LIVESTRONG Sporting Park Construction Update

Page 1

From:

Nick Roberts

Office: Kansas City Date:

4.6.11

Re:

Sporting Kansas City Project Update – Week of 4.6.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Grading on plaza is onging. Seating installation is ongoing. Concrete retaining walls installation is ongoing. Concrete stair pouring and forming is ongoing. Concrete Flatwork: East side walk pours are ongoing. Slab at bottom of Stair 1 will be complete. South concrete walk will be complete. Masonry: Block installation at NW transformer area to be ongoing. Sealing and final wash of block is nearly complete. Finishing concourse exterior walls is ongoing. Stone: NW elevation stone is complete. Stone on field face of Stadium Suite is ongoing. Cast stone installation is ongoing.

Pouring of cast-in-place Plaza stairs.

Steel: Bowl handrail is ongoing. Roofing and Sheet metal: Gutter shrouds at canopy gutter are complete. Canopy deck flashing installation is ongoing. Coping cap installation at concourse is nearly complete. Metal panels on East elevation are ongoing. Metal panels on north mezz interior soffit are ongoing. Concession metal panel installation is ongoing. Fin installation continuing on South elev. Building the Future


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
LIVESTRONG Sporting Park Construction Update by Sporting Kansas City - Issuu