Lead and Copper Rule Improvements

Page 1


Lead and Copper Rule Improvements

Town of Bowling Green, VA

June 4, 2026

Town

About TruePani

 Engineering, communications, and data management firm specialized in lead in drinking water

 Headquartered in Knoxville, TN, with staff nationwide

 Lead and copper assistance to over across 18 states including over 800 waterworks in Virginia

Lead and Copper

Technical Assistance

• TruePani is providing technical assistance to small community and non-transient waterworks serving 10,000 people or fewer

• Assistance available for all aspects of the LCRI with an emphasis on the baseline inventory and unknown identification strategies

What is a service line?

 Inventory must include the systemand customer-owned portions of all service lines in the system’s distribution system.

 ”Public side”

 “Private side”

 Materials include

 Non lead like copper or plastic

 Lead

 Galvanized Requiring Replacement

 Unknown

Federal Reserve Bank of Chicago. Getting the Lead Out: New Opportunities and Challenges to Scale Up Lead Service Line Replacement. February 2022

Lead and Copper Rule Improvement: Major Requirements

 Initial compliance date of November 1, 2027

 Baseline inventory submission

 A list of all schools and licensed child care facilities

 Service Line Replacement Plan, if required

 Begin mandatory lead and GRR service line replacement

 Fully known inventory and removal of all lead and GRR service lines under the control of the waterworks by November 1, 2037

 Validation of non-lead determinations by December 31, 2034

Town of Bowling Green Council Meeting | TruePani Inc.

WSSC Water, Galvanized Water Service Lines

Customer Notification Requirements

 Annual notification to all lead, GRR, and unknown customers by December 31

 Notification deadline changes after start of LCRI

 LCRI requires notification to customer and all served

 Certify the distribution of notifications by July 1 in the following year by either:

 Notify residents upon new service initiations at addresses served by lead, GRR, and unknown within 1 business day

 Starting after November 2027, customers must be offered lead testing

Town of Bowling Green Council Meeting | TruePani Inc.

Deadline Requirements

▪ Certify the distribution of 2025 service line material customer notifications by July 1

In 2026

November 1, 2027

(LCRI Takes Effect)

▪ 24-hour, Tier 1 notification for lead ALE

▪ Update language in the CCR

▪ Annual notification by end of year

▪ Baseline Inventory

▪ Service Line Replacement Plan, if required

▪ List of all schools and child care facilities

▪ Lead action level reduced from 0.015 mg/l to 0.010 mg/l

▪ Begin replacing lead and GRR service lines

▪ Standard tap monitoring begins for systems with GRR or lead

▪ Updated compliance sampling plan

January 1, 2028

▪ Tap sampling protocol provided to customers

▪ List of water quality parameter sites, if required

January 30, 2035 ▪ Validation pool results

November 1, 2037

▪ Fully known inventory

▪ Removal of all lead and GRR service lines under system control

Town of Bowling Green Inventory Status

 Currently compliant, but inventory has GRR and unknowns

 Fully known on system side, Unknown and GRR are due to customer materials

 VDH developed GRR reclassification guidance

 530 unknowns can be IDed through approved statistical methods

 TruePani completed statistical proposal which was approved by VDH in February 2026

 Required a minimum of 107 customer service line investigations from randomly generated list

 Hand digging, meter box inspections, customer surveys, crawl space or basement inspections, etc.

Town of Bowling Green Council Meeting | TruePani Inc.

Advantages of a Fully Known Inventory

 Reduce or eliminate annual notification

 Required by end of year to all customers served by lead, GRR or unknown line

 Certified the following July 1

 If fully non-lead, no mandatory replacement or service line replacement plan

 Replacement must be complete by 2037

 Replacement is independent of ownership and based on control

 VDH is expecting all water systems with GRR and/or Lead to replace these lines

 If fully non-lead, no return to standard monitoring

 Currently collecting 10 samples every 3 years

 Standard monitoring is 20 samples every 6 months with complicated sampling procedure for those served by lead lines

 If fully non-lead, reduction or elimination of extra lead mitigation requirements like pitcher filters and additional communication

Questions?

Guidance Documents

 EPA Lead and Copper Rule Improvements

 Inventory and Replacement Fact Sheet (PDF)

 Validation Pool Fact Sheet (PDF)

 Other EPA LCRI Fact Sheets

 VDH Lead and Copper Rule Guidance

 Preparing for the Lead and Copper Rule Improvements Guidance Document (PDF)

 VDH ODW GEC SWIFT Portal Instructions (PDF)

 VDH Protocol to address GRR Lines (PDF)

 GEC SWIFT Portal

 VDH School and Child Care Sampling Projects