LIVESTRONG Sporting Park Construction Update

Page 1

From:

Nick Roberts

Office: Kansas City Date:

5.25.11

Re:

Sporting Kansas City Project Update – Week of 5.25.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Figureas seat installation is nearly complete. All landscaping is nearly complete. Ticket Booth has been set. Concrete Flatwork: Plaza flatwork will be complete. Plaza colored concrete is complete. Masonry: Plaza wall block is ongoing. Plaza fence installation is ongoing. Stone: Cast stone installation is ongoing. Steel: Stair handrail is ongoing. NW equipment pad screen wall steel is ongoing.

Ticket Booth has been set.

Roofing and Sheet metal: Installation of perforated panels is complete. Plaza Portal panels are ongoing. Polycarbonate: VIP canopy polycarb is ongoing. Metal Stud Framing/Drywall/Ceilings: All project drywall will be complete. Glass/Doors/Hardware: Mechoshade installation is complete. Plaza directory signage. Building the Future


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
LIVESTRONG Sporting Park Construction Update by Sporting Kansas City - Issuu