Town of Bowling Green, Virginia
Bowling Green, Virginia
Corrective Action Plan Requirements
Work Completed in 2026 to-date
Next Steps
![]()


Town of Bowling Green, Virginia
Bowling Green, Virginia
Corrective Action Plan Requirements
Work Completed in 2026 to-date
Next Steps
Bowling Green, Virginia ongoing

Accepted by VDH 5/22/26 without comment completed
Work underway
Bowling Green, Virginia
• Well site selection
• Treatment technology
• Treatment building location(s)
• Costs
Conclusions:
• Second new well on Lacey lane
• Ion-exchange treatment – should be effective and lower-cost option, with additional evaluation
• Central treatment location reduces cost, simplified system
• Est. construction cost in line with original preliminary estimate

Bowling Green, Virginia

Bowling Green, Virginia

Bowling Green, Virginia
• Technical specifications component of bid package finalized in Feb-March 2026

• Town to include with contract documents for driller procurement
• Will follow completion of Environmental Assessment
Bowling Green, Virginia
Funding Decisions – Timing Uncertain
• HB1600 funding awarded Dec 2025; reappropriation underway with GA this session - $6,206,205 as grant
• BIL-010S-26- VDWSRF - $2,068,750 as principal forgiveness
• VDH to provide a single consolidated sub-recipient agreement
Environmental Assessment – schedule in discussion w/ VDH
• Condition of federal funds
• Involves review of environmental and cultural impacts
Well Drilling & Construction – Q1 2027 (pending EA decisions)
• 2 planned locations – Well 4 lot and Town-owned lot on Lacey Lane
• Town to prepare contract documents for driller procurement
Final Engineering/Design for Construction Permit –
30% Q3-4 2026, 60%-final Q1-Q2 2027
• Builds on PER
• Next – 30%-60%-90%-final design phases
• Construction permit deadline July 31, 2027