Week of July 28th Progress Report – Beach House Cottage Retreat
Week of July 28th Progress Report – Beach House Retreat
Our resort-style community is coming to life with exciting upgrades already in motion Stay tuned, Beach House Cottage Retreat is transforming fast!
Current Progress Progress
Site Work: Site Work:
Fire Main Response to Comments submitted to City and Under Review
Fire Main Response to Comments submitted to City and Under Review
ROW Permit Secured Wilson to schedule Directional Drill
ROW Permit Secured Wilson to schedule Directional Drill
RCP Installed at Driveway MES and pads to be installed starting 7/30
RCP at Driveway MES and pads to be installed starting 7/30
Site Meetings Start 8/5 Site Meetings Start
Club House: Club House:
Masonry Walls Complete, Inspection Passed Walls Complete, Inspection Passed
Cell Fill Scheduled for Friday 8/1
Cell Fill Scheduled for Friday 8/1
Trusses on Site 8/5, Install starting 8/6
Trusses Site 8/5, Install starting 8/6
Dry In and Interior walls to Follow In and Interior walls to Follow
Pool Tentatively Scheduled to Start 8/18
Pool Tentatively Scheduled to Start 8/18