LIVESTRONG Sporting Park Construction Update 4/27/11

Page 1

From:

Nick Roberts

Office: Kansas City Date:

4.27.11

Re:

Sporting Kansas City Project Update – Week of 4.27.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Seating installation is ongoing. Concrete retaining walls installation is ongoing. Concrete stair pouring and forming is ongoing. Grading of north side is nearly complete. Concrete Flatwork: East side walk pours are complete. Plaza flatwork is ongoing. VIP Entrance slab was poured. Supporter’s Club concrete staining is ongoing. Masonry: Plaza wall block is ongoing. Stone: Stone on field face of Victory Suite is complete. Cast stone installation is ongoing.

Plaza flatwork at North Breezeway.

Steel: Bowl handrail is ongoing. Concourse handrail is ongoing. Gate frame installation at Portal’s is ongoing. Terrace bar steel installation is nearly complete. Roofing and Sheet metal: Victory Suite metal panels are ongoing. Metal panels on East elevation at louver is ongoing. Metal panels on north mezz interior soffit are ongoing. Concession metal panel installation is ongoing. Installation of perforated panels are ongoing. Installation of Concourse handrails. Building the Future


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
LIVESTRONG Sporting Park Construction Update 4/27/11 by Sporting Kansas City - Issuu