Paris Downtown Dig Project Timeline Unveiled: Transforming the Heart of Paris, Ontario

Next Article
ASTROLOGY

ASTROLOGY

In a bid to rejuvenate the historic core of Paris, Ontario, a comprehensive schedule of events has been proposed for the ambitious Downtown Dig Project. The initiative aims to revitalize key areas, enhancing both infrastructure and aesthetics for residents and visitors alike.

The roadmap for this transformative endeavor is as follows:

Advertisement

October 2024: Following a stringent selection process, PreQualified Contractors are identified, setting the stage for the forthcoming phases of the project.

November 2024: A pivotal moment arrives with the release of the Tender for the Downtown Dig Project to the Pre-Qualified

Bidders, signaling the progression towards tangible development.

January 2025: The anticipation mounts as the Council prepares to Award the Tender, a decision that will shape the course of the project.

March/April 2025: The landscape transforms as the Construction Project takes flight, commencing from the Nith River Bridge to the William Street Intersection, laying the foundation for future endeavors.

October 2025: A milestone moment emerges with the Reopening of Grand River Street North, symbolizing progress and a renewed sense of vibrancy in the heart of Paris.

March-May 2026: The project reaches a crescendo with the Completion of Outstanding Items and the Area North of William Street Intersection, setting the stage for further enhancements.

2026: The focus shifts towards Mechanic Street from Grand River Street North to West River Street, encompassing full underground replacement and street scaping, promising a seamless blend of functionality and aesthetics.

2027: Grand River Street South undergoes a metamorphosis from the Nith River Bridge to Dumfries Street, featuring full underground replacement and the introduction of a roundabout, heralding a new era of connectivity and accessibility.

Continued on page 9

CLICK ON THE PHOTO TO THE LEFT TO WATCH A VIDEO ON THE DOWNTOWN DIG ANNOUNCEMENT

Construction on downtown is set to begin in March/April 2025 – starting from the Nith River bridge to the William Street Intersection.