BUS / MAINTENANCE DEPOT DESIGN DEVELOPMENT

SOUTH-VIEW W CAMPUS S PERSPECTIVE

New w Bus s Depot
Middle e School

Project

1. BUS S / MAINT T DEPOT T (Design Phase)

1.Geotechnical

1.Investigation and borings completed

2.Preliminary findings shared with Structural Engineer for design of retaining walls

3.Final Report expected in June

2.Forthcoming:

CEC Prelim Planning with County DEP office for stormwater and erosion / sedimentation.

Submit for approvals May 29th, 2025 in advance of June 9th Planning Commission

Utility Extension Meetings (gas, water, sewer, elec)

Sewer authority currently reviewing alignment of site sanitary sewer line

PA American: CEC shared site pan and preferred alignment –connections confirmed

Columbia Gas: CEC shared site pan and preferred alignment –connections confirmed

Schedule:

Complete Design Development May 29th, 2025

Planning Commission meetings: June 9th, July 24th, August 13th

Complete Construction Documents August 29th, 2025

Bidding in Fall (October –November) dependent on County/DEP Approval Timeline

Construction Start Early Spring 2026 thru Nov 2028 (18-20 months for building occupancy)

BUS / MAINT. DEPOT LAYOUT PLAN MIDDLE

Snow Removal Station
Future Driveway to Battle Ridge

R PLANS

EXTERIOR R RENDERINGS

South

BUS S / MAINTENANCE E DEPOT T ––

EXTERIOR R RENDERINGS

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
2025_0527 DRAW Bus Update by South Fayette Township School District - Issuu