Week of October 27thProgress Report
Week of October 27thProgress
Beach House Cottage Retreat
Beach House Cottage Retreat
Our resort-style community is coming to life with exciting upgrades already in motion Stay tuned, Beach House Cottage Retreat is transforming fast!
Current Progress Progress
Park Models: Park Models:
7 Units delivered, 4 set 7 Units delivered, 4
Stairs and Railings start 10/29 and Railings start 10/29
Units for lots 104, 105 Deliver 11/7 Lot prep in progress
Units lots 104, 105 Deliver 11/7 Lot prep in progress
Duke Energy Finally complete with switching power to all new Pedestals
Duke Energy complete with switching power to all new Pedestals
EW Removing Old Peds Removing Old Peds
Paving scheduled for 11/24
Paving scheduled for 11/24
Wilson to confirm Direction Drill date - Critical Wilson to confirm Direction Drill date - Critical
Site Work: Site Work: Sanitary Sewer TV Complete and approved by City of Largo Sewer TV Complete and approved by City of Largo
Forming Concrete Parking/Drive. Concrete scheduled for Thursday Concrete Parking/Drive. scheduled for Thursday
Clubhouse: Clubhouse:
Drywall Finishing in Progress
Drywall Finishing in Progress
Hardi Siding In Progress Siding In Progress
Electrical Exterior R/in in Progress
Electrical Exterior R/in in
Exterior Eq Pads Formed Concrete Thursday Exterior Formed Concrete Thursday
Axis One to Confirm all Elec Panel Gear on site or Available for Delivery
Axis One to Confirm all Elec Panel Gear on site Available for Delivery
Axis One to Confirm of Concealed Arm System for all wall hung sinks
Axis One to Confirm of Concealed Arm System all wall hung sinks
Final Exterior and Interior Paint Colors selected and approved
Final Exterior and Interior Paint Colors and approved