From:
Nick Roberts
Office: Kansas City Date:
3.30.11
Re:
Sporting Kansas City Project Update – Week of 3.30.2011
To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner
Current Activities this Week: Site/Playing field/Bowl: Grading on plaza is onging. Installation of field sod will be complete. Forming of east side and plaza concrete stairs is ongoing. Seating installation is ongoing. Concrete retaining wall installation is ongoing. Concrete Flatwork: East side walks will begin. Area 1- SOG work at SW toilet entry to be completed. SE vomitory road was poured to completion. Masonry: Block installation at NW transformer area to be ongoing. Block at Terrace bar is being washed. Sealing and final wash of block on the East side to be ongoing. Finishing concourse exterior walls will be ongoing.
Sod installation and irrigation.
Stone: NW elevation stone is complete. Stone outside Owner’s Suite is ongoing. Cast stone installation is ongoing. Steel: Wind columns are complete. NE entry gate steel installation is complete. SW breezeway gate steel is complete.
Building the Future
Stone installation outside owner’s suite.