From:
Nick Roberts
Office: Kansas City Date:
5.11.11
Re:
Sporting Kansas City Project Update – Week of 5.11.2011
To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner
Current Activities this Week: Site/Playing field/Bowl: Figureas seat installation is ongoing. France Family Drive has been paved. Drop off lane will be paved. Concrete Flatwork: Plaza flatwork is ongoing. Supporter’s Club concrete staining is complete. Plaza colored concrete will begin. Masonry: Plaza wall block is ongoing. Plaza fence installation is ongoing. Stone: Cast stone installation is ongoing. Stone at VIP entrance is complete.
Plaza transformer has been set.
Steel: Stair handrail is ongoing. North Portal steel frame is complete. Terrace bar steel installation is complete. Plaza portal steel to begin this week. Roofing and Sheet metal: Metal panels on north mezz soffit are nearly complete. Concession metal panel installation is nearly complete. Installation of perforated panels is ongoing. VIP Canopy panels will begin. Plaza Portal panels will begin. Accelerator gate panels are ongoing.
Building the Future
Stained concrete in Supporter’s Club.