are so reliable. Unfortunately, only during a catastrophic failure is there any public focus on the water and sewer systems, and the cost of regular maintenance and upkeep. n

40

Insurance & Bonding Professionals Lou Tonry | Commercial Insurance Kris Bibbo | Personal Insurance Kristin Erickson | Bonds

BRAINTREE 150 Grossman Drive Suite 200 Braintree, MA 02184

(617) 773-9200 LEXINGTON 238 Bedford Street Lexington, MA 02420

(781) 861-1800

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

Proud UCANE Member since 1954

TONRY.COM

MARCH, 2026


UCANE’s 2026 Schedule of Events

• March 25, 2026: UCANE’s 14th Annual Trade Show and Forecast Dinner Meeting with Presentations from MassDEP, MWRA, and BWSC – Four Points by Sheraton, Norwood, MA • April 13 - 17, 2026: Water Week Fly-In Federal Advocacy – Washington, D.C. • May 18 - 22, 2026: Infrastructure Week Fly-In Federal Advocacy – Washington, D.C. • July 15, 2026: UCANE’s 47th Annual Golf Tournament – Pinehills Golf Club, Plymouth, MA • September 16, 2026: UCANE’s 3rd Annual Topgolf Event – Canton, MA • October 14, 2026: UCANE’s 2nd Annual State House Day and Legislative Forum – Boston, MA • October 24, 2026: UCANE’s 72nd Annual Banquet – Marriott Hotel, Newton, MA

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

41


P.A. Landers, Inc. The Smart Choice For All Your Site Development Needs “WE DELIVER QUALITY BY THE TRUCKLOAD”

NEW LOCATION 608 Main St. Mashpee, MA 02649 800.660.6404

42

351 Winter St. Hanover, MA 02339 800.660.6404 781.826.8818 F: 781.826.6377

152 Route 130 Forestdale, MA 02644 800.834.4333 508.477.8818 F: 508.477.9692

228 Cherry St. Plymouth, MA 02360 508.747.1800 F: 508.747.6017

www.palanders.com

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


A recent Boston Globe editorial highlighted a striking paradox in rural Massachusetts: New Salem, a town of just over 1,000 residents nestled along the banks of the Quabbin Reservoir, sits beside one of the largest sources of drinking water in the state—yet struggles to provide reliable water to its own community.

T

he Quabbin supplies millions of residents in Eastern and Central Massachusetts through the Massachusetts Water Resources Authority (MWRA). But in New Salem, there is no municipal water system. Homes and public buildings rely on private wells. When the well serving the town administrator’s office recently ran dry, bottled water became a necessity and staff were forced to use facilities across the street. The irony is difficult to ignore.

The Challenge of Geography and Resources As reported in the original article, New Salem’s terrain presents a major barrier. The town’s hilly landscape and dispersed population make a traditional, town-wide water system physically and financially impractical. Board of Selectmen Chair Susan Cloutier noted that while a limited municipal system in the town center might be feasible, providing emergency access for residents whose wells fail or become contaminated, it would require funding far beyond what a community with a $3.5 million annual budget can easily support. Many municipal roles in town are filled by volunteers. A coalition of Quabbin watershed towns has proposed legislation to establish a trust fund, financed by MWRA member communities, to support towns bordering the reservoir. While the state already provides some compensation to these communities, proponents argue that the proposal reflects a deeper reality: many Massachusetts towns lack sustainable, reliable water infrastructure, and there is no comprehensive statewide framework to address the issue.

A Broader Statewide Problem New Salem is not alone. Across Massachusetts, communities face mounting water challenges; limited supply, aging infrastructure, contamination concerns, and increasing demand. The MWRA currently provides drinking water to 61 member communities. However, joining the system can be costly, and membership has historically been limited to communities with the financial capacity to absorb the expense.

MARCH, 2026

Recognizing growing regional needs, the MWRA has conducted expansion studies in recent years examining service to: •

The MetroWest Region

•

The Ipswich River Basin

•

The South Shore

•

Quabbin Watershed Communities

Each region faces distinct pressures. The Ipswich River Basin is considered “stressed,” with demand frequently outpacing supply and triggering seasonal water restrictions. South Shore communities confront similar constraints. PFAS contamination has added costly treatment requirements for several municipalities statewide. In some areas, limited water supply directly constrains economic development. For example, Weymouth explored joining the MWRA while planning redevelopment of the former South Weymouth Naval Air Station, recognizing that existing water sources could not support the scale of proposed residential and commercial growth.

The Cost of Expansion Yet expansion is not simple. The MWRA does not have unlimited capacity, and infrastructure expansion carries staggering price tags. According to recent studies referenced in the article:

continued on page 45

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

43


44

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


New Salem continued from page 43 •

Extending Quabbin water to New Salem and three neighboring towns was estimated at $215.4 million (2024 dollars).

•

Developing a new groundwater source for the same communities would cost approximately $112.4 million.

•

Expanding service to 10 South Shore communities could reach $1.25 billion (2022 dollars).

•

Projects in the Ipswich River Basin and MetroWest could range from $110 million to $1.1 billion, depending on scope.

For small, rural communities, these numbers are simply out of reach.

The Need for a Statewide Plan As David McGlinchey of the Massachusetts Rivers Alliance argued in the original article, Massachusetts lacks a comprehensive, strategic plan for managing future water allocation and supply. The state’s Water Resources Commission is well positioned to lead such an effort. A statewide water plan could: •

Assess long-term supply and demand across all regions.

•

Identify infrastructure gaps.

•

Prioritize investment.

•

Evaluate when and where MWRA expansion is viable.

•

Develop equitable funding mechanisms for smaller communities.

Without coordinated planning, Massachusetts risks deepening regional disparities; where some communities enjoy resilient, redundant water systems while others depend on private wells vulnerable to drought, contamination, or simple depletion.

A Warning and an Opportunity New Salem’s situation is not merely a local challenge; it is a cautionary example. A town located beside one of the Commonwealth’s most critical water resources should not find itself without dependable access. Before water scarcity, contamination, or infrastructure failure becomes more widespread, Massachusetts has an opportunity to act deliberately rather than reactively. The Commonwealth has long been a national leader in water quality and environmental protection. Ensuring that leadership extends to long-term water equity and infrastructure resilience will require strategic vision, collaborative financing, and statewide commitment. The question is not whether the need exists—it clearly does. The question is whether the state will seize this moment to plan for the decades ahead. n

“Fueling America’s Progress” Your Complete On-Site Fuel & Petroleum Service

• Ultra Low Sulfur Diesel • Gasoline • Kerosene Boston, MA New York, NY Providence, RI

• Biodiesel • Lubricants • Storage Tanks and Equipment LOCATIONS

Baltimore, MD Philadelphia, PA Somerville, NJ

Hartford, CT Pleasantville, NJ Washington, DC

1-800-894-FUEL (3835) • www.tayloroilco.com

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

45


Put Funding and Policy First, Please The Globe’s editorial calling for a statewide water plan (“Massachusetts needs a statewide water plan,” Opinion, February 19) highlights real water-supply challenges. But another plan is not what communities need most. The more immediate barriers are insufficient infrastructure funding and state policies that hamper responsible local water-

supply development. Across Massachusetts, aging drinking water, wastewater, and stormwater systems are beyond their intended lifespans. An estimated $37 billion will be needed over the next 20 years to meet existing regulatory requirements — a figure that does not include the cost of removing newly regulated PFAS, already affecting many public water systems and often requiring treatment plants costing tens of millions of dollars. Meanwhile, the state’s allocation of federal State Revolving Fund dollars — the backbone of water infrastructure financing — is being cut by more than 60 percent, which reduces statewide funds available for projects. Planning without protecting infrastructurefunding will not solve the problem. Communities also face restrictive water-quantity regulations, lengthy permitting, and rigid water-use policies that can discourage local supply development. Each community has unique needs and should be supported in developing a plan that meets those needs.

1200 Worcester Road 625 Pleasant Street Watertown, Framingham, MA . 617 (508) 532-3200 MA. - 924 - 3673 MATel: Ask for: Chris Uhl

watertownford.com mcgovernfordofframingham.com 3 Locations to– Serve You& TRUCK in Eastern SALES – SERVICE PARTS – CAR RENTAL MA

46

Water infrastructure underpins housing, economic development, public health, and emergency preparedness. A true statewide strategy must focus on sustained investment and regulatory flexibility — not simply production of another report. Jennifer A. Pederson, Acton (The writer is executive director of the Massachusetts Water Works Association, a nonprofit representing 1,600 drinking water professionals across the Commonwealth.) n

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Infrastructure Failure

UPDATED: No Easy Fix for Potomac River Sewage Spill, Now Estimated at $20M

New Salem and the Urgent Case for a Statewide Water Strategy

One month after a collapsed Washington, D.C., pipe spilled more than 240 million gallons of raw sewage into the Potomac River, contractors face challenges to clear the damaged section and begin repairs at the site, now a declared disaster area.

O

ne month after a collapsed pipeline north of Washington, D.C., spilled about 240 million gallons of raw sewage into the Potomac River and possibly between 300 and 400 million—which could be the largest wastewater spill in U.S. history— efforts are progressing to clear the damaged section and begin repairs despite weather and other impacts. Further questions remain regarding the time and investment needed to restore the critical infrastructure and reduce environmental impacts, even with a February 22 disaster declaration and new assistance from the U.S. Army Corps of Engineers and other federal agencies. The January 19 collapse in Montgomery County, MD, occurred in a section of the 72-inch diameter Potomac Interceptor operated by the District of Columbia Water and Sewer Authority (DC Water). Adjacent to the river near the I-495 Beltway crossing, the 1960s-era pipe is part of a regional system that conveys 60 million gallons of sewage daily from areas of northern Virginia and Maryland to the city’s Blue Plains wastewater treatment plant. Officials have not

MARCH, 2026

disclosed the cause of the collapse, which they said is under investigation. Since the spill, DC Water has said subsequent discharges have largely been contained with a temporary bypass system that uses eight high-capacity pumps to route sewage flow about ½-mile around the break through a dry, clay-lined section of the historic C&O Canal and back into the pipeline. Despite flow surges from two big snowstorms and multiple rain events in recent weeks, DC Water reports no overflows since February 8. “I’m reassured that DC Water is acting very aggressively to try to repair this, but there’s still a hundred questions out there about what the affect is on the C&O Canal, what the impact is on the Potomac River,” Maryland Representative Jamie Raskin (D) said at a February 26 DC water briefing in Bethesda, MD. After President Donald Trump’s initial social media criticism of local officials for the line collapse and response—despite their assertions that the pipeline is on federal property—he approved the February 18 recontinued on page 49

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

47


®

®

rainforrent.com

BUILD WITH CONFIDENCE

28 Trolley Crossing Charlton, MA 01507 (508) 248-4607

48

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Potomic River continued from page 47 quest of Washington, D.C., Mayor Muriel E. Bowser (D) for federal repair and cleanup assistance. The Corps and the Federal Emergency Management Agency have joined the effort, already including the U.S. Environmental Protection Agency. The latter is involved to prevent additional overflows until the pipe is repaired, it said in a statement.

Rock Blockage Removed February 26 Contractors have refined a managed approach to take individual pumps offline during low-flow periods for preventive maintenance, while the Corps implements measures to contain and divert stormwater from the collapse and bypass area and assist in other project execution areas. Drinking water is unaffected by the spill, as intakes for that system are located several miles upstream, said Col. Francisco Peña, who leads the Corps Baltimore District. With a temporary steel bulkhead fully isolating the damaged section, inspectors found a large rock and debris blockage about 30 feet away from the break, DC Water said. Boulders, originally used as construction backfill, likely entered the pipe during the initial collapse. The pipe section was deemed structurally compromised and unsafe for workers, so

crews excavated a new 30- to 40-ft section to create another access point. Contractors cut the crown of the pipe to provide direct access to the blockage, and DC Water said February 26 that the blockage has been removed manualy and by machine, but some large rocks and boulders remain in other sections of the pipe and may require additional excavation to remove. The utility said it now intends to fully develop an emergency repair strategy that could take up to six weeks to complete before the bypass system can be decommissioned. “An environmental restoration plan is being developed in coordination with federal, state, and local regulators and will be released to the public when approved,” was said on February 24. An agency spokesperson said the cost of both the repair and environmental cleanup has now reached about $20 million, according to multiple media reports.

Long Term View DC Water has not responded to ENR’s requests for information on contractors involved in the response, or how the incident may affect the scope and cost of the agency’s current and long-term infrastructure upgrade efforts—including a previously stated continued on page 50

YOUR TRUSTED PARTNER IN QUALITY & CONVENIENCE We are proud to offer solutions for utility contractors, sitework and road builders, as well as municipalities across the region. Recycled gravel Sand bedding & crushed stone Delivery services Mobile crushing Accepting excavated materials On-site credit card payments

FOR YOUR CONVENIENCE, WE HAVE TWO LOCATIONS:

1

Canton Yard

90 Cedar Street, Canton, MA 02021

MARCH, 2026

2

South Boston Yard

300 West First Street, South Boston, MA 02127

SCAN TO LEARN MORE

RJVCONSTRUCTION.COM/PRG

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

49


Potomic River continued from page 49 ten-year, $625-million program underway to rehabilitate Potomac Interceptor sections. The agency has said the 2,700-linear-foot section where the break occurred was targeted for rehabilitation, with work to accelerate when pipeline emergency repairs are complete. Estimated to take nearly one year, the project will use sliplining methods where feasible, while other areas of the pipe will be reinforced and strengthened with a high-strength geopolymer lining. Bowser said in a February 18 letter to President Trump and FEMA that she seeks “100% reimbursement for costs incurred by the District” and D.C. Water, to avoid ratepayer impact. In media comments, she said that “outreach from the president’s team … would indicate to me that they’re supportive of the request.” But according to comments by D.C. emergency management Director Clint Osborn made at a February 25 public briefing at DC Water headquarters, reported by locally-based WTOP News, the declaration does not allow the city or DC Water to recoup money already spent on repairs. He clarified in earlier statements that the federal government would cover 75% of the utiity company’s total repair and cleanup costs as only applying when U.S. agencies directly

perform work assigned through the emergency declaration. “We’re going to continue to work through the preliminary damage assessment process with FEMA this week to determine whether we can convince [the agency] and the White House to upgrade us to a major disaster declaration, which would get us reimbursement,” he said. “How the cost will be borne and allocated is still being worked out,” by DC Water and its four county customers—Montgomery and Prince George’s in Maryland, and Fairfax and Loudoun in Virginia, the utility firm spokesperson said. Meanwhile, a 14-member group of regional House members said it is seeking additional funding for the interceptor repair and upgrade, and related work on other U.S. wastewater treatment systems, “Congress must play a role in solving this crisis, investing in our nation’s wastewater infrastructure, and preventing this and similar crises from recurring,” they said in a February 24 letter to the House Transportation and Infrastructure Committee leaders. “The failure of the Potomac Interceptor is an acute crisis for our region.” Yet to be determined are the spill’s lingering effects on the river’s water quality. Sampling by DC Water and state agencies have shown gradually decreasing, although still fluctuating, levels of E. coli and other continued on page 51

NOW AVAILABLE: BOSTON GRAVEL PLANT LOCATION:

200 LEGACY BLVD. DEDHAM, MA 02026 Plant: 617-590-0024

MATERIALS AVAILABLE FOR PURCHASE: • 1” MINUS PROCESSED GRAVEL • ¾” & 1½” CRUSHED STONE • SCREENED LOAM • SCREENED SAND MATERIALS ACCEPTED: • BROKEN ASPHALT • NON & REINFORCED CONCRETE • CONCRETE WITH WIRE MESH • ROCK • BLASTED LEDGE

50

OFFICE:

1039 EAST STREET DEDHAM, MA 02026 Office: 781-329-4111 Fax: 781-329-1039

HOURS OF OPERATION: MONDAY-FRIDAY: 6:30 A.M. – 4:00 P.M. SATURDAY: 7:00 A.M. – 12:00 P.M.

DELIVERIES AVAILABLE ON LARGE ORDERS. PLEASE CALL FOR PRICING.

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Potomic River continued from page 50 bacteria downstream from the overflow, with health advisories issued, according to DC Water posted data. Betsy Nicholas, president of the Potomac Riverkeeper Network, said DC Water’s overall collapse response has been good, and that its independent testing shows downstream water quality largely meeting recreational contact standards despite occasional spikes from high flows and melting ice. But she cautioned that “testing should continue,” especially as warmer weather draws people to riverside areas. Another concern is that, like other infrastructure agencies, DC Water lacks resources to address other parts of its infrastructure system that may be in jeopardy of failing. “Hopefully, this incident will be the poster child for preventing similar incidents in the future,” Nicholas said. “It is important to note ... that this incident does not reflect a systematic failure on the Potomac Interceptor,” David Gadis, DC Water CEO and general manager, told regional government officials on February 23, although describing it as a “known vulnerability” due to its age. “However it reinforces the importance of the Potomac Interceptor and the continued investment that must occur in [it] to get to where we need to get.” Written by Jim Parsons & Debra K. Rubin. Reprinted from Engineering News Report. n

Green Beam Pipe Laser Compact & Powerful! • 500 ft. (150 m) operating range • High visibility Green Beam excellent for use in dark pipe conditions • Stop by for a complete demonstration on this NEW state-of-the-art Pipe Laser • From the leaders in Pipe Laser technology - Spectra Precision Model DG613G

5 Eastpoint Drive, Unit 1, Hooksett, NH 03106 Phone: 603-623-0188 • www.eastpointlasers.com

A trusted partner in construction...

now as The Baldwin Group For over a decade, RogersGray has been a proud UCANE member, and that commitment continues as we transition to The Baldwin Group. While our name is evolving, our dedication to protecting what matters most remains unwavering—now with even greater resources and expertise. We’re here to support owners, developers, general contractors, designers, and subcontractors, helping them navigate risk, strengthen their businesses, and achieve their next level of growth. At The Baldwin Group, we’re not just protecting your projects—we’re Protecting the Possible.

Strategic differentiators: Dedicated Construction Practice Group Captive and standard market relationships Our people

RogersGray is becoming The Baldwin Group

Service strategy Trust & transparency

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

51


Norton, MA

trench box Sales & Rentals

Road plates “WE'LL HELP KEEP THE TRENCH...AND OSHA OFF YOUR BACK!”

Family Owned & Operated 30+ Years of Industry Experience New England’s Only Kundel Trench Box Dealer

gla n

d

of all

En

Servi ng

W

(

88

New

North East Shoring Corp., Inc.

52

|

422-43 ) 8 Call us today for more info

Norton, MA

|

43

northeastshoring.com

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

Since 1996

|

888-422-4343

MARCH, 2026


Digging Smarter: Practical Lessons from Dig Safe’s February Training Breakfast

U

CANE staff joined a broad coalition of contractors and utility professionals on Thursday, February 26 for the Managing Underground Safety Training hosted by Dig Safe System, Inc. and National Grid, which focused on excavation safety, regulatory enforcement, and best practices for working around underground utilities. The list of presenters included staff from the Massachusetts Department of Public Utilities Pipeline Safety Division, which reviewed common violation types associated with Dig Safe tickets, including failing to obtain a ticket, timeliness errors when submitting violation reports, marking issues, and excavation process mistakes. Non-gas violations carry a minimum civil penalty of $1,000, with second offenses within 12 months increasing to $5,000–$10,000, while natural gas violations can result in significantly higher fines. In some cases, violators may be allowed to attend the Managing Underground Safety Training (MUST) program instead of paying the full penalty. Overall, the training emphasized that Dig Safe functions primarily as a private notification center that alerts member utility companies of planned excavation activity. Utilities then mark their own facilities or hire contracted marking firms. Contractors were reminded that Dig Safe tickets in Massachusetts are valid for 30 days and that excavation may begin only after the required three business day notification period has passed. Pre-marking of proposed excavation areas is required for all tickets, and contractors are responsible for maintaining the utility markings throughout the life of the ticket or requesting remarks if they become unclear. Best practice is to begin work shortly after markings are completed to reduce the likelihood of faded or damaged marks. Speakers also highlighted field practices that help reduce the risk of damaging underground infrastructure. Contractors must hand dig within 18 inches on either side of marked utilities, with mechanical equipment permitted only for the initial pavement penetration. In complex utility corridors, technologies such as air spades or vacuum excavation may be necessary to safely expose utilities. Private locating firms also recommend using passive locating tools to double-check markings before digging. Attendees were reminded that Dig Safe does not mark privately owned underground utilities – such as internal electri-

MARCH, 2026

cal or water lines on large properties like universities, hospitals, or multi-structure residential lots – making it essential for contractors and project managers to identify and account for those lines before excavation begins. Overall, the training provided valuable practical guidance for contractors, field personnel, and administrative professionals responsible for coordinating excavation work and ensuring underground utility safety. n

JOHN HOADLEY AND SONS, INC. WATERWORKS SPECIALIST

TEL:781-878-8098

Water-Sewer-Drain Supplies Vactor Service/Hydro Excavation

● 24/7 Emergency Service ● Plant Maintenance ● Catch Basin Cleaning ● Filter Media Removed from Tanks ● Lift Stations and Pump Chamber Cleaning ● High Velocity Water Jetting ● Clean Sewer and Drain Lines

T.V INSPECTION & SEWER MANHOLE AIR / VACUUM TESTING

www.hoadleyandsons.com

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

53


&

DEWATERING | BYPASS PUMPING | ONE-PASS TRENCHING | POWER GENERATION

Mersino is the premier specialty contractor that provides solutions to meet your challenging needs nationwide. 24 HOURS | 7 DAYS A WEEK | 365 SERVICE WWW.MERSINO.COM | 866.637.7466

54

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Patrick W.Underhill Saltmarsh Blake Corporate Safety Director President Industrial Safety & Rescue J. Derenzo Companies

March is National Ladder Safety Month A Tool We Use Every Day — A Risk We Often Underestimate

M

arch marks National Ladder Safety Month, an annual safety awareness campaign led by the American Ladder Institute (ALI). The initiative focuses on reducing ladder-related injuries and fatalities through education, training, and jobsite awareness. Ladders are among the most commonly used tools on any construction project including underground and utility work. Whether accessing a manhole, climbing from a trench, reaching overhead connections, or entering a vault, crews rely on ladders daily. Because they’re routine, they rarely receive the same level of attention as heavy equipment or confined space entry.

The Numbers Are Clear: • • • •

Approximately 160 workers die each year from ladder-related incidents. More than 130,000 ladder injuries are treated in emergency rooms annually. Ladder falls account for nearly 20% of all occupational fall injuries. Nearly 90% of ladder fall injuries occur from heights under 20 feet.

Massachusetts Incidents Hit Close to Home: In February 2026, two construction workers in Duxbury, Massachusetts fell approximately 20 feet from a ladder at a residential construction site. Both were hospitalized. In 2025, a worker in Edgartown, Massachusetts died after falling from a ladder at a construction proj-

MARCH, 2026

ect, a tragic reminder that routine tasks can turn fatal. Earlier, a Massachusetts carpenter lost his life when his extension ladder slipped on stone pavers, a preventable setup failure.

Why Underground and Utility Work Faces Unique Risk These incidents remind us that ladders are more than simple tools — they are potential injury vectors if not used with understanding, planning, and respect. In New England, crews contend with frozen ground, mud, gravel, sloped surfaces, congested work zones, and wet equipment. When ladders shift, tip, or sink into soft ground, the margin for error disappears.

The Most Common Causes of Ladder Falls • • •

Improper ladder selection Incorrect ladder angle Unsecured bases or tops continued on page 56

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

55


Platform ladders for longer duration work at height • Placement on uneven surfaces • Multi-position ladders for variable access needs • Overreaching Each type has its purpose, weight limits, and proper application. Making the wrong choice can create in• Carrying tools while climbing stability or increase the likelihood of a fall, especially • Failure to inspect damaged equipment when workers lean or reach beyond safe boundaries Field-Tested Practices for 2. Proper Setup: The Foundation of Safety: Even a perfectly selected ladder can become dangerous Utility Crews without correct setup. 1. Match the Ladder to the Job: There’s no oneHere are essential practices to prevent falls: size-fits-all ladder for all tasks. Construction sites 3. Correct Angle: A ladder should be positioned at typically use: about a 4:1 ratio, one foot out at the base for every • Step ladders for stable, low-height work four feet of height. This angle maximizes stability and • Extension laddersBoston for roofArea access or multi-story minimizes the risk of tipping. Locations tasks 4. Secure Base and Surface: Uneven or soft ground under lad2 Dexter Street ders is a recipe for disaster. Use Everett, MA 02149 Boston Area Boston Area boards, ladder levelers, or other Locations Locations 431 Second Street stabilizing accessories to ensure the base is firm and won’t shift unEverett, MA 02149 2 Dexter Street 2 Dexter Street der the load. Everett, MA 02149 Everett, MA 02149 5. Extend Above Landing: The ladder should extend at least three 431 Second Street 431 Second Street feet above the upper landing surEverett, MA 02149 Everett, MA 02149 face to give secure handholds and BOSTON AREA LOCATIONS prevent overreach, a factor OSHA 100 Fremont Street 2 Dexter Street 431 Second Street Worcester, MA 01603 specifically cited in fall hazard inEverett, MA 02149 Everett, MA 02149 spections in Massachusetts. 6. Avoid Carrying Tools While Climbing: Never carry heavy tools while ascending or descending — use tool belts, hoists, or lift lines. Hands-free climbing keeps balance focused on the ladder itself. 7. Three Points of Contact: More Than a Mantra: The safety industry emphasizes maintaining three Minichiello Bros./Scrap-It, Inc., Minichiello Bros./Scrap-It, Inc. points of contact — two hands and Serves over 2500 customers a week and is one of New England’s largest Serves over 2500 customers a week and is one New England's largest buyers, one foot, or two feet and one hand buyers, sellers, and processors of scrap metal. Forour overgoal 60 years goal sellers and processors of scrap metal. For over 60 years has our remained — at all times while climbing. It remained the same - to in provide the best along prices in thetop industry along with the same - tohas provide the best prices the industry with notch might sound simple, but in practice top notch service! Fred Rogers at 617-595-5505 customer service! Callcustomer Fred Rogers at Call 617-595-5505 it dramatically increases stability Minichiello Bros./Scrap-It, Inc., and reduces slips. Minichiello Bros./Scrap-It, Inc.,

Safety Corner continued from page 55

•

Serves over 2500 customers a week and is one New England's largest buyers, sellers and processors of scrap metal. For overa60week years ourisgoal Serves over 2500 customers and onehas Newremained England's largestQuick buyers, Ladder Safety Audit for March he same - to provide the best in theof industry along with notch sellers and prices processors scrap metal. Fortop over 60 years our goal has remained customer service! the Callsame Fred -Rogers at 617-595-5505 to provide the best prices in the industry along with top notch • Are all ladders inspected customer service! Call Fred Rogers at 617-595-5505 weekly?

•

Turn your metal into money today! Turn your metal into money today! Minichiello Bros. Inc./Scrap-It Inc. Minichiello Bros. Inc.,/Scrap-It Inc.

•

Are damaged ladders tagged and removed? Are crews trained on the 4:1

56

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

Turn your metal into money today!

continued on page 57

MARCH, 2026


Safety Corner continued from page 56 • •

setup rule? Are toolbox talks including ladder safety? Are supervisors correcting unsafe behaviors?

Training: From Compliance to Competency Ladder safety isn’t just a checklist — it’s a competency. Construction teams should invest in training that includes: • Inspection routines • Proper setup procedures • Hazard recognition • Task-specific ladder use • Environmental considerations (weather, surfaces, obstacles) Training should also include scenario-based exercises that reflect the kinds of tasks workers perform daily. National Ladder Safety Month is more than a calendar event — it’s an invitation to strengthen workplace culture. A culture that prioritizes safety empowers every worker to: • Speak up about hazards

• • • •

Refuse unsafe work Participate in training Report equipment defects Hold peers accountable This shared commitment transforms ladders from hazards into reliable tools that support productivity and well-being.

Ladders may be simple, but their risks are real. From fatal falls to near misses, ladder safety deserves focused attention and continuous reinforcement. This month is an opportunity to reinforce safe habits, increase training, perform inspections, and protect your workforce. In underground and utility construction, safety culture is built one decision at a time. n

WHATEVER IT TAKES.

WE’VE GOT YOU COVERED. The Right Equipment, Right When and Where You Need It Reliable and Ready To Work 24/7/365. ELEVATE OPERATIONS WITH TOP-TIER EQUIPMENT RENTALS MA: Chicopee • Plymouth • Randolph • Shrewsbury • Uxbridge NH: Chichester • Gorham • Lebanon • Plaistow ME: Portland NY: Auburn • Dansville • Ithaca • Rochester

` Rent by the Day/Week/Month

` Caterpillar and Leading Brands

` Low Hour/Late Model Machines

` Independently Owned and Locally Operated

877-DIG-LIFT • MILTONRENTS.COM

Milton Rents Magazine Ad 5.5 x 4.25 LANDSCAPE.indd 1

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

4/5/24 9:09 AM

57


58

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


UCANE’s 14th Annual Trade Show Will be held on Wednesday, March 25, 2026 prior to our Forecast Dinner Meeting

Trade Show booths offered at NO COST to Construction Outlook Magazine Advertisers.

If you are not currently advertising in Construction Outlook, we hope you will consider placing an ad. Our monthly magazine showcases your products and services to contractors and municipal officials who use them. Our Trade Show is a great opportunity to meet with UCANE members and guests face-to-face.

In addition to placing your ad in our magazine, your ad will also be on our website and issuu.com. Space is limited, so if you would like to place an ad in our magazine and reserve a booth at our Trade Show, please contact Suzanne Hatch as soon as possible at shatch@ucane.com.

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

59


Your Partner for HDPE Product & Services More contractors are turning to High-Density Polyethylene (HDPE) piping—and F.W. Webb’s Water Works team delivers everything you need to get the job done right.

End to End Approach

For guidance on the unique HDPE installation process, the knowledgeable team at F.W. Webb is ready to help. From our large selection of in-stock materials and McElroy fusion equipment to pre-project planning, certified training, rentals and service, we’re your single source trusted partner. Our experts review your plans, recommend the right HDPE pipe, fittings, and tools, and guide you through installation—eliminating guesswork and saving time. Whether you’re specifying HDPE for the first time or scaling up, our team helps you do it right—from the ground up.

GUIDANCE

Pre-project guidance on all the necessary materials and equipment

PRODUCTS

Full range of HDPE pipe, fittings, accessories and tools

EQUIPMENT

McElroy Certified Dealer, Rental Distributor and Authorized Service Center

TRAINING

Fusion Training Center in Springfield, MA or job site training

To speak with someone today, contact the Water Works Malden location at 781-322-1238

fwwebb.com/waterworks


For sponsorships or reservations contact Suzanne at shatch@ucane.com (Reserve your spots today! This will sell out quickly.)


Make Your Project Stand Out:

Expert Construction Signage Solutions

• Indoor/Outdoor Signage • Flyers/Brochures • Target Marketing • Direct Mail • Banners

Contact Ernie@websterprinting.com 781.447.5484

LARGE RESOURCES. LOCAL RELATIONSHIPS.

IS YOUR INSURANCE PROGRAM KEEPING PACE IN TODAY’S MARKET? Let us review your programs and recommend improvements to ensure you are fully protected should the unexpected happen. COMMERCIAL INSURANCE & BONDS • All forms of liability and property coverages • Bonds including Express Bond Program • Competitive terms • Personalized service • Highly experienced with Construction programs

RISK MANAGEMENT SOLUTIONS • Employee and executive benefits • Retirement planning services • Investment advisory services • Private wealth management • Personal and high-net-worth portfolios

CHRISTOPHER CLARK, PRINCIPAL, CLIENT ADVISOR World Insurance Associates LLC, 50 Prospect Street, Waltham, MA 02453 O 781-642-9000 | D 781-398-9318 | M 508-400-4010 | christopherclark@worldinsurance.com

62

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

worldinsurance.com

MARCH, 2026


Pittsfield Seeks $28M Borrowing for Water and Sewer Infrastructure PITTSFIELD, MA — The city is seeking a total of $28 million in borrowing authorizations to upgrade its drinking and wastewater infrastructure.

T

his includes $13 million for upgrades to the wastewater treatment plant and $15 million for upgrades to the Cleveland and Ashley Water Treatment Plants, which are located outside Pittsfield. The City Council referred the $15 million borrowing request to the Finance Subcommittee. The full drinking water project is expected to cost $165 million over the next eight years, with $150 million for long-term construction and $15 million for near-term needs. The initial ask would fund the final design and permitting for Phases 1-3, Phase 1 of interim updates, allowances, and contingency. After the meeting, Commissioner of Public Services and Utilities Ricardo Morales explained that these are needed repairs so the current infrastructure can be stretched a little longer while design work is underway. Pittsfield's two Krofta drinking water treatment plants were installed in the 1980s. The city says they are beyond anticipated useful service and at risk for catastrophic failure that could leave Pittsfield with a shortage of potable water. Krofta is a compact filtration system that Pittsfield will continue to use. There are four units at the Cleveland WTP and two at the Ashley WTP. Morales said the system is "very good" but needs to be upgraded. "We were one of the first to use that type of technology in the 80s, and it's outdated now, and getting parts and getting repairs to it is very costly because of the outdated technology that it's using, and we can replace that with better infrastructure," he explained. "We need to build a chemical facility on the Cleveland side. We already have that done at Ashley with [American Rescue Plan Act] funds, largely, and then we need to build better tank holding systems at the plants to allow for chlorination to happen at the plant, instead of on its way down to Pittsfield." The Ashley WTP received more than $4 million in ARPA funds. From 2019 to 2022, the city piloted a new generation Krofta with approval from the Department of Environmental Protection. Morales said they need to be tested on-site to ensure that they can

MARCH, 2026

provide the expected quality of water. According to the project timeline, starting this year, two finished water storage tanks would be designed and constructed, chemical improvements would be made at the Cleveland WTP, and the East New Lenox Road flow control station would receive a new pump station to allow the Ashley WTP to be offline during the third phase. Both WTPs would undergo "major" process and building improvements starting in 2028, and there would be upgrades to the Lower Ashley Reservoir and gatehouse. Construction is expected to be complete in late 2033. Pittsfield provides drinking water for Dalton, the town pays for sewer, and the city has been in conversations with the Dalton Fire District about the upgrades, Morales reported. Dalton anticipates a rise in water and sewer rates. Town Manager Eric Anderson recently said Pittsfield has proposed raising its fees for the town to include a charge to contribute towards the capital costs, but there is no official agreement with the city yet. Recently, the Finance Subcommittee discussed the borrowing for sewer infrastructure, which was reduced from $15.2 million. After a couple of hours of questions and concerns, it was tabled until next month. Councilor at Large Kathy Amuso referenced the conversation, asking for a "lot of data" at the next Finance Committee meeting. Funding would support a new administration and laboratory building at the plant. The WWTP’s existing laboratory building was built in 1938 and adapted for use in 1973, and is said to no longer meet current needs. Mold, layout issues, rodents, ineffective air conditioning, and insufficient lab space were cited as conditions that necessitate the project. This means samples have to be sent to external labs, causing delays, while the new lab will allow same-day analysis. Written by Brittany Polito. Reprinted from iberkshires.com n

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

63


Products and Services

25 Concord Street Pawtucket, RI 02860 Tel: (401) 722-4488 Fax: (401) 312-0992 pawtuckethotmixasphalt.com

64

Hot Mix Asphalt Paving Fine Grading Cold Planning Reclaiming RI & MA DOT Approved

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


AMWA Testifies at Senate EPW Committee Hearing on Cybersecurity At the end of January, the Association of Metropolitan Water Agencies (AMWA) testified before the Senate Environment and Public Works Committee for a hearing on "Identifying and Addressing Cybersecurity Challenges to Protect America's Water Infrastructure." Scott Dewhirst, Deputy General Manager of Engineering and Technology at Fairfax Water, represented AMWA during the hearing, where he called on the Committee to increase federal assistance for drinking water system cybersecurity.

A

MWA’s written testimony outlines the current cyber threat landscape for the water sector, naming an increase in frequency of cyberattacks, increasingly sophisticated attacks, and vulnerabilities within the sector. It points to existing EPA and CISA tools for water systems to identify vulnerabilities and implement best practices, as well as legislative recommendations to improve overall water system cybersecurity. "Drinking water systems represent an attractive target for cyber adversaries," Mr. Dewhirst told the committee in his prepared testimony. "A successful attack could not only threaten water quality and public health, but would also undermine public confidence in the safety and reliability of drinking water." Mr. Dewhirst highlighted the need to increase water system access to risk mitigation and incident response resources, such as through participation in the Water Information Sharing and Analysis Center (WaterISAC). He also spoke about fully funding federal grant programs to help water systems address cyber threats and exploring new industry-led oversight models to encourage water systems to adopt cybersecurity practices based on utility size. During the hearing, Senator Markey (D-MA) and Senator Lisa Blunt Rochester (D-DE) highlighted the Water Intelligence, Security, and Cyber Threat Protection Act (S. 1118) and the Water Infrastructure Resilience and Sustainability Act (S. 3590) as avenues to bolster cybersecurity for water systems. AMWA worked with Senators Markey and Blunt Rochester, respectively, to develop each bill, and in the leadup to the hearing, AMWA joined other water sector groups in writing to congressional leaders to outline broad support for these and other proposals that are intended to help water systems increase their cybersecurity preparedness.

MARCH, 2026

In the coming months AMWA will continue to advocate for passage of these proposals, and will offer to work with lawmakers to develop or refine additional ideas to increase cybersecurity in the water sector. AMWA encourages members to visit the association’s Legislative Action Center to message their Representatives and Senators in support of these and other legislative priorities. n

IF YOU LIVE FOR IT, WE’LL HELP YOU PLAN FOR IT.

Patrick Di Cerbo

CFP®, MSFS Wealth Management Advisor 518-281-8200 pat.dicerbo@nm.com www.patdicerbo.com

07-1012 ©06-2023 The Northwestern Mutual Life Insurance Company (NM), Milwaukee, WI.

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

65


UCANE’S Employee Safety Manuals UCANE’s Employee Safety Manuals Your Company Must Have a Comprehensive Safety Program! This year’s Safety Manual includes information on: • Updated DOL Drug Testing Information and Updated CDL Information • Massachusetts Safety Standards - COVID-19 • OSHA’s Final Rule on Silica Exposure Limits • OSHA’s Final Rule on Improved Tracking of Workplace Injuries and Illnesses • OSHA’s Final Rule on Confined Space in Construction • OSHA’s New Requirements for Reporting Severe Injuries

EMPLOYEE SAFETY EMPLOYEE MANUAL SAFETY MANUAL

Promote a Safe Working Environment

It should be your company’s policy to provide a safe place to work, with the prevention of accidents being your ultimate goal. Your Insurance/Bonding carrier requires a Safety Program. State and Federal Agencies require a Safety Program.

OSHA Inspectors Will Be Enforcing:

• Overall Construction Safety (29 CFR 1926) • Excavating Standards • Written Safety and Health Plans

• Hazard Communications Programs • Drug Free Workplace • OSHA 10-Hour Training Requirements

Examine the UCANE Pocket Directory

When ordering Company Safety Manuals, the Safety Manual section only, in the back of UCANE’s Pocket Directory, will be made up into an individual Employee Pocket Safety Manual with Your Company Name and Logo printed on the cover. Employee signature cards verifying compliance with safety manual procedures are included. When signed, these cards should be placed in each employee’s file.

-----------------------------------------------------------------------------------------------------Employee Pocket Safety Manual Order Form

Company Name:___________________________________ Authorized By:________________________ Pocket Manuals w/Signature Cards: Qty.:____________ x $4.75 Ea. = $_________________________ 65.00 Printing and Set Up Charge for Personalized Covers: $_________________________ TBD Postage and Handling: $_________________________ Date:________________ Total: $_________________________ Company Logo enclosed

Company Logo to be mailed

My check is enclosed

Employee Pocket Safety Manuals are available to UCANE members only. Utility Contractors' Association of New England, Inc. • 300 Congress Street, Suite 101 • Quincy, MA 02169


Michelle L. Norton, AAI, CRIS

Senior Vice President, Account Executive – Construction HUB International New England, LLC

A Slowly Stabilizing Insurance Market for the Water and Sewer Industry Now as we’re into 2026, the insurance market is stabilizing after several years of aggressive rate increases, but that stabilization is not uniform across all contractor classes. Underground utility contractors remain one of the most closely evaluated segments in the construction industry because insurers view this work as severitydriven rather than frequency-driven. In practical terms, that means carriers are less concerned about how often claims occur and more concerned about how large they can become when they do occur.

M

ost well-run contractors with strong loss histories should expect renewals that are relatively flat or modestly improved. However, contractors with recent claims, large infrastructure projects, or significant fleet exposure should still anticipate targeted pricing increases, particularly in Auto Liability, Umbrella Liability, and Environmental coverage lines. Historically, specialty construction trades lag broader market improvements by roughly one to two years, which means water and sewer contractors will not experience pricing relief as quickly as lower-hazard industries. With a softening market though comes increased underwriting capacity, which allows for greater negotiating power for insurance brokers. Underwriters are willing to compete for well-performing contractors, but they remain disciplined and selective. Excavation and trenching operations carry collapse potential, underground utility strikes can trigger multi-party liability claims, and roadway projects expose crews to traffic-related injury risk. Environmental exposures add another layer of severity potential because groundwater contamination or sewage discharge claims can require long remediation timelines and regulatory oversight. These factors combine to create loss volatility, which insurers view as more predictive of future losses than simple claim counts.

MARCH, 2026

Regional Factors Operating in Massachusetts and the broader New England region introduces additional underwriting considerations that insurers explicitly factor into pricing and coverage decisions, like older infrastructure systems, dense urban environments, higher regulatory enforcement, and weather-related soil instability. Workplace safety data shows construction consistently ranks as the highest risk industry sector in the state. Recent state injury reports document tens of thousands of workplace injury and illness continued on page 68

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

67


Insurance continued from page 67 cases annually, with a substantial portion involving lost workdays, which is a key severity indicator for Workers’ Compensation carriers. Data from the U.S. Bureau of Labor Statistics indicates construction nationally accounts for roughly one-fifth of all workplace fatalities despite representing a much smaller share of total employment. Excavation work is particularly scrutinized. According to the Occupational Safety and Health Administration (OSHA), trench collapses are several times more likely to be fatal than other construction incidents, and soil failure can occur in seconds. This statistical reality is one of the primary reasons excavation contractors often see higher Liability and Umbrella premiums than other trades.

Roadway Exposure and Transportation Risk Underground utility contractors frequently perform work in or near active roadways, which introduces one of the most severe loss drivers in construction. National work-zone safety studies show that dozens to more than one hundred worker fatalities occur each year at road construction sites, and most involve vehicles. Transportation incidents are the leading cause of workplace deaths across all in-

dustries, and they represent a disproportionate share of severe claims for utility contractors. For insurers, roadway exposure directly affects three major lines simultaneously: Commercial Auto, Workers’ Compensation, and General Liability. Claims involving vehicles also tend to involve multiple parties, which increases litigation potential and drives up settlement values. As such Commercial Auto pricing will continue to trend in the +5-12%, with greater increases for urban contractors.

Workers’ Compensation Severity Trends Workers’ Compensation pricing for underground contractors is influenced more by claim severity than claim frequency. Construction claims are significantly more expensive on average than claims from most other industries, and utility contractors frequently exceed construction averages because injuries often involve heavy equipment, crush trauma, or confined spaces. Massachusetts data shows thousands of construction Workers’ Compensation claims are filed annually, with average claim costs that can reach tens of thousands of dollars. While MA performs slightly better than national averages on frequency, severe cases involving permanent disability or multiple incontinued on page 69

Build on what matters most. HUB’s dedicated insurance and risk management specialists will work to help you build on your success and protect what matters most.

o o o o

Business insurance and Risk Services Employee Benefits Personal insurance Retirement and Private Wealth Management

HUB International New England Michele L. Norton, AAI, CRIS (978) 761-5488 michele.norton@hubinternational.com

hubinternational.com/construction

Risk & Insurance | Employee Benefits | Retirement & Private Wealth

68

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Insurance continued from page 68 juries can exceed six-figure values. Insurers price policies with this severity potential in mind, which is why experience modification factors and loss history remain among the strongest predictors of premium levels. MA Workers’ Compensation rates continue to rank below the national average, with several consecutive years of rate reduction, while other New England states like CT and RI rank in the top 10 highest for countrywide index rates. Despite pushback in recent years, expect this to be the trend for the foreseeable future.

Liability Claim Severity and Litigation Trends Across the United States, liability verdict values have increased dramatically over the past decade. Large jury awards, sometimes referred to as nuclear verdicts, have risen several hundred percent in frequency, and median construction-related verdict values have doubled in many jurisdictions. For underground contractors, who have seen a boom in federal and state infrastructure spending, the most severe claims typically arise from gas line strikes, structural damage to adjacent property, roadway accidents, or flooding incidents tied to excavation work. Umbrella and Excess Liability insurers are particularly sensi-

tive to these trends because their coverage applies once primary policy limits are exhausted. Global reinsurers set the ceiling for capacity and pricing and are the primary influence on this segment of the market. Even contractors with clean loss histories should expect to see Excess pricing increases of +10-20% simply because of industry-wide severity trends.

Equipment and Property Exposure Heavy equipment losses represent another area of concern for insurers. Replacement values for excavation equipment, vacuum trucks, and drilling machinery commonly range from hundreds of thousands of dollars to well over three-quarters of a million dollars per unit. When losses occur due to theft, fire, overturn, or weather damage, they are rarely small. Increasing equipment values combined with rising repair costs have led many insurers to adjust deductibles or require tighter losscontrol measures.

Environmental Liability Considerations Environmental exposure is one of the defining characteristics of water and sewer contractor risk. New England represents one of the most infrastructure-focused regions in the United States. Federal continued on page 70

Asphalt Paving • Excavating • Site Development Hot Mix Asphalt Lawrence-Lynch Corp.

White Bros. – Lynch Corp.

P.O. Box 913 • Falmouth, MA 02541

P.O. Box 155 • Oak Bluffs, MA 02557

396 Gifford Street • Falmouth, MA 02540

20 Vineyard Ave. • Oak Bluffs, MA 02557

PH 508-548-1800 • FX 508-457-1825

PH 508-693-0845 • FX 509-693-0312

Visit our website @ www.lawrencelynch.com

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

69


Insurance continued from page 69 and state funding initiatives continue to direct billions toward drinking water, wastewater, and stormwater upgrades, particularly projects addressing PFAS contamination, climate resiliency, and aging municipal systems. Massachusetts alone has delivered $9.6B in water infrastructure financing, with prioritization for projects that combine environmental compliance with system modernization. Claims involving contamination or discharge events often cost several times more than standard liability claims because cleanup costs, testing requirements, and regulatory involvement extend claim duration and increase total loss amounts. Insurers therefore maintain firm pricing and stricter underwriting standards for Pollution coverage compared with most other lines and, with the characteristics unique to New England, pricing is stable, flat to +7% but, on the upper half of the national average.

An Overall Outlook From a practical standpoint, most contractors should expect General Liability pricing to remain stable or improve slightly if their loss experience is favorable. Umbrella and Excess Liability pricing will likely con-

70

tinue to increase modestly due to ongoing severity concerns. Commercial Auto will remain the most challenging line because loss ratios across the industry continue to exceed profitability thresholds. Workers’ Compensation in Massachusetts is currently stable due to regulatory rate conditions, though long-term upward pressure may emerge if claim severity trends continue. Equipment and environmental coverage are expected to remain firm because of largeloss volatility. Among these factors, prior severity losses and auto claims carry the greatest weight in pricing decisions. In the short term, the insurance market for underground contractors should remain stable with selective increases. Over the next several years, casualty lines may tighten again if litigation severity continues rising. Long term, there’s reason for optimism. The contractors best positioned for favorable insurance outcomes will be those who continue to invest in their people and measurable risk controls, maintain disciplined documentation, and actively manage their loss profiles. n

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


2026 Scholarship Applications Available Now UCANE to Award Twelve $3,000 Scholarships WHO IS ELIGIBLE TO APPLY? •

Any child or grandchild of a UCANE member OR an employee of a member in good standing.

•

The applicant should be a high school senior who will be enrolling full time in an accredited two- or four-year academic institution for the year beginning in September 2026 OR a current full-time college student who has not previously received a UCANE scholarship.

•

In the event the applicant receives a full scholarship from the college of his/her choice, or from any organization, civic group, etc., the UCANE Scholarship will be awarded to another applicant. Applicant’s parent/grandparent must work for a company in the New England Region.

HOW WILL THE APPLICATION BE JUDGED? Twelve scholarships will be awarded. Two of the scholarships will be awarded to applicants pursuing a construction related degree. There will be a question on the application to indicate if you believe you are eligible for these scholarships. The other scholarships are open to all other courses of study. Applications are judged and winners are selected by independent outside educators. Selection will be based on the overall worthiness of the applicant by considering: 1. Scholastic achievement; 2. Interest and effort in preparing for your vocation; 3. Extra-curricular activities at and away from school, including community and religious service; 4. Difficulty of course curriculum and career objectives; 5. Personal recommendations; 6. Thoroughness of the completed application, particularly the essay

WHAT MUST ACCOMPANY THE APPLICATION? 1. 2. 3.

A transcript of high school or college grades through the latest period prior to April 12, 2026. A letter of recommendation from the principal or faculty advisor/academic advisor. A letter of recommendation from a community member familiar with the applicant’s ability and character.

DEADLINE: Applications and letters of recommendation must be received by UCANE via email at bward@ucane.com no later than 11:59 PM on Sunday, April 12, 2026. If you have any questions regarding the completion of the application, please contact Brandon Ward at bward@ucane.com or (508) 314-2449. Utility Contractors’ Association of New England, Inc. 300 Congress Street • Suite 101 • Quincy, MA 02169 Tel: 617.471.9955

MARCH, 2026

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

71


Advertisers’ Index 21st Century Concrete, Inc.................................................................... 72 Acrisure..................................................................................................... 17 ATS Equipment, Inc. .............................................................................. 28 Badger Daylighting................................................................................... 8 The Baldwin Group................................................................................. 51 Benevento Companies............................................................................ 37 Blue Collar Customs............................................................................... 44 Boro Sand & Stone Corp.......................................................................... 7 Dennis K. Burke, Inc............................................................................... 40 Concrete Systems, Inc....................................................Inside Back Cvr. Core & Main............................................................................................... 2 Cumberland Quarry Corp..................................................................... 35 Dagle Electrical Construction Corp...................................................... 4 Darmody, Merlino & Co., LLP.............................................................. 41 Dedham Recycled Gravel....................................................................... 50 Dig Safe System, Inc................................................................................ 11 The Driscoll Agency................................................................................ 25 Eastpoint Lasers, LLC............................................................................. 51 T. L. Edwards, Inc.................................................................................... 29 Genalco, Inc.............................................................................................. 64 Granite City Electric............................................................................... 14 L. Guerini Group, Inc............................................................................. 19 Henniker Directional Drilling, LLC.................................................... 13 Hinckley Allen LLP................................................................................. 10 John Hoadley & Sons, Inc...................................................................... 53 HUB International New England......................................................... 68 JESCO........................................................................................................ 26 P. J. Keating Company............................................................................ 32 P. A. Landers, Inc..................................................................................... 42 Lawrence-Lynch Corp............................................................................ 69 Lorusso Corp............................................................................................ 22 Lorusso Heavy Equipment, LLC........................................................... 58 McGovern Ford of Framingham.......................................................... 46 Mersino Dewatering............................................................................... 54 Midwest Mole............................................................................................. 7 Milton CAT..............................................................................Back Cover Milton Rents............................................................................................. 57 Monroe Tractor........................................................................................ 33 National Trench Safety........................................................................... 30 Norfolk Power Equipment, Inc............................................................. 62 North American Crane & Rigging LLC.............................................. 38 North East Shoring Equipment, LLC................................................... 52 Northwestern Mutual............................................................................. 65 Ocean State Oil........................................................................................ 70 Pacella Recycled Gravel.......................................................................... 49 Pawtucket Hot Mix Asphalt.................................................................. 64 Podgurski Corp........................................................................................ 12 E. J. Prescott, Inc................................................................ Ins. Front Cvr. Rain For Rent-New England.................................................................. 48 Read Custom Soils................................................................................... 13 Scituate Concrete Products Corp......................................................... 16 Scrap It, Inc............................................................................................... 56 Shea Concrete Products, Inc. ................................................................ 24 SITECH New England.............................................................................. 6 Starkweather & Shepley Ins. Brokerage, Inc....................................... 36 Sunbelt Rentals........................................................................................ 26 Taylor Oil Northeast............................................................................... 45 Tonry Insurance Group, Inc.................................................................. 40 Trimble........................................................................................................ 9 United Concrete Products..................................................................... 31 Vortex Services......................................................................................... 18 F. W. Webb................................................................................................ 60 Webster Printing..................................................................................... 62 C. N. Wood Co., Inc. .............................................................................. 20 World Insurance Associates LLC......................................................... 62 Tim Zanelli Excavating.......................................................................... 15

72

“BUY FROM THE ADVERTISERS IN CONSTRUCTION OUTLOOK”

MARCH, 2026


Concrete Systems, Inc.: Manholes & Catch Basins, Box Culverts, Utility Structures, Special Box Structures, Containment Vaults, Fire Cisterns, CSI Arc-Span™ Bridges, Rigid Bridge ™ Systems, Bridge Deck Slabs, Permanent & Temporary Median Barrier, Uwall™ Retaining Wall Systems, Stablewall™ Retaining Wall, Headwalls & Wingwalls. Clampcrete Construction Systems: TL-4 Anchored Barrier for Roadway Structures. Tunnel Systems: Precision Segmental Tunnel Lining Rings. Cleco Manufacturing: Precision Fabricated Forms & Forming Systems, Complete Plant Design, Batch Plant Computer Automation, Countercurrent Mixers & Concrete Delivery Systems.


CAT’S NEXT-GEN COMPACT TRACK LOADERS

READY TO RAISE THE BAR? (AMONG OTHER THINGS) THE COMPLETE PACKAGE OF POWER, PERFORMANCE & COMFORT. This is the CTL you’ve been waiting for. With more torque, giving you the power you need to get things done. Completely re-imagined, it delivers enhanced grading, ride and stability. And its new cab layout simply redefines operator comfort. See it. And believe it.

0%

FINANCING AVAILABLE *

INCLUDES A 2-YEAR/2,000 HR. STANDARD WARRANTY.

SEE FOR YOURSELF. CALL YOUR REP OR VISIT YOUR NEAREST LOCATION TODAY. MILFORD

BREWER

NORTH READING

RICHMOND

WAREHAM

LONDONDERRY

STOUGHTON

CRANSTON

100 Quarry Drive | (508) 634-3400 84 Concord Street | (978) 276-2400 14 Kendrick Road | (508) 291-1200 207 Page Street | (781) 399-8580

79 Robertson Boulevard | (207) 991-3100 150 Cat Lane | (802) 434-7800

www.miltoncat.com

30 Industrial Drive | (603) 665-4500 2158 Plainfield Pike | (401) 946-6350

SCARBOROUGH

16 Pleasant Hill Road | (207) 885-8000 *CAT® machines sold by participating CAT dealers to customers in the USA or Canada. Purchase and delivery must occur during offer period. Offer subject to machine availability and credit approval by CAT Financial. Not all customers will qualify. Payments do not include taxes, freight, set-up, delivery, document fees, inspections, additional options, or attachments. Offer may change without prior notice and cannot be combined with any other offers. Additional terms and conditions may apply. Contact your CAT dealer for details.


Turn static files into dynamic content formats.

Create a flipbook
Construction Outlook March 2026 by UCANE - Issuu