ABOUT THE PRINCIPAL ARCHITECTS OF THE FIRM Ideology Believing that every problem has the capacity to inspire unique and creative solutions that motivate growth, the young duo of Badrinath Kaleru and Prerna Kaleru, founded Studio Ardete in the year 2010. Located in Chandigarh, India, the team at Studio Ardete aims to make each project they undertake, a study in logical and comprehensive designing. Their vision is to design spaces that would evolve into art, enriching the lives of people inhabiting them.
Not hesitating to take on even the most challenging of projects, they use modern construction and building methods to come up with designs that are at par with the most accomplished practices in the world. Ardete incorporates new techniques like parametric modelling and customised design elements, unique to each project they take on, striving to use materials available on site to make the projects sustainable. They work closely with the clients to understand their requirements and engage them in the design process, making them an intrinsic part of it.
Working on projects ranging from architecture to interiors, the architects at Ardete are always motivated to transform what is regular and conventional and flirt with the boundaries of art in architecture. Careful deliberation is employed at each step of process for building the project. In the urban and economic scenario today, that dictates most of the construction and architectural practices, Ardete attempts to erase the divide between practicality and innovation. Each project, regardless of the scale is considered complete in itself and attention is given to each and every detail.
Awards
Badrinath Kaleru & Prerna Kaleru, an Alumni of IIT Roorkee , founded Studio Ardete in 2010 as a proponent of “SPACE IS MORE” with the belief that built spaces need to celebrate the Human existence, the Life . Buildings need to connect to its users at an emotional domain. If it happens the physical aspects of space the form, materials and style disappear, The space bonds to its user like another human, its becomes alive.
PROFESSIONAL PRACTICE REPORT STUDIO ARDETE (INDIA) PVT. LTD., CHANDIGARH FEBRUARY 2021- JULY 2021
An Architect is directly responsible for what he or she builds. Direct involvement with the construction and ultimately responsible for the lives of the people. Such a huge responsibility can be dealt with the confidence only when one has the experience to do so. I was fortunate enough to gain such experience in my internship. The main reason being the experience in the profession teaches a lot rather than what we could be studying in academics. I was more inclined towards learning about the execution and implementation of designs on site and how to overcome challenges that come during actual construction. Studio Ardete, the firm where I was interning, provided me with such exposure. The Ideology of the firm: Believing that every problem has the capacity to inspire unique and creative solutions that motivate growth, the young duo off Badrinath Kaleru and Prerna Kaleru, founded Studio Ardete in the year 2010. Located in Chandigarh, India, the team at Studio Ardete aims to make each project they undertake, a study in logical and comprehensive designing. Their vision is to design spaces that would evolve into art, enriching the lives of people inhabiting them. One such ideology enriched ongoing project is a residential high-end luxury 5-Storey Double Duplex situated at E-58, Vasant Vihar, Delhi. Instead of experiencing the in-office culture, situated in Chandigarh, I was physically present at the site office in Delhi throughout the entire internship, working on all the Architectural, Services, Interiors of this Structure. I find this as an advantage since I was able to witness site complications and how designing and construction can ease it. Designing and Implementing Executing it on site are two different things, and working at the site office, helped me experience it. Since the project is built on such an immense scale and systems, including all services, it is taken care of and managed by a PMC Company. In this case, the Management company was held responsible to find the best suitable vendors and contractors for this project, even the Architectural Firm. So the hierarchy goes like this, all the client's demand is taken care by the Management Company, which has their trusted set of Vendors for certain construction related works, which in this case have equal say since the relationship they have with the client. Relationship plays an important role and the quality of the products and services rendered by these vendors and contractors are of high quality and incorporates experienced skill work. The site is being looked after by several contractors for their distinct services, like Window Systems, Interiors, Electrical, HVAC Systems, Plumbing, POP, Light Fixtures, Kitchen, Gas Connection, Lift System, Civil Services. I got the opportunity to interact with all the site supervisors of respective assistance on site.
As per site Measurements, Cross Checking of Work Done, Solutions for site Complication, while interacting with the skilled labor, nourished me to learn a lot from their involvement and expertise. I worked on the Revision of drawings of Electrical Layout, Plumbing, Interiors, Washroom Fixtures, Facade Specifications, Staircase, Selection of Materials, HVAC layout configuration to maximise height in each space. I got on-site techniques for particular Construction work, akin to Cladding, Stonework, Waterproofing, etc. Had experience with the overall design and functionality of all the services, completely coordinated together. I was committed to every system installed in the construction. Likewise, I was revealed to the procedures and discipline developed by the Management Company. They are held accountable for any rework happening on site, or any structural modifications or alterations if tend to occur. A conventional schedule of every work was also maintained, renewed, and rigorously ensued. There were site meetings, with the client individually and with the contractors on weekly basis. Punctuality is equally important. I came across multiple vendors contracting different construction products, ranging from Cladding Material to Marble Selection for Interiors. During the Internship, I had frequent site Checking of the electrical points, plumbing, and washroom fixtures position to be well-defined and also had to be certain if the necessary electrical and Plumbing point is correctly positioned as per the issued drawing. Most of the drawings were initially drafted and issued in the head office in Chandigarh, but my duty was to keep revising them and updating them as per requirement. This gave me insights into the working drawings and details required for construction to happen. The principal Architects of the firm usually traveled every Thursday for a meeting with the client. All the processes for presentation and Material selection were being followed. I even worked on interiors details such as Mosaic Designs, Tile Allocation, Provision of Ply work for Various Fixtures to be installed in the Ceiling. At the end of the Internship, I was looking after the approval by every contractor for the closure of the ceiling, floor wise. I was under the guidance of Mr. Soumen Adhikary, he is an architect and working as a project manager for this site and as a representative of the Architectural Firm. He has succeeded in installing passion inside me by the way he works and how he manages things so efficiently. Except working on the E-58 Site, I worked on other design projects as well including, the Interior Renovation Project of an Apartment, E-2/4 Vasant Vihar, Delhi One, a commercial project with Auditorium, Interior Rack Details for Kanpur Library, 3D Modelling of Siddharth Residence, Structural 3D of Rajendra Nagar. Thus, this internship did allow me to gain insight into fields related to Architecture, Construction, and Management and how design plays a vital role and can become the solution to several site dilemmas. I was wholly committed throughout, curious to know ways of how various systems work collectively and how everything can be established. The office work culture is surely way different than what we learn in Academics, and there is a necessity for every architect to hereby have a practical site knowledge of how to get the design executed as planned.
E-58, VASANT VIHAR My office/ site for my internship was this site, situated in the urban context of South Delhi, Vasant Vihar. This is an ongoing residential project started in 2019. The residential property is spread across 16,000 sq. ft, comprising of Two Duplexes, Terrace and a Basement as well. The structure of the Building is enveloped by concrete facade creating interesting perspectives and source for natural light and ventilation. There are slanting balconies on all four sides hence making fascinating extrusions in the structure. Using of contrast metallic materials which creates an impact of contrast and is alluring to the viewers eyes. The design has been. The design clearly portrays the ideology of the Firm of ‘space is more’ and using facade as an attractive element in each of their Architecture. This building is an high-end luxury project managed by a PMC Company having separate vendors and contractors for electrical, plumbing, HVAC, Wifi, Automation, Light Fixtures, Lift and Interiors.
LOWER DUPLEX | UPPER DUPLEX BASEMENT STILT FLOOR FOR PARKING GROUND FLOOR: LOUNGE AREA | DOUBLE HEIGHT FORMAL LOUNGE | KITCHEN DINING AREA DAY ROOM | WASHROOM POWDER LOO UTILITY FIRST FLOOR: GUEST ROOM | WASHROOM KID’S ROOM | WASHROOM | WC MASTER BEDROOM | WASHROOM | WALKING CLOSET
EXTERIOR VIEW
FACADE
WEEKLY TASK OF CREATING REPORTS AND DOCUMENTATION OF E-58
SITE PHOTOS AND PROCESS
FACADE
6th June July, 26th 2021 10th July,, 2021
E-58, VASANT VIHAR Basement Contractor Electrical
Drawing Selection/ Material
Work Progress Conduit Wiring DB/Panel
Plumbing
Soil/Waste Piping Water Supply Pipe Fixing Fixture Fitting Testing
HVAC
Ducting Piping Indoor Unit Grill Fixing Outdoor Unit Testing
Services
Lighting/ AutomationOrder Pening
Conduit Wiring Curtain Fixing DB Fixing Testing
Audio/ Video
Conduit Wiring AV Rack fixing Testing
Data/ Wifi/ Security
Conduit Wiring DB/Rack Fixing Testing
Ceiling
Hanging Arrangement Light/Fan Framing Partition above framing Gypsum/POP ceiling Trap Door Cutouts Light/Grill Paint
Flooring
Marble Granite Tiles
Door/ Window
DW Base stone External DW&Shutter DW Internal frame Internal Shutter
Wall
POP Paint Framework Stone Fixing Fabric Fixing Wood Fixing Decorative Panel Fixing Mosaic Panel
Furniture
Fixed Furniture Loose Furniture
Fixture fitting
Light Fixtures Decorative Lights Plumbing Fixture
Switch/ Socket Kitchen
Fixing Testing Counter Cabinets Hood Accessories
Lift
Wall Floor
Ceiling
Stilt
Ground
First
Second
Third
Terrace
10% 50% 90% 100%10% 50% 90% 100%10% 50% 90% 100%10% 50% 90% 100%10% 50% 90% 100%10% 50% 90% 100%10% 50% 90% 100%
Front Facade Frame Cladding For CORIAN
Front Facade Frame Cladding For CORIAN
On the East Facade External Wall M S Framing | External Stone Cladding
On the East Facade External Wall M S Framing | External Stone Cladding
LOWER DUPLEX
| LOWER FLOOR
Living Lounge
Lift Lobby
Dining Area
Kitchen
Kitchen
Powder Room
Day Bedroom
Day’s Room Washroom
LOWER DUPLEX
Guest Bedroom
| UPPER FLOOR
Facade Views from Corridor
Kid’s Bedroom
Guest Bedroom Washroom Masterbedroom
Masterbedroom
Washroom
Washroom
UPPER DUPLEX
Kitchen
| LOWER FLOOR
Living Lounge
Dining Area
Day Washroom
Day Washroom
Powder Toilet
Day’s Room
Powder Toilet
UPPER DUPLEX
Guest Bedroom
| UPPER FLOOR
Corridor
Kid’s Bedroom Masterbedroom
Lift Lobby
Terrace Lift Lobby
Masterbedroom
Washroom
Walking Closet
Basement
Terrace
Basement
Facade Cladding Framework for Corian
Ceiling Layout Status
Guest Bedroom | Upper Duplex
Guest Bedroom | Upper Duplex
Day Room | Upper Duplex
Double Height Lounge Area | Upper Duplex
LOWER DUPLEX - ARCHITECTURAL PLANS 62' [18.90]
62' [18.90] 11'-121" [3.39]
3'-6"
C.B C.B
BEAM 8" DN.
M.BEDROOM 21'-412"x18'-0"
1'-834"
SLAB 10" THK.
5'-0" WIDE BALCONY
BEAM 8" DN. 5'-421"
DRESS 421" 4'-9" 412" 1'-6"
76
69
UP
97'-4" [29.66]
117' [35.66]
10'-9"
LIFT/STAIR LOBBY 16'-0"x17'-0" LVL. +19'-3"
SLAB 10" THK.
SLAB 6" THK.
ELEC.(LOW SIDE) 5'-0"x1'-0"
SLAB 10" THK.
LIFT-2 (6P) 5'-0"x5'-0"
LIFT-1 (10P) 6'-3"x6'-0"
BEAM 1'-0" DN.
HVAC SHAFT 3'-3"x 6'-412"
LIFT-1 (10P) 6'-3"x6'-0"
PEDESTAL LAMP
BALCONY
TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% = 5440.50 SQ.FT (505.43 SQ.MT) ACHIEVED COVERED AREA = 4196.45 SQ.FT (389.86 SQ.MT) i.e 57.85%
1'-9"
421" 2'-6"
2'-0"
1'-9"
3'-121"
8'-9" TOILET
15'-0"x6'-0"
4'-6"
PL. DUCT 1'-0"x2'-6"
2'-121"
15'-0"
BEAM 8" DN.
BEDROOM-3 21'-9"x11'-712"
1'-3"
LCD ON POLE
DOUBLE HEIGHT BALCONY BELOW
16'-921" [5.12]
6'-921"
SLAB 6" THK.
FINAL LAYOUT PLAN, GROUND FLOOR
1'-9"
4'-6"
SLAB 10" THK.
C.B
BEAM 8" DN.
DOUBLE HEIGHT CUTOUT IN SLAB 16'-0"x18'-0"
BEAM 8" DN.
BEAM 1'-0" DN.
SETBACK LINE
1'-9" 1'-9"
VESTIBULE 6'-9"x6'-0"
412"
2'-3"
BALCONY
PEDESTAL LAMP
SHOWER
721"
DRESS
1'-3"
3'-0"
BEAM 1'-0" DN.
BEAM 1'-0" DN.
BEAM 1'-0" DN.
67
BEAM 1'-0" DN.
DOUBLE HEIGHT CUTOUT PUJA ROOM BELOW
DOUBLE HEIGHT FORMAL LOUNGE 16'-0"x18'-0"
16'-921" [5.12]
60
BEAM 1'-0" DN.
BEAM 8" DN.
BEAM 1'-0" DN.
CONSOLE
UPTURN BEAM 6" UP.
SLAB 7" THK.
PL. DUCT 1'-6"x1'-6"
DN
PL. DUCT 1'-0"x2'-6"
5'-0" WIDE DOUBLE HEIGHT BALCONY
1'-6"
3'-0"
HVAC SHAFT 3'-3"x 6'-412"
3'-0"
TOILET 10'-3"x7'-0"
SHOWER
BEAM 1'-0" DN.
SLAB 6" THK. SLAB 6" THK.
3'-0" 3"
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
ELEC.(LOW SIDE) 5'-0"x1'-0"
BEAM 8" DN.
4'-0"
97'-4" [29.66]
UP
LIFT/STAIR LOBBY 16'-0"x17'-0" LVL. +9'-3"
LIFT-2 (6P) 5'-0"x5'-0"
SLAB 10" THK.
BENCH
49
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
BEAM 1'-0" DN.
1'-1021"
DOUBLE HEIGHT CUTOUT IN SLAB 16'-0"x32'-112"
3'-0"
90'-221" [27.50]
BEAM 8" DN.
WALL MURAL
BEAM 1'-0" DN.
DN 48
DOUBLE HEIGHT (19'-3") PUJA ROOM 7'-9"x14'-10"
FOYER
C.B
DRESSING WALK-IN CLOSET 7'-9"x6'-9" 8'-3"x6'-9"+ SLAB 10" THK. 5'-9"x7'-412"
DOUBLE HEIGHT TERRACE BELOW
BEAM 1'-0" DN.
56
SLAB 10" THK.
SLAB 10" THK.
PL. DUCT 1'-6"x1'-6"
CONSOLE
KIDS ROOM 16'-412"x12'-712"
LEDGE WALL UPTO CEILING HT.
HALF BATH 16'-412"x7'-0"
42
19
1
UP
2'-0" 3'-8"
SHOWER
DN
8 6
3'-0"
DOUBLE HEIGHT LIVING AREA 16'-0"x32'-112"
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
421" 1'-3"
TOILET 10'-3"x6'-9"
PEDESTAL LAMP
5'-0" WIDE PASSAGE
3'-6"
2'-1"
1'-0" 3'-0"
3'-11"
3'-9"
VESTIBULE 6'-112"x6'-9"
TERRACE
SLAB 6" THK.
ACCESSORIES
DRESS
C.B
DAY ROOM 16'-412"x12'-712"
SLAB 10" THK.
UP
N. "D
UPTURN BEAM 6" UP.
5'-0" WIDE BALCONY
1
BEAM 8" DN.
ACCESSORIES
19
6
6'-921"
C.B
2'-9"
2'-0" 6'-9" 4'-9"
TOILET 9'-1"x13'-7"
3'-10"
19'-8" [6.00]
5' 9"
6'-10"
3'-5"
2'-3"
C.B
11'-8"
C.B
FULL HT. CABINET
INBUILT FRIDGE
47'-421"
BEAM 18" DN.
FULL HT. CABINET
421"
BEAM
SLAB 10" THK.
2'-3"
2'-3"
SLAB 10" THK.
90'-221" [27.50]
DISH WASHER
. 18" DN
WALK-IN CLOSET (HE) 7'-3"x13'-11"
9"
4'-021"
DRESSING 17'-6"x6'-4"
BENCH
117' [35.66]
5'-021"
BEAM 8" DN.
8
10'-3" WIDE DOUBLE HEIGHT TERRACE
2'-0"
2'-0"
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
18
5'-6"
SLAB 10" THK.
SUNKEN
1'-8" 421"
2'-421"
DINING AREA 13'-7"x18'-412 "
SPACE FOR UTENSIL WASHING ON FLOOR
AM BE
4'-8"
C.B
WALK-IN CLOSET (SHE) 10'-0"x17'-7 12"
SERVANT ROOM (3P) 10'-0"x13'-0"
BEAM 8" DN.
11'-7"
C.B 2'-3"
BEAM 18" DN.
BALCONY BELOW
PL. DUCT 2'-0"x2'-0"
NICHE
3'-5"
C.B
2'-3"
C.B
C.B
SLAB 10" THK.
UTILITY 6'-0"x12'-6"
5'-0" WIDE BALCONY
BEAM 8" DN.
EL./HVAC DUCT 10'-0"x1'-712"
11'-3" [3.43]
WALK-IN CLOSET 6'-0"x10'-7"
TOILET 8'-0"x4'-6"
SHOWER W.B 3'-3"X4'-9" 3'-0"X4'-2"
CONSOLE
KITCHEN 12'-0"x21'-10" +7'-9"x8'-3"
SLAB 6" THK.
BEAM 8" DN.
W.C 3'-0"X4'-9"
9'-3"
UPTURN BEAM. 4" UP.
BEAM 8" DN.
K.STORE 6'-0"x6'-712"
BEAM 8" DN.
C.B
WALK-IN CROCKERY 6'-0"x7'-0"
33'-721"
2'
10'-0"
SERVANT ROOM (3P) 10'-0"x13'-0"
BEAM 8" DN.
BEAM 8" DN.
PL. DUCT 2'-0"x2'-0"
MAID ROOM 8'-0"x8'-4"
10' [3.05]
SHOWER W.B 3'-3"X4'-9" 3'-0"X4'-2"
19'-8" [6.00]
W.C 3'-0"X4'-9"
421"
PL. DUCT 3'-0"x0'-712"
5'-0" WIDE BALCONY
EL./HVAC DUCT 10'-0"x1'-712"
11'-121" [3.39]
PL. DUCT 3'-0"x0'-712"
BEAM 8" DN.
10' [3.05]
SLAB 6" THK.
50'-1021" [15.51]
421"
BEAM 8" DN.
50'-1021" [15.51]
BEAM 8" DN.
BALCONY
SLAB 6" THK.
SETBACK LINE
FINAL LAYOUT PLAN, FIRST FLOOR TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% = 5440.50 SQ.FT (505.43 SQ.MT) ACHIEVED COVERED AREA = 4196.45 SQ.FT (389.86 SQ.MT) i.e 57.85%
UPPER DUPLEX - ARCHITECTURAL PLANS 62' [18.90]
62' [18.90] [15.51]
50'-1021" [15.51]
421"
[3.39]
11'-121" [3.39] 3'-0"x0'-712"
TAPERED WALL
2'-9"
ACCESSORIES
DAY ROOM 16'-412"x12'-712"
89
LIFT/STAIR LOBBY 16'-0"x17'-0" LVL. +29'-3"
LIFT-3 (6P) 5'-0"x5'-0"
107
116
109
47'-421"
90'-221" [27.50]
LIFT-1 (10P) 6'-3"x6'-0"
HVAC SHAFT 3'-3"x 6'-412"
LIFT-3 (6P) 5'-0"x5'-0"
PL. DUCT 1'-0"x2'-6"
2'-3"
3'-0" 8'-3"
2'-0"
5'-0"
TOILET 15'-0"x6'-0"
4'-6"
3'-0"
6'-6"
4'-0"Ø LOOSE PUFFY TABLEØ1'-6"
C.B
TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% = 5440.50 SQ.FT (505.43 SQ.MT) ACHIEVED COVERED AREA = 3964.20 SQ.FT (368.28 SQ.MT) i.e 54.65%
DOUBLE HEIGHT BALCONY BELOW
16'-921" [5.12]
6'-921"
5'-0" WIDE DOUBLE HEIGHT BALCONY
C.B
C.B DRESS 421"
PL. DUCT 1'-0"x2'-6"
2'-121"
15'-0" 2'-6"
3'-1"
1'-3"
CB
DOUBLE HEIGHT DRAWING ROOM 20'-0"x18'-0"
LIFT-1 (10P) 6'-3"x6'-0"
SHOWER 2'-0"
412"
VESTIBULE 6'-9"x6'-0"
DOUBLE HEIGHT CUTOUT IN SLAB 20'-0"x18'-0"
FINAL LAYOUT PLAN, SECOND FLOOR
4'-9"
UP
ELEC.(LOW SIDE) 5'-0"x1'-0"
5'
SETBACK LINE
PL. DUCT 1'-6"x1'-6"
LIFT/STAIR LOBBY 16'-0"x17'-0" LVL. +39'-3" DOUBLE HEIGHT CUTOUT IN SLAB 7'-9"x14'-10"
12'-6"
100
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
DOUBLE HEIGHT TERRACE BELOW
ELEC.(LOW SIDE) 5'-0"x1'-0"
HVAC SHAFT 3'-3"x 6'-412"
1'-9"
DN
DRESS
FOYER
3'-0"
3'-0"
TOILET 10'-3"x7'-0"
SHOWER
3'-0"
ELECTRICAL POINT NEEDED ON FLOOR
ELECTRICAL POINT NEEDED ON FLOOR
UP
3"
97'-4" [29.66]
96
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
4'-0"
421" 2'-6"
87
117' [35.66]
DN 80
97'-4" [29.66]
WALL MURAL
47'-421"
90'-221" [27.50]
PL. DUCT 1'-6"x1'-6"
16'-921" [5.12]
117' [35.66]
HALF BATH 16'-412"x7'-0"
BENCH
421"
1'-0"
DOUBLE HEIGHT CUTOUT IN SLAB 16'-0"x32'-112"
DRESSING 7'-9"x6'-9"
3'-121"
5'-0"
WALK-IN CLOSET 8'-3"x6'-9"+ 5'-9"x7'-412"
DOUBLE HEIGHT TERRACE BELOW
CONSOLE
5' C.B
7'-0"
TOILET 10'-3"x6'-9" SHOWER
UP
C.B
3'-6"
KIDS ROOM 16'-412"x12'-712"
1
2'-9"
3'-0" 5'-9"
3'-9"
BENCH
VESTIBULE 6'-112"x6'-9"
19
6
3'-0"
1'-0"
1'-6"
6'-0"
DN
8
1'-121" 1'-6"
UP
5'-0" WIDE BALCONY
19
ACCESSORIES
DRESS
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
5'-0" WIDE BALCONY
DN 1
DOUBLE HEIGHT LIVING AREA 16'-0"x32'-112"
9"
6'-9" 4'-6"
C.B
M.BEDROOM 21'-412"x18'-0"
421"
6
3'-6"
1'-421"
3'-0"
6'-6"
Width - 4'-0" Tread - 1'-0" Riser - 0'-6" 8
6'-6"
2'-6"
3'-0"
2'-9"
FULL HT. CABINET
WALK-IN CLOSET (HE) 7'-3"x13'-11"
WALK-IN CLOSET (SHE) 10'-0"x16'-8 12"
7'-6"
INBUILT FRIDGE
11"
2'-0"
2'-421"
5'-0" WIDE PASSAGE
FULL HT. CABINET
TAPERED WALL
4'-021"
SERVANT ROOM (3P) 10'-0"x13'-0"
DRESSING 17'-6"x6'-4"
1'-6"
SPACE FOR UTENSIL WASHING ON FLOOR
1'-8" 421"
5'-021"
C.B
DINING AREA 21'-412"x12'-1"
6'-10"
C.B
11'-3" [3.43]
WALK-IN CLOSET 6'-0"x10'-7"
CROCKERY CABINET
TOILET 4'-1012"x6'-6"
DISH WASHER
UTILITY 6'-0"x10'-4"
NICHE
2'-9"
PL. DUCT 2'-0"x2'-0" EL./HVAC DUCT 10'-0"x1'-712"
SHOWER W.B 3'-3"X4'-9" 3'-0"X4'-2"
CONSOLE
KITCHEN 12'-0"x19'-9" +7'-9"x8'-3"
9'-3"
5'-0" WIDE BALCONY
C.B
WALK-IN CROCKERY 6'-4"x7'-0"
C.B
K.STORE 6'-0"x7'-0"
C.B
MAID ROOM 8'-0"x8'-4"
SERVANT ROOM (3P) 10'-0"x13'-0"
C.B
EL./HVAC DUCT 10'-0"x1'-712"
C.B
PL. DUCT 2'-0"x2'-0"
33'-721"
2'
3'-5"
SHOWER W.B 3'-3"X4'-9" 3'-0"X4'-2"
W.C 3'-0"X4'-9"
C.B
5'-0" WIDE BALCONY
10' [3.05]
W.C 3'-0"X4'-9"
9'-3"
19'-8" [6.00]
33'-721" 5'
10' [3.05]
PL. DUCT 3'-0"x0'-712"
2'
421"
13'-11" PL. DUCT
19'-8" [6.00]
11'-121"
C.B
50'-1021"
BEDROOM-3 21'-9"x11'-712"
BALCONY
SETBACK LINE
FINAL LAYOUT PLAN, THIRD FLOOR TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% = 5440.50 SQ.FT (505.43 SQ.MT) ACHIEVED COVERED AREA = 3964.20 SQ.FT (368.28 SQ.MT) i.e 54.65%
E-58 Vasant Vihar | Studio Ardete | Electrical Points Count 7/05/21
WORKED ON ELECTRICAL DRAWINGS, LIGHT FIXTURES
LOWER DUPLEX (GROUND FLOOR) DIRECTION: E S.S
SE E.SE
AIR
E
USB OUTLET (RAW POWER)
S.No.
DESCRIPTION LIGHT POINT ON FLOOR
BUILT-UP AREA SCHEDULE C.AREA ON G.FLOOR C.AREA ON F.FLOOR C.AREA ON S.FLOOR C.AREA ON T.FLOOR TOTAL COVERED AREA
2
LIGHT POINT AT HEIGHT 7'-6"
3
LIGHT POINT AT HEIGHT 3'-3"
4
BUZZER
+3'-6" +2'-3"
FAN REGULATOR
+3'-6"
KEY PAD (UNDER DISCUSSION)
C2 6A SWITCH SOCKET OUTLET (RAW POWER)
+3'-6"
USB OUTLET (RAW POWER)
+2'-3"
DATA OUTLET
6A SWITCH SOCKET
+3'-6" +4'-6"
TV OUTLET + DATA OUTLET
+4'-6"
2NOS. 6A SWITCH SOCKET OUTLET (RAW POWER)
AS/CABINET DETAIL
MASTER SWITCH
D1 6A SWITCH SOCKET
E
6A SWITCH SOCKET OUTLET (RAW POWER)
CONDUIT IN FLOOR
1
1
5
5
1
27
3
3
Lobby | Corridor | Balcony
Day Room
3
16A SWITCH SOCKET OUTLET (RAW POWER)
+1'-0"
INTERCOM OUTLET
+2'-6"
H
6A SWITCH SOCKET OUTLET (RAW POWER) (AROMA DIFFUSER) LIGHT POINT
H1 6A SWITCH SOCKET OUTLET (RAW POWER) (AROMA DIFFUSER) I J
LIGHT POINT (ON PARTITION) SHAVER'S SOCKET
+4'-0"
2NOS. 6A SWITCH/SOCKET
K L
6A SWITCH SOCKET OUTLET (RAW POWER) (WATER CLOSET)
Master Bedroom
FOR BED SIDE PLEASE REFER WALL ELEVATIONS
B
6A SWITCH SOCKET, FOR T.V, DATA SOCKET
TOTAL
2NOS. 6A SWITCH/SOCKET (MORE POINTS TO BE ADDED AS/ AUDIO SYSTEM FINALIZED)
B1 6A SWITCH SOCKET, T.V SOCKET, DATA SOCKET
LOCATION
+1'-0"
+4'-6"
INTERCOM OUTLET CLIENT/PROJECT:
RESIDENCE #58 AT VASANT VIHAR, DELHI
NOTE:-
1. This drawing is a COPYRIGHT & PROPERTY of STUDIO ARDETE PVT. LTD, and is NOT TO BE REPRODUCED, COPIED, HANDED OVER to third party or used for any other purpose other than for which its intended.
6)
7) 2. While every attempt has been made in the preparation of this drawing and to avoid mistakes the maker cannot guarantee against human error. The contractor 8) on job must check all dimensions and other details and be responsible for the same. 9)
2
2
7
1
1
1
6
6
13
1
2
16
3
25
8
1
6
1 3
1
11
1
12 0
29
5
Switch
12
12
BERKER | 16A
Socket
50
Double
Switch
6
4
Dummy
5
DATA
6
INTERCOM
7
USB
91
Box | Plate
Socket
23
23
BERKER | 6A
BERKER | 16A
Socket
Double
Switch
6
6
12
9
161
Dummy
DATA
INTERCOM
USB
Box | Plate
Socket
8
1
19 5
1
4
2
1
1
1
Dining Area
3
3
1
1
Lobby | Corridor | Balcony
1
1
3
3
2
12
1
6
1
9 8 0
Servant’s Room
15
19
1
10
10
2
1
6
3
67
UPPER DUPLEX (THIRD FLOOR) BERKER | 6A Switch
BERKER | 16A
Socket
3
4
Master Bedroom
4
Master Washroom Lobby | Corridor | Balcony
+1'-0"
Servant’s Room
GOOD FOR CONSTRUCTION Date of Issue:- 29/04/2019
LOWER DUPLEX_ELECTRICAL
REV-09 CHANGES IN LAYOUT AS PER VASTU CHANGES IN LAYOUT FROM CLIENT (12/09/2018) CHANGES IN LAYOUT FROM CLIENT (11/11/2018) CHANGES IN LAYOUT AS PER VASTU (05/01/2019) CHANGES IN LAYOUT AS PER F.A.R AREA (17/04/2019)
REVISION NO. & NOTES: 5)
1
8
2
1
CONDUIT IN FLOOR
+2'-3"
2
4
2
1
1
PTS. SERVANT ROOM
16A SWITCH SOCKET OUTLET (RAW POWER)
Box | Plate
1
2
Kid’s Washroom
C
1
1
2
+1'-0"
+1'-0" +3'-6"
1
2
2
Kid’s Bedroom
6A SWITCH/SOCKET (RAW POWER)
1
2
+3'-0" +1'-0"
6A SWITCH/SOCKET (RAW POWER)
4
1
1
Day Room
6A SWITCH/SOCKET (RAW POWER)
B
70
Socket
1
Powder Room
C3
+3'-6"
2
USB
1
Guest’s Washroom
B1
4
INTERCOM
1
+1'-0"
SWITCH PLATE
1
DATA
4
6A SWITCH/SOCKET (RAW POWER)
A
Switch
Dummy
1
C2
6/16A SWITCH/SOCKET (RAW POWER)
6
4
Guest’s Bedroom
F1
1
1
CONDUIT IN FLOOR
6/16A SWITCH/SOCKET (RAW POWER)
2
5
6A SWITCH/SOCKET (RAW POWER)
F
11
2
C1
AS/LIFT CONSULTANT
9
5
LOCATION
16A SWITCH/SOCKET (RAW POWER)
6
2
CONDUIT IN FLOOR
1X10W LED BULKHEAD LIGHT
14
1
Living Area | Double Height
AS/CABINET DETAIL
+3'-0"
2
1
Formal Lounge
6A SWITCH/SOCKET (RAW POWER), INTERCOM OUTLET
E
4
Day Washroom
INTERCOM OUTLET
Double
2 4
Switch
C
D 16A SWITCH/SOCKET (RAW POWER) D1 16A SWITCH/SOCKET (RAW POWER)
1
UPPER DUPLEX (SECOND FLOOR)
CONDUIT IN FLOOR
2NOS. 6A SWITCH/SOCKET (MORE POINTS TO BE ADDED AS/ AUDIO SYSTEM FINALIZED)
Socket
3
26
+3'-6"
(ON WOODEN PANELING)
11
BERKER | 16A
BERKER | 6A
LOWER DUPLEX
+2'-6"
(ON WOODEN PANELING)
BERKER | 6A
11
BALCONY
KEY PAD
1
1
Servant’s Room
PTS. DRAWING AREA, LOBBY & DINING AREA, LIFT, LIFT LOBBY,
A
1
Lobby | Corridor | Balcony
+2'-8"
6/16A SWITCH/SOCKET (TOWEL WARMER)
21
Master Washroom
USB
M
1
2
0
Kid’s Washroom
2 NOS. 6A SWITCH/SOCKET DATA OUTLET
1
1
3
15
+1'-0"
DATA OUTLET
1
Servant’s Room
Kid’s Bedroom
+1'-0" CONDUIT IN FLOOR
4 3
3
1
3
Day Washroom Dining Area
6
2
Guest’s Washroom
+1'-0"
F G
Socket
5
Switch
+3'-0"
E1 6A SWITCH SOCKET OUTLET (RAW POWER) E2 6A SWITCH SOCKET OUTLET (RAW POWER)
Switch
8
TV OUTLET + DATA OUTLET
CONDUIT IN FLOOR
Double
8
FROM CEILING
2NOS. 6A SWITCH SOCKET OUTLET (RAW POWER)
Socket
Living Area | Lobby
Guest’s Bedroom
FAN REGULATOR
D
Box | Plate
1
LOCATION
YET TO BE FINALIZED AS/AUTOMATION
AS PER LEGEND
USB OUTLET (RAW POWER) DATA OUTLET
USB
1
1"
C1 6A SWITCH SOCKET OUTLET (RAW POWER)
INTERCOM
LOWER DUPLEX (FIRST FLOOR)
+2'-3"
DATA OUTLET
DATA
1
ACHIEVED F.A.R = 16321.50 SQ.FT i.e 1:2.25 OF SITE AREA
CENTRE LINE
USB OUTLET (RAW POWER)
= 4196.55 SQ.FT = 4196.55 SQ.FT = 3964.20 SQ.FT = 3964.20 SQ.FT = 16321.50 SQ.FT
PERMISSIBLE F.A.R @ 1:2.25:7254 x 2.25 = 16321.50 SQ.FT
6A SWITCH SOCKET OUTLET (RAW POWER)
Dummy
Formal Lounge
Powder Room
DWG NOTES:
1
KEY PAD (UNDER DISCUSSION)
C
SYMBOL
+2'-3"
INTERCOM OUTLET
W N.N
WATER
B1 6A SWITCH SOCKET OUTLET (RAW POWER)
N
TAB/KEY PAD (UNDER DISCUSSION)
E
+2'-3"
INTERCOM OUTLET
NW
6A SWITCH SOCKET OUTLET (RAW POWER) USB OUTLET (RAW POWER)
E.N
B
W
+3'-6"
BERKER | 16A
W.N
+4'-0"
A2 ONE WAY SWITCH
Switch
W
A1 KEY PAD
8.0° N.NE
+3'-6"
NE
KEY PAD
BERKER | 6A
H
SPA CE
BEDROOMS &TOILETS
A
S
LEVELS
W
DESCRIPTION
RT
W.S
PTS.
LOCATION
EA
SW
ELECTRICAL LEGEND
S.SW
E FIR
SCALE:DATE:-
N.T.S 13/02/2020
DWG NOSTATUS-
GFC-FLP-004 FINAL GFC
DRAWN BY:-
SIMARPREET KAUR
CHECKED BY:-
NISHA SARAO
ARCHITECT:
STUDIO ARDETE PRIVATE LIMITED SCO - 43, First Floor, Swastik Vihar, MDC, Panchkula - 134109, Chandigarh (Tricity) TELE. : 0172-4020185 E-MAIL: office.studioardete@gmail.com
TOTAL |
UPPER DUPLEX
Double
Switch
Dummy
DATA
INTERCOM
USB
Box | Plate
Socket
2
-
1
1
4
1
1
1
4
-
1
1
4
1
-
8
2
2
7
1
1
1
6
6
2
13
1
1
2
-
1
-
8
1
1
2
16
-
-
1
-
6
2
3
1
3
25
-
1
-
11
2
12 0
11
29
5
12
12
4
5
6
7
91
26
48
6
22
22
6
6
12
10
158
Date of Revised:- 19/08/2019 CONSULTANT:
TOTAL ALL FLOORS
BERKER | 6A
BERKER | 16A
Switch
Socket
Double
Switch
Socket
52
98
12
45
45
Dummy
DATA
INTERCOM
USB
Box | Plate
12
12
24
19
319
A B
DN DIRECTION:
W N.N
9"
6'
9"
1'
HM A F
1'
1'-6"
2'
2'-6"
1'-6"
A DN
A
1
UP
49
5'-121"
UP
1'
1'
E1
C.B
E 2'-321"
6"
4'-912"
E
3'-3"
2'-9"
F
13'-6"
1'
DA
6"
6"
A
C.B 4'-8"
6'-9"
DA
3'-9"
C1
5'
D
LVL. +9'-3"
B
A
1'
19
C1
C1
E
4'-4"
DRESS
4'
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
6
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
3'-9" EQ EQ
C 9'-621"
48
56
C2
3'
L
1'
1'
DN 42
4'-7"
6"
E2 3'-821"
8
8'-6"
B 1'-6"
ACCESSORIES
DRESS
4'-7"
H
9"
H1
B1
G K
F
2'
5'-3"
A1 I
1'-3" 2'-421" 1'-6"
EQ.
1'-3"
EQ.
SHOWER
ACCESSORIES
1'-3"
4' 9"
G D
D
1'
C.B
A
F
6"
5'-221" 8'-5" 10"
9'-2"
6"
A
1'
K
BENCH
9"
5'
4'-621"
1'-10"
6"
3'-3"
9"
C.B
C.B
5'-321" 2'-1021"
E
8' 4'-8"
3'-8"
UP
C1
4'-2"
J
D A
1
F
E2
2'-6"
BENCH
K
6'-6"
5"
D
D
4'-8"
EQ. EQ.
3'-9"
1'
1'-11"
I
A
9"
SHOWER
3'-3"
G
9"
19
I
G
4'-3"
C.B
E S.S
C.B
8"
= 4196.55 SQ.FT = 4196.55 SQ.FT = 3964.20 SQ.FT = 3964.20 SQ.FT = 16321.50 SQ.FT
PERMISSIBLE F.A.R @ 1:2.25:7254 x 2.25 = 16321.50 SQ.FT
5'-321"
6"
3'-421" 4'-7"
K
4'-3"
3'
CROCKERY CABINET
C.B
EQ.
EQ.
C.B
C.B
1'
C.B 4'-5"
E
B C
E1
C1
3'-1021"
WATER
8
2'-9"
N
1'-7"
A
4'-6"
E
C.AREA ON G.FLOOR C.AREA ON F.FLOOR C.AREA ON S.FLOOR C.AREA ON T.FLOOR TOTAL COVERED AREA
ACHIEVED F.A.R = 16321.50 SQ.FT i.e 1:2.25 OF SITE AREA
C 9'-6"
1'-521"
C3
4'-6"
NW
AIR
E.SE
E.N
6"
SE
W
W.N
C3
D C1
BUILT-UP AREA SCHEDULE
H
PEDESTAL LAMP
2'-221"
PEDESTAL LAMP
C
2'-2"
DN
13'-6"
2'-2"
2'-221"
C1
SETBACK LINE
60
67
76
69
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
UP
1'
STUDIO ARDETE | Electrical Conduits Check | 02/02/21 LOWER DUPLEX FINAL LAYOUT PLAN, GROUND FLOOR
North
There is one conduit running at ht 1’-0” but A should be at ht 3’-6”
C|B|A
Servant’s Room
South
C is missing. There has to be a provision for C at ht 2’-3”. B at ht 1’-0” and A at ht 3’-6” is present.
๏ ๏
CHECKED BY:-
NISHA SARAO
Behind the Crockery Cabinet
๏
Electrical Layouts in Both the Washrooms (i.e. Half Bath & Day Room) are correctly positioned. E Point of the lift blocks are missing. (To be checked when lift is installed)
LOCATION
WALL SIDE
Behind the Main Staircase
West
(MISSING)
D|A
West
E
UPPER PART
LOCATION
(MISSING)
WALL SIDE
Dressing Table
South
Bathroom | Right to W/C
West
Conduits to be provisioned at ht 2’-6”
H
Bathroom | Left of Washbasin
North
Conduits to be provisioned at ht 1’-0”
South
Conduits are present but not on the given vertical line( i.e. 8” from left edge). Currently it is at 3’ from the left edge. (Horizontally)
North
Conduit Line is present but the wall of the balcony is missing to which it has to go at ht 1’-0”.
B1
Left Side of the Bed
South
There is one conduit running at ht 1’-0” but B1 should be at ht 2’-3”
M
Bathroom
North
Conduits are missing, to be provisioned at ht 2’-6” for Towel Warmers
Bathroom | On the wall of the Duct
North
Conduits are missing, to be provisioned at ht 3’-6”
G
E2
๏ ๏
Bathroom | Left to W/C
West
There is one conduit running at ht 1’-0” but G (Intercom Outlet) should be at ht 2’-6”
Bathroom
WALL SIDE
REMARKS
Infront of Basement Staircase
East
Conduit Line has been shifted to the adjacent wall on the right
B (2)
Next to the Lift Shaft
North
Both Conduit Lines are to provided at ht 9”
F
Massage Room | Next to the Cupboard
North
Conduits to be provisioned at ht 2’-9”
Adjacent to the Sump
North
Conduits to be provisioned at ht 9”
POINTS (MISSING)
MASTER BEDROOM
๏
Bathroom | Left to W/C
Basement + Ground Floor
KID’S ROOM
A
West
Conduits are missing, to be provisioned at ht 1’-0”
Rest of the points are in correct position. Light Points at height 7’-6” are also present where marked. E Point of the lift blocks are missing. (To be checked when lift is installed)
B1 | B ๏ ๏
Satyam Rastogi | 2nd February, 2021
9"
E1
MASTER BEDROOM - WASHROOM K
LOCATION
H A
A2
I K G
2'-712"
1'
SHOWER
2'-5"
5"
3'-8"
F 1'
M B1
3'-521"
C2 8'-6"
2'-021"
C.B
Balcony
A
Conduit Line is present but the fitting is to be made on the cupboard at ht 3’-0”
G
GUEST ROOM D
E
REMARKS
GUEST ROOM
REMARKS A (Keypad) at ht 3’-6” is not present. Conduit Line is going for only D at ht 1’-0”
DA
Conduits for 2 Light Points at ht 7’-6” should be provided.
KID’S ROOM - WASHROOM
UPPER PART POINTS
CONSULTANT:
UPPER DUPLEX
E1
LOWER DUPLEX
Provision of light point at ht 3’-3” is required.
SCO - 43, First Floor, Swastik Vihar, MDC, Panchkula - 134109, Chandigarh (Tricity) TELE. : 0172-4020185 E-MAIL: office.studioardete@gmail.com
Electrical Layouts in Both the Washrooms (i.e. Half Bath & Day Room) are correctly positioned. E Point of the lift blocks are missing. (To be checked when lift is installed)
POINTS ๏
East
STUDIO ARDETE PRIVATE LIMITED
1'-6"
Servant’s Room
FINAL GFC
SIMARPREET KAUR
Rest of the points are in correct position. Electrical Conduits have to cross checked on Ground Floor and Basement, when the walls are finalised.
Satyam Rastogi | 2nd February, 2021
8"
C.B
D1 D
2'-2"
A
GFC-FLP-002
STATUS-
DRAWN BY:-
1'-4"
North
N.T.S
DATE:-
13/02/2020 DINING AREA
ht 1’-0” for the same. 9) CHANGES IN LAYOUT AS PER F.A.R AREA (17/04/2019) on job must check all dimensions and other details and beatresponsible
Dining Area | External Wall of Day Room
MidDWGLanding of the Internal Staircase NOARCHITECT:
SCALE:-
F1
D1 | A
Date of Issue:- 29/04/2019
Conduit Line is present but the wall is missing to which it has to go at ht 3’-0”.Date of Revised:- 19/08/2019
LOWER DUPLEX_ELECTRICAL
CLIENT/PROJECT:
Intercom Outlet is present at ht 3’-0” but 16A Socket at ht 1’-0” is missing. A (Keypad) provision is there as well.
LVL. +19'-3"
GOOD FOR CONSTRUCTION REMARKS
West
1'
West
Below Mid Landing of the Internal There is one conduit but& not in the same vertical REVISION NO. NOTES: REV-09 1. This drawing is a COPYRIGHT & PROPERTY of STUDIO ARDETE running NOTE:East PVT. LTD, and is NOT TO BE REPRODUCED, COPIED,line. HANDED OVER to third 5) CHANGES IN LAYOUT AS PER VASTU Staircase 6) CHANGES IN LAYOUT FROM CLIENT (12/09/2018) party or used for any other purpose other than for which its intended. RESIDENCE #58 AT 7) CHANGES IN LAYOUT FROM CLIENT (11/11/2018) 2. While every attempt has been made in the preparation of this drawing and to On the Externalavoid Wall of Day Room | There is one conduit running at ht 3’-3” but D should be VASANT VIHAR, DELHI mistakes the maker cannot guaranteeWest against human error. The contractor 8) CHANGES IN LAYOUT AS PER VASTU (05/01/2019) D Opposite the Internal Staircase
WALL SIDE
DRESS
Behind the Main Staircase
LOCATION
Living Lounge (Closed)
D2
1'-6"
D|A
Conduits are missing, to be provisioned at ht 1’-0” and 3’-6” respectively.
3'-10"
(MISSING)
DA
3'-1121"
POINTS
UPPER DUPLEX LOWER PART TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) WALL @ 75% = 5440.50 SQ.FT (505.43 SQ.MT) POINTS PERMISSIBLE COVERED AREA LOCATION REMARKS (MISSING) SIDE ACHIEVED COVERED AREA = 4196.45 SQ.FT (389.86 SQ.MT) i.e 57.85%
3'-10"
LOWER PART
1'-3"
3'
B
1'-3"
6
1'-6"
S
C3
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
F1
W
FULL HT. CABINET
INBUILT FRIDGE
W.S
FULL HT. CABINET
W
D1 A B
D
E
6"
1'
D
C.B
DWG NOTES:
4'-2"
A
3'
H
SPAC
CB A
SW
D
RT
8.0°
1'-3"
UP
N.NE
D
6"
NE
7"
B
A B
DN
1021"
EA
S.SW
E FIR
B1 A
UP
B C
BEAM 8" DN.
C1
C1
C2
C2
DN
SLAB 6" THK.
UP
ODU
C6 C5
4'
BEAM 8" DN.
C3
BEAM 8" DN.
BEAM 8" DN.
C4
DN 9'
UP
6'-6"
BEAM 8" DN.
C6 C5
BEAM 18" DN.
4'
10'
C7
C8
DALI TRACK LIGHT
SW1
BEAM 18" DN.
C4
C3
SLAB 10" THK.
SW2
Width - 4'-0" Tread - 1'-0" Riser - 0'-6" 8
19
6
18" BEAM
DN.
SUNKEN
N.
"D
AM
18
1
C9
SLAB 10" THK.
UP
BE
C11
UPTURN BEAM 6" UP.
9" 1'
AA
V-1
18'
C7
BEAM 8" DN.
9'
C10 6'-6"
8'-421"
C8
C14
48
49
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
UP
C15 LVL. +9'-3" SLAB 6" THK.
SLAB 6" THK.
3'-7"
SW5
7'-3"
LIFT-2 (6P) LIFT-2 (6P) 5'-0"x5'-0" 5'-0"x5'-0"
C17
UPTURN BEAM 6" UP.
SLAB 7" THK.
8'-1121"
11'-11"
4'
19
8'
DN
8
SW7
BEAM 1'-0" DN.
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
SW6
LIFT-1 (10P) LIFT-1 (10P) 6'-3"x6'-0" 6'-3"x6'-0"
SW4
BEAM 1'-0" DN.
SW2
BEAM 8" DN.
BEAM 1'-0" DN.
5'
SW1
1
4' 6'-812"
3'
C9
SW3 DN
42
56
BEAM 1'-0" DN.
C13
6
SW3 BEAM 1'-0" DN.
10'
BEAM 1'-0" DN.
8'
UP
C19
C18
C20 BEAM 1'-0" DN.
BEAM 8" DN.
SLAB 6" THK.
C10
C11
SETBACK LINE
FINAL LAYOUT PLAN, GROUND FLOOR
AA
V-1
TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% = 5440.50 SQ.FT (505.43 SQ.MT) ACHIEVED COVERED AREA = 4196.45 SQ.FT (389.86 SQ.MT) i.e 57.85%
4'
8'-2"
C1
C2
4' DN UP
2'
C5 8'-312"
3'-6"
6"
87
1' 1'
80
C4
C3
DN
4'-4"
SW3
9"
SW3
C6
C7
1'-6"
96
C14
89
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
C8
UP SW1 SW2
C13
C15
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
DN
8 6
C9
19
1
UP
LVL. +29'-3"
C10
C11 1'
1'
LIFT-3 (6P) 5'-0"x5'-0"
C17
SW4
7"
SW6
1'
SW5
2'-312"
SW3
SW3 DN
LIFT-1 (10P) 6'-3"x6'-0"
SW7
C14
100
107
116
109
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
UP
C13
C15 LVL. +39'-3"
9'-1"
SW5 LIFT-3 (6P) 5'-0"x5'-0"
C17
SW6
LIFT-1 (10P) 6'-3"x6'-0"
SW4
SW7
2'
6'
11'-021"
3'
8'
WORKED ON SUPERIMPOSITION OF ALL SERVICES DRAWINGS COORDINATED TOGETHER
ODU
SLAB 10" THK.
9'-021"
C18
C18
C19
C19
C20
SETBACK LINE
C20 FINAL LAYOUT PLAN, THIRD FLOOR
TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% = 5440.50 SQ.FT (505.43 SQ.MT) ACHIEVED COVERED AREA = 3964.20 SQ.FT (368.28 SQ.MT) i.e 54.65%
WORKED ON ALL WASHROOMS
RENDERED VIEW
RENDERED WASHROOM VIEWS RENDERED VIEW
RENDERED VIEW
RENDERED VIEW
RENDERED VIEW
RENDERED WASHROOM VIEWS
RENDERED VIEW
1'-3"
4'-8"
6'-03 4"
6"
1'-0"
WORKING DRAWINGS OF WASHROOMS B.O.SLAB B.O.BEAM FALSE CEILING
3
LIGHT AS APP.
1'-6"
BINDS AS APP. 2'-0"
6"
eq
LAYOUT@1'-0" HT FROM FFL
3"
H
eq
HEALTH FAUCET AS APP.@ 1'-6"FROM FFL. POINT @ (K )AS/ ELECTRICAL LAYOUT@1'-0" HT FROM FFL
SHOWER/DIVERTER AS APP
WIRE FROM ELECTRICAL POINT TO HEATED SEAT TO BE ENCASED IN ALUMINIUM PROFILE AS/DETAIL-7
WF S-1
1'
HEATED W.C. AS/ APP.
9"
6A SWITCH SOCKET OUTLET (E2) (RAW POWER) AS/ ELECTRICAL LAYOUT@1'-0" HT FROM FFL
PAINTING
LVL+4'-021"
E2
K LVL±0"
4
8
FINISHED FLOOR LVL..
FINISHED FLOOR LVL..
9" 1'-6" 1'-3"
TOWEL WARMER
LVL±0"
LVL±0"
G
TOILET PAPER HOLDER AS APP @1'-6"FROM FFL.
LVL±0"
5
2'-9"
2" 1'-0"
2" 5"
I
1'-3"
6A SWITCH SOCKET OUTLET (RAW POWER) (AROMA DIFFUSER) (H)AS/ ELECTRICAL
WF S-1
GLASS/ BLACK MIRROR
INTERCOM OUTLET @ (G) AS/ ELECTRICAL LAYOUT @2'-6" HT FROM FFL
1'-0"
WF M-1
COUNTER HT. OF COUNTER AS/ WASH BASIN SELECTION
LVL±0"
SHAVER'S POINT SOCKET @ I, AS/ ELECTRICAL LAYOUT@3'-6" HT FROM FFL
3'-621"
WF S-1
CILL LVL@ 4'-0" FROM FFL.
3'
HANGING LIGHT AS/ APP.
2
WF S-3
LVL+2'-9"
1'-6"
4'-0"
MIRROR AS/ APP.
FLUTED GLASS UPTO 7'-0" HEIGHT
LVL+2'-421"
FALSE CEILING
BLINDS AS APP. LED LIGHT STRIP
WF S-2
WF S-2
1'-1121"
LIGHT
2
LIGHT AS APP. LIGHT AS APP. 7'-0" FROM FFL.
R1 '-0 "
1'-0"
C.L.OF MIRROR
FALSE CEILING
LINE OF LED LIGHT STRIP IN STONE FLUTING
2'-3"
B.O.SLAB
1'
B.O.SLAB
4'-8"
6'-03 4"
6"
6"
1'-0"
B.O.SLAB
B.O.SLAB
B.O.BEAM FALSE CEILING
B.O.BEAM LVL.
3
LIGHT AS APP.
2
FALSE CEILING
WF S-3
WF S-1
1'
LED LIGHT AS APP
6"
TOWEL WARMER
6/16A SWITCH/SOCKET (TOWEL WARMER)(M) AS/ ELECTRICAL LAYOUT@2'-6" HT FROM FFL
FALSE CEILING
KEYPAD @ A, AS/ ELECTRICAL LAYOUT@3'-6" HT FROM FFL
A
6A SWITCH SOCKET OUTLET (E2) (RAW POWER) AS/ ELECTRICAL LAYOUT@1'-0" HT FROM FFL
WASH BASIN ABOVE COUNTER AS APP.
M
7
2'-6"
PAINTING
LVL+4'-021"
E2 1'-0"
1'
3' 1'-6"
G
WF S-1
TOWEL WARMER
LVL±0"
LVL±0"
TOILET PAPER HOLDER AS APP @1'-6"FROM FFL.
LVL±0"
DF LM
FLUTED GLASS UPTO 7'-0" HEIGHT
LVL+2'-421"
CILL LVL@ 4'-0" FROM FFL. INTERCOM OUTLET @ (G) AS/ ELECTRICAL LAYOUT @2'-6" HT FROM FFL
WF S-1
LINE OF LED LIGHT STRIP IN STONE FLUTING
2'-3"
1'-6"
BINDS AS APP.
BLINDS AS APP.
9" 1'-6"
LOOKING MIRROR DOOR WITH WOODEN FRAME FINISHED FLOOR LVL..
11 1021"
6"
6"
3'-3"
FALSE CEILING
WASH BASIN AS APP.
MIRROR AS /DETAIL-9
M 1
OPEN SHELF AS APP WITH LIGHT PROVISION AT BOTTOM
MASTER-UPPER-ELEVATIONS PAI NTING AS APP.
2'-9"
S 1
2'-6"
S 3
OPEN SELF FOR STORAGE
10
WASH BASIN AS APP.
5
CILL LVL. 4" FROM FFL.
FINISHED FLOOR LVL
S 1
FINISHED FLOOR LVL
ELEVATION -A
ELEVATION -B
B.O.S LVL.
B.O.BEAM FALSE CEILING
FALSE CEILING
LED LIGHT AS APP
S 3
S 2
10'-0"
BLINDS AS APP. HEALTH FAUCET AS APP.@ 1'-6"FROM FFL.
7'-3"
KEYPAD @A AS/ ELECTRICAL LAYOUT @3'-6" HT FROM FFL
A
W.C.AS APP.
INTERCOM OUTLET @ G AS/ ELECTRICAL LAYOUT @2'-6" HT FROM FFL
G
POINT @ K AS/ ELECTRICAL LAYOUT@1'-0" HT FROM FFL
3'-5"
K
ELEVATION -B
6"
TOILET PAPER HOLDER AS APP @1'-6"FROM FFL.
1021" 5
E2
SWITCH SOCKET @ E2 AS/ ELECTRICAL LAYOUT @1'-0" HT FROM FFL
2
4'-821"
5'-3"
S 3
FINISHED FLOOR LVL
FINISHED FLOOR LVL.
ELEVATION -D
POWDER ROOM_LOWER DUPLEX CLIENT/PROJECT:
RESIDENCE #58 AT VASANT VIHAR, DELHI
NOTE:-
1. This drawing is a COPYRIGHT & PROPERTY of STUDIO ARDETE PVT. LTD, and is NOT TO BE REPRODUCED, COPIED, HANDED OVER to third party or used for any other purpose other than for which its intended.
REVISION NO. & NOTES: 5)
REV-00
SCALE:-
N.T.S
DATE:-
STATUS-
6)
7) 2. While every attempt has been made in the preparation of this drawing and to avoid mistakes the maker cannot guarantee against human error. The contractor 8) on job must check all dimensions and other details and be responsible for the same. 9)
DWG NO-
DRAWN BY:-
SATISH
CHECKED BY:-
NISHA
GFC-TD-002 FINAL GFC
ARCHITECT:
STUDIO ARDETE PRIVATE LIMITED SCO - 43, First Floor, Swastik Vihar, MDC, Panchkula - 134109, Chandigarh (Tricity) TELE. : 0172-4020185 E-MAIL: office.studioardete@gmail.com
CONSULTANT:
WATERPROOFING TEST | E-58 Vasant Vihar
Mosaic Wall Design
21/06/21
LOWER DUPLEX LOWER PART | Ground Floor Location
Date of Filling
Date of Emptying
Remarks
Day Bedroom Bathroom
20/3/21
1/4/21
Good to go.
Powder Room
30/3/21
7/4/21
Good to go.
Servant’s Room
23/3/21
3/4/21
Good to go.
Maid’s Room
10/4/21
22/4/21
Good to go.
Master Bedroom Bathroom
22/3/21
3/4/21
Good to go.
Kid’s Bathroom
22/3/21
3/4/21
Good to go.
Guest’s Bathroom
20/3/21
3/4/21
Good to go.
Servant’s Room
23/3/21
3/4/21
Good to go.
Date of Filling
Date of Emptying
Day Bedroom Bathroom
30/3/21
7/4/21
Good to go.
Powder Room
30/3/21
7/4/21
Good to go.
Servant’s Room
22/3/21
3/4/21
Good to go.
Maid’s Room
10/4/21
22/4/21
Good to go.
Master Bedroom Bathroom
31/3/21
7/4/21
Good to go.
Kid’s Bathroom
31/5/21
10/6/21
Good to go.
Guest’s Bathroom
19/3/21
3/4/21
Good to go.
Servant’s Room
21/3/21
3/4/21
Good to go.
Dark Brown
Light Brown
UPPER PART | 1st Floor
Cream
Grey-Base UPPER DUPLEX LOWER PART | 2nd Floor
Iterations (More Dense)
Location
Remarks
UPPER PART | 3rd Floor
Signature | Approval
STAIRCASE/LOBBY DESIGN
9"
SW7
6"
6'-921"
C20
5'
9"
36
26
19
1" 11'-112
10"
STONE SHADE AS APP. STONE SHADE AS APP. (BLACK) FIXED GLASS
D
B
C
LIFT/STAIR LOBBY 16'-0"x17'-0" 6"
5'
9"
1" 04/03/2020
DRAWN BY:-
SIMARPREET KAUR
CHECKED BY:-PRERNA
ARCHITECT:
19
HVAC SHAFT 3'-3"x 6'-412"
WALL MURAL
LIFT-2 (6P) 5'-0"x5'-0"
SW4
C.B
19'-8" [6.00]
SW5 SW6 LIFT-1 (10P) 6'-3"x6'-0"
SW7
PEDESTAL LAMP
C19
C20 BALCONY
5'-0" WIDE DOUBLE HEIGHT BALCONY
SETBACK LINE
1" 2'-102
2'-6"
3'-6"
1" 11'-112
D
1'
B
DA
C
6'
LIFT/STAIR LOBBY 16'-0"x17'-0" 6"
LIFT-1 (10P) 6'-3"x6'-0"
HVAC SHAFT
5'
9"
2'-6"
1" 2'-102
3'-6"
STONE SHADE AS APP. STONE SHADE AS APP.
S 3
STONE SHADE AS APP. (BLACK)
G 1
FIXED GLASS
1" 10'-82
1'-4"
LIFT-1 (10P) 6'-3"x6'-0"
HVAC SHAFT
LIFT-2 (6P) 5'-0"x5'-0"
Ground Floor and Above
BEAM 1'-0" DN.
Electrical Plan
STAIRCASE (Plans)
BEAM 1'-0" DN.
NOTE:-
REVISION NO. & NOTES:REV-00 1. This drawing is a COPYRIGHT & PROPERTY of STUDIO ARDETE PVT. LTD, and is NOT TO BE REPRODUCED, COPIED, HANDED OVER to third 5) 6) RESIDENCE #58 AT party or used for any other purpose other than for which its intended. 2. While every attempt has been made in the preparation of this drawing and 7)to VASANT VIHAR, DELHIavoid mistakesthe maker cannot guarantee against human .error The contractor8) on job must check all dimensions and other details and be responsible for the9)same.
SCO - 43, First Floor, Swastik Vihar, MDC, Panchkula - 134109, Chandigarh (Tricity) TELE. : 0172-4020185
BEAM 1'-0" DN.
S 1 S 2
ELEC.(LOW SIDE) 5'-0"x1'-0"
LIFT-2 (6P) 5'-0"x5'-0"
STUDIO ARDETE CONSULTANT: PRIVATE LIMITED
MATERIAL KEY ( LEGEND )
5'
A
1'-4"
TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% 5440.50 SQ.FT(505.43 SQ.MT) = ACHIEVED COVERED AREA4196.45 = SQ.FT(389.86 SQ.MT) i.e 57.85%
UP
1" 10'-82
ELEC.(LOW SIDE) 5'-0"x1'-0"
CLIENT/PROJECT:
LD-GBE-003
ELEC.(LOW SIDE) 5'-0"x1'-0"
C18
4'
26
10"
6'
LOWER DUPLEX STATUS-
LVL. +9'-3"
FOYER
DN 36
BEAM 1'-0" DN.
BEAM 1'-0" DN.
12" 5"
2"
2"
S 2 S 3
G 1
8'
29
4'-6"
A
STAIRCASE (DETAILS) DWG NO-
4' 4'-6" 5'
UP
STONE SHADE AS APP.
FLUTING IN ITALIAN MARBLE
N.T.S
C15
DOUBLE HEIGHT FORMAL LOUNGE 16'-0"x18'-0"
BEAM 1'-0" DN.
6"
29
1"X21"
DATE:-
UP
PEDESTAL LAMP
BEAM
4'
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
BEAM 1'-0" DN.
BRICK WALL
SCALE:-
LIFT-1 (10P) 6'-3"x6'-0"
HVAC SHAFT
LIFT-2 (6P) 5'-0"x5'-0"
DN
FIXED GLASS TO THE BEAM BOTTOM
REVISION NO. & NOTES:REV-00 1. This drawing is a COPYRIGHT & PROPERTY of STUDIO ARDETE PVT. LTD, and is NOT TO BE REPRODUCED, COPIED, HANDED OVER to third 5) 6) RESIDENCE #58 AT party or used for any other purpose other than for which its intended. 2. While every attempt has been made in the preparation of this drawing and 7)to VASANT VIHAR, DELHIavoid mistakesthe maker cannot guarantee against human .error The contractor8) on job must check all dimensions and other details and be responsible for the9)same.
49
LIFT/STAIR LOBBY 16'-0"x17'-0"
1'-1021"
1'-0" DN.
8'
MATERIAL KEY ( LEGEND )
NOTE:-
56
Width- 4'-0"
FINAL LAYOUT PLAN, GROUND FLOOR
S 1
FALSE CEILING DN.AS/HVAC DUCT LVL./ (+1'-6" LVL. FROM B.O.S)
SW3
48
Tread- 1'-0" C14 Riser - 0'-6"
7'-9"x14 '-10"
C17
BEAM 1'-0" DN.
4'
4'-6"
18MM PLY GLASSFIXED ON 12MM PLY & Aluminium Frame21"1 X 2" GLASS 18MM
HEIGHT (19'-3") C13DOUBLE PUJA ROOM
DN
42
1'-3"
4'-6"
4" HVAC GRILL
LEDGE WALL UPTO CEILING HT.
3'-0"
SW3
PL. DUCT 1'-0"x2'-6"
SETBACK LINE
Elevation-Lift Lobby
121"
1'-4"
LIFT-1 (10P) 6'-3"x6'-0"
HVAC SHAFT
LIFT-2 (6P) 5'-0"x5'-0"
TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% 5440.50 SQ.FT(505.43 SQ.MT) = ACHIEVED COVERED AREA4196.45 SQ.FT(389.86 SQ.MT) i.e = 57.85%
R.C.C. SLAB
3'-6"
PL. DUCT 1'-6"x1'-6"
CONSOLE
10'-3" WIDE DOUBLE HEIGHT TERRACE
ELEC.(LOW SIDE) 5'-0"x1'-0"
FINAL LAYOUT PLAN, GROUND FLOOR
1'-6"
3'-6"
ELEC.(LOW SIDE) 5'-0"x1'-0"
BALCONY
DETAIL A-Fluting
CLIENT/PROJECT:
2'-6"
3'-8"
3'-0"
TOILET C11 10'-3"x6'-9"
SHOWER
HALF BATH 16'-412"x7'-0"
BALCONY
C19 5'-0" WIDE DOUBLE HEIGHT BALCONY
1" 2'-102
117' [35.66] 90'-221" [27.50]
LIFT/STAIR LOBBY 16'-0"x17'-0"
LIFT-1 (10P) 6'-3"x6'-0"
C.B C.B
C.B
19'-8" [6.00]
SW5 SW6
2'
1" 6'-72
3'-9"
BENCH
VESTIBULE 6'-112"x6'-9"
CONSOLE
HVAC SHAFT 3'-3"x 6'-412"
3"
DETAIL B
DAY ROOM 1" 16'-412"x12'-7 2
UP
6'-921"
SW4
1'-3"
16'-921" [5.12]
Fluted Stone
19 1
DOUBLE HEIGHT LIVING AREA 1" 16'-0"x32'-1 2
16'-921" [5.12]
LIFT-2 (6P) 5'-0"x5'-0"
PEDESTAL LAMP
5'
8 6
3'-6" 9" 1'-1"
5'-0" WIDE BALCONY
1'-0"
ELEC.(LOW SIDE) 5'-0"x1'-0"
1'-1021"
C17
DOUBLE HEIGHT FORMAL LOUNGE 16'-0"x18'-0"
9"
BEAM 1'-0" DN.
1" 10'-82
1'-0"
2'-1"4
2'-0" 3'-8"
LVL. +9'-3"
6'
BEAM 1'-0" DN.
CONSOLE
LIFT/STAIR LOBBY 16'-0"x17'-0" FOYER
BEAM 1'-0" DN.
WALL MURAL
UP
C8
FULL HT. CABINET
C10
SW3
49
PEDESTAL LAMP
2'-6"
INBUILT FRIDGE
Width- 4'-0" Tread- 1'-0" Riser - 0'-6"
C9
DN 48
42
56
Width- 4'-0"
C15
C18
2'-10"
SW2
FULL HT. CABINET
11'-3" [3.43]C7
WALK-IN CLOSET 6'-0"x10'-7"
DINING AREA 1" 13'-7"x18'-4 2
SW1
1" 2
117' [35.66] 90'-221" [27.50]
SW3
Tread- 1'-0" C14 Riser - 0'-6"
7'-9"x14 '-10"
Detail A-Fluting
3'-6"
TOILET 8'-0"x4'-6"
UTILITY 6'-0"x12'-6"
2'
C2
SERVANT ROOM (3P) 10'-0"x13'-0"
WALK-IN CROCKERY 6'-0"x7'-0"
PL. DUCT 1'-6"x1'-6"
HEIGHT (19'-3") C13DOUBLE PUJA ROOM
PL. DUCT 1'-0"x2'-6"
1'-4"
1" 2'-02
C6
C.B
C5
KITCHEN 12'-0"x21'-10" +7'-9"x8'-3"
UP
HALF BATH 16'-412"x7'-0"
7'-9"
Metal Finish
10"
1
Width - 4'-0" Tread - 1'-0" Riser - 0'-6"
BEAM 1'-0" DN.
BEAM 1'-0" DN.
STAIRCASE WORKING DRAWING
Wallpaper
8
UP
1" 11'-112
BEAM 1'-0" DN.
LIFT 1
Width - 4'-0" Tread - 1'-0" Riser - 0'-6 1/4"
FIXED GLASS TO THE BEAM BOTTOM
LEDGE WALL UPTO CEILING HT.
3'-0"
BEAM 1'-0" DN.
8'
3'-6"
TOILET C11 10'-3"x6'-9"
SHOWER
CONSOLE
10'-3" WIDE DOUBLE HEIGHT TERRACE
S 3
3'-0"
3'-11"
3'-9"
BENCH
1" 2
DAY ROOM 1" 16'-412"x12'-7 2
C10 VESTIBULE 6'-112"x6'-9"
412"
PL. DUCT 1" 3'-0"x0'-7 2
C4
MAID ROOM 8'-0"x8'-4"
K.STORE 1" 6'-0"x6'-7 2
W.C SHOWER 3'-0"X4'-9" W.B 3'-3"X4'-9" 3'-0"X4'-2"
DN UP
PL. DUCT 2'-0"x2'-0"
C3
EL./HVAC DUCT 1 10'-0"x1'-7 2"
2'-1"4
19
UP
11'-121" [3.39]
C1 5'-0" WIDE BALCONY
5'
1
FULL HT. CABINET
1
DOUBLE HEIGHT LIVING AREA 1" 16'-0"x32'-1 2
62' [18.90] 50'-1021" [15.51]
67
3'-11"
INBUILT FRIDGE
8 6
60 5'
8
Ceiling Plan and Lighting Plan
2'
DN
2'-0" 3'-8"
SW2
FULL HT. CABINET
SW3
5'
8'-11"
C8
Width- 4'-0" Tread- 1'-0" Riser - 0'-6"
C9
2'
2'
17
97'-4" [29.66]
Stilt Floor Plan
4'
DN
11'-3" [3.43]C7
WALK-IN CLOSET 6'-0"x10'-7"
DINING AREA 1" 13'-7"x18'-4 2
UTILITY 6'-0"x12'-6"
SW1
8'
10
97'-4" [29.66]
6"
TOILET 8'-0"x4'-6"
4'
BALCONY
KITCHEN 12'-0"x21'-10" +7'-9"x8'-3"
C.B C.B
C.B
K.STORE 1" 6'-0"x6'-7 2
C2
SERVANT ROOM (3P) 10'-0"x13'-0"
WALK-IN CROCKERY 6'-0"x7'-0"
CROCKERY CABINET
1'-6"
C5
5'-0" WIDE BALCONY
10' [3.05]
1'-6"
C6
C.B
MAID ROOM 8'-0"x8'-4"
C.B
412"
PL. DUCT 1" 3'-0"x0'-7 2
C4
W.C SHOWER 3'-0"X4'-9" W.B 3'-3"X4'-9" 3'-0"X4'-2"
DN UP
PL. DUCT 2'-0"x2'-0"
EL./HVAC DUCT 1 10'-0"x1'-7 2"
CROCKERY CABINET
11'-121" [3.39]
C1 5'-0" WIDE BALCONY
C3
10' [3.05]
62' [18.90] 50'-1021" [15.51]
6"
LOWER DUPLEX
SCALE:DATE:-
N.T.S
DWG NO-
LD-GBE-003
STUDIO ARDETE CONSULTANT: PRIVATE LIMITED
ARCHITECT:
STATUS-
04/03/2020
DRAWN BY:-
SCO - 43, First Floor, Swastik Vihar, MDC, Panchkula - 134109, Chandigarh (Tricity) TELE. : 0172-4020185 E-MAIL: office.studioardete@gmail.com
SIMARPREET KAUR
CHECKED BY:-PRERNA
E-MAIL: office.studioardete@gmail.com
62' [18.90] 50'-1021" [15.51]
11'-121" [3.39]
412"
PL. DUCT 1" 3'-0"x0'-7 2
KITCHEN 12'-0"x21'-10" +7'-9"x8'-3"
TOILET 8'-0"x4'-6"
SW1 SW2
3'-3"
FULL HT. CABINET
INBUILT FRIDGE
19
S 3
G 1
S 1
S 3
C.B
LEDGE WALL UPTO CEILING HT.
1'-0"
2'-0" 3'-8"
3'-0"
HALF BATH 16'-412"x7'-0" PL. DUCT 1'-6"x1'-6"
CONSOLE
HEIGHT (19'-3") C13DOUBLE PUJA ROOM
DN
SW3
48
42
56
49
Tread- 1'-0" C14 Riser - 0'-6"
Width- 4'-0"
UP
C15 LIFT/STAIR LOBBY 16'-0"x17'-0" LVL. +9'-3"
FOYER ELEC.(LOW SIDE) 5'-0"x1'-0"
1'-1021"
S 1
SW3
7'-9"x14 '-10"
CONSOLE
1'-2" 2"
3'-6"
TOILET C11 10'-3"x6'-9"
SHOWER
DOUBLE HEIGHT LIVING AREA 1" 16'-0"x32'-1 2
10'-3" WIDE DOUBLE HEIGHT TERRACE
1'-6"
3'-0"
2'-1"
3'-9"
BENCH
3'-11"
C10 VESTIBULE 6'-112"x6'-9"
412"
DAY ROOM 1" 16'-412"x12'-7 2
UP
9"
FIXED GLASS
C9 1"
97'-4" [29.66]
3'-3"
Studs used to fix the Railing
1
WALL MURAL
Entrance
FULL HT. CABINET
8
117' [35.66] 90'-221" [27.50]
Glass Railing
7'-9"
LIFT
7'-8"
11'-3" [3.43]C7
C8
Width- 4'-0" Tread- 1'-0" Riser - 0'-6" 6
8'-3"
WALK-IN CLOSET 6'-0"x10'-7"
DINING AREA 1" 13'-7"x18'-4 2
UTILITY 6'-0"x12'-6"
LIFT
SERVANT ROOM (3P) 10'-0"x13'-0"
WALK-IN CROCKERY 6'-0"x7'-0"
C.B C.B
C5
19'-8" [6.00]
DN UP
C6
C.B
MAID ROOM 8'-0"x8'-4"
K.STORE 1" 6'-0"x6'-7 2
2" S 1
DETAIL B
C4
CROCKERY CABINET
5"
2"
EL./HVAC DUCT 1 10'-0"x1'-7 2"
C.B
C3
1'-6" 4" Grill
5'-0" WIDE BALCONY PL. DUCT 2'-0"x2'-0"
1'-9"
C2
W.C SHOWER 3'-0"X4'-9" W.B 3'-3"X4'-9" 3'-0"X4'-2"
5'-0" WIDE BALCONY
10' [3.05]
C1
LIFT-2 (6P) 5'-0"x5'-0"
C17
SW4
HVAC SHAFT 3'-3"x 6'-412"
SW5 SW6 LIFT-1 (10P) 6'-3"x6'-0"
SW7
PL. DUCT 1'-0"x2'-6"
Glass Railing
PEDESTAL LAMP PEDESTAL LAMP
FIXED GLASS
Entrance
S 3
7'-0"
C19
C18
S 3
S 1
G 1
F.F.L.
F.F.L.
5'-0" WIDE DOUBLE HEIGHT BALCONY
6'-921"
LIFT
LIFT
16'-921" [5.12]
7'-3"
C20
BALCONY
1'-3"
DOUBLE HEIGHT FORMAL LOUNGE 16'-0"x18'-0"
BALCONY
SETBACK LINE
FINAL LAYOUT PLAN, GROUND FLOOR
TOTAL PLOT AREA:- = 62'-0"x117'-0" = 7254.00 SQ.FT (806.00 SQ.YD / 673.91 SQ.MT) PERMISSIBLE COVERED AREA @ 75% 5440.50 SQ.FT(505.43 SQ.MT) = ACHIEVED COVERED AREA4196.45 SQ.FT(389.86 SQ.MT) i.e = 57.85%
Elevation C
1'-6"
Elevation D
1' 6"
DETAIL B 10'
S 2
8'-6"
LVL. ± 0'-0"
1'-0"
8'-3"
LVL. ± 0'-0"
1'-6"
S 2
4" Grill
6"
Ground
LVL. ± 0'-0"
12MM Groove
8'-9"
S 1
FIXED GLASS
LIFT
G 1
8'
A
4'-9"
Mock Up Detail
Stilt
3'-6" 8'-9"
8'
Elevation B
STAIRCASE (WALL ELEVATIONS)
Detail as per mock up
Elevation A REVISION NO. & NOTES:REV-00 1. This drawing is a COPYRIGHT & PROPERTY of STUDIO ARDETE PVT. LTD, and is NOT TO BE REPRODUCED, COPIED, HANDED OVER to third 5) 6) party or used for any other purpose other than for which its intended. RESIDENCE #58 AT 2. While every attempt has been made in the preparation of this drawing and 7)to VASANT VIHAR, DELHIavoid mistakesthe maker cannot guarantee against human .error The contractor8) on job must check all dimensions and other details and be responsible for the9)same.
F.F.L.
0"
6"
F.F.L.
NOTE:-
D
9"
7'-3"
S 2
12"
LVL. ± 0'-0"
3'-3"
CLIENT/PROJECT:
FALSE CEILING LvL.
6"
S 2
TRUE CEILING LvL.
0"
FALSE CEILING 6" LvL.
LVL. ± 0'-0"
LOWER DUPLEX SCALE:DATE:-
N.T.S
DWG NO-
LD-GBE-003
STATUS-
04/03/2020
DRAWN BY:-
SIMARPREET KAUR
CHECKED BY:-PRERNA
ARCHITECT:
STUDIO ARDETE CONSULTANT: PRIVATE LIMITED SCO - 43, First Floor, Swastik Vihar, MDC, Panchkula - 134109, Chandigarh (Tricity) TELE. : 0172-4020185 E-MAIL: office.studioardete@gmail.com
ANALYSING SPACES BETWEEN DUCTS AND FALSE CEILING LEVEL
UPPER DUPLEX-KITCHEN DESIGN WITH MATERIALS
LOWER DUPLEX-KITCHEN DESIGN WITH MATERIALS
E-2/4, VASANT VIHAR This Another Site Was A Renovation Super Fast Construction Project, Undertaken By Studio Ardete. The Interiors And All Designing Is The Charm Of The Place.
APARTMENT LOUNGE AREA KITCHEN DRAWING ROOM + DINING AREA POWDER LOO GUEST ROOM | WASHROOM KID’S ROOM | WASHROOM | WC MASTER BEDROOM | WASHROOM | WALKING CLOSET
ON GOING SITE PICTURES
COMPLETED ON 26TH JUNE, 2021 AND HANDED OVER TO THE CLIENT
SITE PHOTOS AND PROCESS
RAJENDRA NAGAR
6th July, 2021 26th June 2021
RAJENDRA NAGAR Basement Basement Drawing DrawingWork Work Progress Progress
This Another Site Was Also A Residential Bungalow Of 4 Floors, Into The Dense Typology, Situated In Rajendra Nagar. This Is An Ongoing Site, With Forth Floor Slab Currently Being Casted. In This Project, We Faced Municipal And Law Negligence, Due To Which We Had To Shift The Entire Building Behind By 3 Feet
Civil Civil
Stilt Stilt
First First
Second Second
Third Third
10% 10%50% 50%90% 90%100% 100% 10% 10%50% 50%90% 90%100% 100% 10% 10%50% 50%90% 90%100% 100% 10% 10%50% 50%90% 90%100% 100% 10% 10%50% 50%90% 90%100% 10
Excavation Excavation AntiTermite AntiTermite PCC PCC Foundation/Footing/Raft Foundation/Footing/Raft Retaining Retaining Wall Wall Guniting Guniting Casting Casting Columns Columns Casting Casting Roof Roof Slab Slab Brickwork Brickwork Plaster Plaster Waterproofing Waterproofing Terrace Terrace Terrace Terrace PCC PCC Foundation Foundation forfor Services Services
External External Cladding Cladding
Cladding Cladding
External External landscape' landscape'
Hardscape Hardscape
Boundary Boundary Wall Wall
Foundation Foundation
Softscape Softscape Brickwork/RCC Brickwork/RCC Boundary Boundary Gate Gate
Basement
Third Fourth Terrace Basement Stilt First Second Third 10% 50% 90% 100% 10% 50% 90% 100% 10% 50% 90% Work 100%Progress 10% 50% 90% 100% 10%50% 50%90% 90% 100% 10%50% 50%90% 90% 100% 10%50% 50%90% 90% 100% Drawing 10% 100% 10% 100% 10% 100% 10% 50% 90% 100% 10% 50% 90% 100%
Drawing Work Progress Civil
MS/SS MS/SS
Stilt
First
Excavation
Civil
AntiTermite
Weekly Reports Of This Site Was My Assigned Task. Made 3D Structural To Show The Shift Of The Building Along With Demolition External Cladding External landscape'
PCC
Foundation/Footing/Raft
Foundation/Footing/Raft
Retaining Wall
Retaining Wall
Guniting
Guniting
Casting Columns
Casting Columns
Casting Roof Slab
Casting Roof Slab
Brickwork
Brickwork
Plaster
Plaster
Waterproofing Terrace
Waterproofing Terrace
Terrace PCC
Terrace PCC
Foundation for Services
Foundation for Services
Cladding
External Cladding
Cladding
Hardscape
External landscape'
Hardscape
Boundary Wall
Foundation
Foundation
Softscape
Brickwork/RCC Boundary Gate
Excavation AntiTermite
PCC
Softscape Boundary Wall
Second
MS/SS
Brickwork/RCC Boundary Gate
MS/SS
• Stilt Floor Slab is being casted with respect to new lift positions. • New Columns are being casted.
DELHI ONE
SITE PHOTOS AND PROCESS Delhi One
This Site Is A Commercial Project, Located In Noida. It Consists Of Various Hospitable Spaces, Gathering Spaces And Huge Auditorium.
Site Photos Page 1
26th 2021 10thJune, July, 2021
Tower D G2 Fire Staircase
Tower C G2 Corridor
6007
FLOORING PATTERN FOR THE AUDITORIUM
5431
17529
11470
LOBBY 4256 X 4091 EL
FHC
6058
EX
A
EL
CHW
A EL
A
1184
EL
8
5788 EL
EX KID'S.TOILET
5723
CHW
LIFT-20 2150X2450 ELE
11460
DESIGN FOR AIR CURTAINS-EXPLORATIONS
1
HORIZONTAL | L-Angle Boxed by 12mm Ply To Base Plate
3
VERTICAL | L-Angle To Base Plate
4
HORIZONTAL | L-Angle To Base Plate
6
HORIZONTAL | Equipment attached with L-Angle, Entirely Boxed by 12mm To Base Plate
PRODUCT DESIGNING With The Help Of Prerna Ma’am, I Was Working On Few Models Using Wooden Mosaics Pieces As An Element.
TABLE RUNNER
VASES
POUCH
ANGULAR TRAY
PERFORATED LAMP
TRAY
WALL ART