BUS / MAINTENANCE DEPOT DESIGN DEVELOPMENT
SOUTH-VIEW W CAMPUS S PERSPECTIVE


Project
1. BUS S / MAINT T DEPOT T (Design Phase)
1.Geotechnical
1.Investigation and borings completed
2.Preliminary findings shared with Structural Engineer for design of retaining walls
3.Final Report expected in June
2.Forthcoming:
CEC Prelim Planning with County DEP office for stormwater and erosion / sedimentation.
Submit for approvals May 29th, 2025 in advance of June 9th Planning Commission
Utility Extension Meetings (gas, water, sewer, elec)
Sewer authority currently reviewing alignment of site sanitary sewer line
PA American: CEC shared site pan and preferred alignment –connections confirmed
Columbia Gas: CEC shared site pan and preferred alignment –connections confirmed
Schedule:
Complete Design Development May 29th, 2025
Planning Commission meetings: June 9th, July 24th, August 13th
Complete Construction Documents August 29th, 2025
Bidding in Fall (October –November) dependent on County/DEP Approval Timeline
Construction Start Early Spring 2026 thru Nov 2028 (18-20 months for building occupancy)