LIVESTRONG Sporting Park Construction Update 3/16/2011

Page 1

From:

Nick Roberts

Office: Kansas City Date:

3.16.11

Re:

Sporting Kansas City Project Update – Week of 3.16.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner

Current Activities this Week: Site/Playing field/Bowl: Grading on East side of site is ongoing. Installation of underground drainage at plaza is ongoing. Underground drainage is ongoing on south side of field. Root zone is installed on north half of field. Seating support install is ongoing. Concrete Flatwork: Area 1-Suite and Press level tub intermediate stairs are near complete. Area 3-Topping slab at cauldron club is complete and protected. Area 1- SOG work at SW toilet entry to be completed. Masonry: Block installation at NW transformer area to be ongoing. Block installation at Terrace Bar is nearly topped out. Sealing and final wash of block on the East side to be ongoing. Washing and sealing F-line will be complete this week. Finishing concourse exterior walls will be ongoing.

Topped out Terrace Bar wall.

Stone: Area 1-Stone installation in area H is ongoing. Steel: Installation of stone support steel at Stadium Suite is complete. Installation of dock overhead doors is complete. Wind columns will be complete. Installation of Area H stone.

Building the Future


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
LIVESTRONG Sporting Park Construction Update 3/16/2011 by Sporting Kansas City - Issuu