LIVESTRONG Sporting Park Construction Update - May 4th, 2011

Page 1

From:

Nick Roberts

Office: Kansas City Date:

5.4.11

Re:

Sporting Kansas City Project Update – Week of 5.4.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Seating installation is nearly complete. Figureas seat installation is ongoing. Concrete stair pouring and forming is ongoing. Grading of north side is complete. Concrete Flatwork: Plaza flatwork is ongoing. Supporter’s Club concrete staining is ongoing. North drop off lane will be poured. Masonry: Plaza wall block is ongoing. Plaza fence installation is ongoing. Stone: Cast stone installation is ongoing. Stone at VIP entrance is nearly complete.

Tree installation at Plaza.

Steel: Concourse handrail is nearly complete. Concourse handrail is ongoing. Gate frame installation at Portal’s is ongoing. Terrace bar steel installation is complete. Plaza portal steel to begin this week. Roofing and Sheet metal: Victory Suite metal panels are complete. Metal panels on north mezz soffit are nearly complete. Concession metal panel installation is nearly complete. Installation of perforated panels is ongoing.

Building the Future

Café rail at Plaza.