LIVESTRONG Sporting Park Construction Update - May 18, 2011

Page 1

From:

Nick Roberts

Office: Kansas City Date:

5.18.11

Re:

Sporting Kansas City Project Update – Week of 5.18.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Figureas seat installation is ongoing. Drop off lane has been paved. Goal post installation is ongoing. Plaza landscaping is ongoing. Concrete Flatwork: Plaza flatwork is ongoing. Plaza colored concrete is complete. Masonry: Plaza wall block is ongoing. Plaza fence installation is ongoing. Stone: Cast stone installation is ongoing.

Colored concrete in Plaza.

Steel: Stair handrail is ongoing. Plaza portal steel is complete. Roofing and Sheet metal: Metal panels on north mezz soffit are nearly complete. Installation of perforated panels is nearly complete. VIP Canopy panels will be complete. Plaza Portal panels will begin. Accelerator gate panels are ongoing.

Polycarbonate: North polycarbonate is ongoing. Ceiling covering in Victory Suite. Building the Future