3-5 INTERMEDIATE SCHOOL Construction Phase
Project Activities 1. Intermediate School Additions (Construction Phase) 1. 2.
Construction OAC meetings occurring bi-weekly Construction Progress: Area C: AHU set, Exterior walls completed, interior framing and drywall ongoing. MEP rough-in ongoing. Area D foundations and basement concrete ongoing. Plumbing underground rough-in has commenced. Area A exterior wall framing and sheathing completed. Roof dried in. MEP wall and overhead rough-in ongoing. Interior renovations are ongoing throughout building Playground re-paving to occur week of October 20th.
3.
Proposed Change Orders: Additional Bulk Excavation Quantities and pricing are pending verification by the Design Team and PJ Dick.
South Fayette Twp School District School Board Meeting October 28, 2025
7
Complete Dec 2025 Complete Aug 2026
Complete Dec 2025