LIVESTRONG Sporting Park Construction Update - 4/20/11

Page 1

From:

Nick Roberts

Office: Kansas City Date:

4.13.11

Re:

Sporting Kansas City Project Update – Week of 4.13.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Grading at Plaza is complete. Seating installation is ongoing. Concrete retaining walls installation is ongoing. Concrete stair pouring and forming is ongoing. Grading of north side is ongoing. South mow strip installation is complete Concrete Flatwork: East side walk pours are complete. Plaza flatwork is ongoing. VIP Entrance slab will be poured. Masonry: Finishing concourse exterior walls is complete. Plaza wall block is ongoing. Stone: NW elevation stone is complete. Stone on field face of Victory Suite will be complete. Cast stone installation is ongoing.

Pouring of Plaza flatwork.

Steel: Bowl handrail is ongoing. Gate frame installation at Portal’s is ongoing. Overhead door at south breezeway is complete. Terrace bar steel installation is ongoing. Roofing and Sheet metal: Canopy deck flashing installation is ongoing. Metal panels on East elevation at louver is ongoing. Metal panels on north mezz interior soffit are ongoing. Overhead rolling grilles at south breezeway. Building the Future


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.