LIVESTRONG Sporting Park Construction Memo

Page 1

From:

Nick Roberts

Office: Kansas City Date:

4.13.11

Re:

Sporting Kansas City Project Update – Week of 4.13.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Grading at Plaza is onging. Seating installation is ongoing. Concrete retaining walls installation is ongoing. Concrete stair pouring and forming is ongoing. Concrete Flatwork: East side walk pours are nearly complete. South concrete walk is complete. Plaza flatwork near south breezeway is ongoing. Masonry: Finishing concourse exterior walls is ongoing. Plaza wall block is ongoing. Stone: NW elevation stone is complete. Stone on field face of Victory Suite is nearly complete. Cast stone installation is ongoing.

Pouring of flatwork at the South breezeway.

Steel: Bowl handrail is ongoing. Gate frame installation at Portal’s is ongoing. Roofing and Sheet metal: Canopy deck flashing installation is ongoing. Final roof penetration seals will be complete. Metal panels on East elevation will be complete. Metal panels on north mezz interior soffit are ongoing. Concession metal panel installation is ongoing.

Overhead doors at Supporter’s Club. Building the Future