Skip to main content

Plant Shutdown & Turnaround Planning: Complete Guide & Checklist

Page 1

Read the original article on Sarom Global

Plant Shutdown and Turnaround Planning: Complete Guide and Checklist Short Summary Effective plant shutdown and turnaround planning starts well before the outage, with clear goals, a controlled scope, detailed work packs and early procurement. Most cost and schedule overruns can be traced back to issues such as scope creep, late materials, incomplete work packs and poor restart planning. A successful turnaround also depends on clear responsibilities across the asset owner, EPC contractors and onsite engineering and trade teams. By using readiness reviews, critical KPIs, FAT and SAT, and a structured post-shutdown review, teams can reduce execution and start-up risks while improving future outages.

Plant shutdown and turnaround planning is the structured process of preparing a facility for a planned outage, completing critical maintenance or upgrade work, and returning the plant to safe operation. For a major turnaround, planning commonly begins 12 to 24 months before the shutdown, although the lead time varies with plant complexity, scope and long-lead procurement. Why so much preparation? Because most turnaround delays are created before the plant ever stops. A late material, a poor work pack or an uncontrolled scope change can become a critical-path problem once the outage begins. Quick answer: Plant shutdown and turnaround planning is the process of preparing for a planned plant outage. It covers scope, cost, schedule, materials, contractors, safety and start-up, followed by a review after restart. Many large turnarounds need 12 to 24 months of planning.

In this guide Why Turnarounds Overrun Budget and Schedule Turnaround Planning Timeline Planning Phases Explained How Do You Decide What Goes in the Turnaround Scope? Roles: Owner, EPC, and Onsite Trades What Is the Difference Between FAT and SAT in a Plant Turnaround? A Pre-Shutdown Checklist Which Turnaround KPIs Should You Track? Post-Shutdown Review When Should You Use an Owner’s Engineer for a Turnaround? Frequently Asked Questions Plan Your Next Turnaround

Sarom Global | Plant Shutdown and Turnaround Planning

Page 1


Why Turnarounds Overrun Budget and Schedule Most overruns come from weak planning, not bad luck on the day. These are the six most common causes.

1. Scope creep. The work list keeps growing after it should be locked. 2. Unplanned discovery work. Crews open equipment and find corrosion, cracks or worn parts, with no time or budget set aside.

3. Late materials. Long-lead valves, exchanger bundles or alloy pipe arrive after they are needed. 4. Poor work-pack quality. Jobs reach the field without confirmed materials, access, permits or tools.

5. Unclear decision rights. The owner, contractors and trades are not sure who approves what. 6. Weak start-up planning. Teams focus on taking the plant apart and forget the restart. From the field: Scope changes A scope change rarely affects one job alone. Adding a valve replacement may also need scaffolding, new isolations, lifting equipment, extra permits and a revised commissioning sequence. Check the change across every affected workstream before you approve it.

Turnaround Planning Timeline Here is a typical plant shutdown and turnaround planning timeline for a large outage. Note that planning and procurement run in parallel. Timing

Primary focus

18 to 24 months out

Strategy and business case

12 to 18 months out

Scope development

9 to 12 months out

Scope freeze

6 to 12 months out

Detailed planning and work packs

6 to 12 months out

Procurement and contractor engagement

1 to 3 months out

Readiness reviews

Outage

Execution, commissioning and start-up

1 to 3 months after

Review and lessons learned

Planning Phases Explained A good turnaround programme follows a clear sequence. Each phase has its own goal and its own sign-off.

Sarom Global | Plant Shutdown and Turnaround Planning

Page 2


1. Strategy and Business Case Decide why the turnaround is needed: inspection, reliability work, a capacity upgrade, or all three. Set targets for safety, cost, duration and performance after restart. Name a turnaround manager and a core team. Decision rule: If the team cannot state the purpose of the outage in one or two sentences, the strategy is not ready.

2. Scope Development Collect work requests from operations, maintenance, inspection and projects. Challenge each one using inspection data, failure history and risk-based inspection results. Decision rule: If a job can be done safely while the plant is running, challenge it before adding it to the outage.

3. Scope Freeze Lock the scope on an agreed date. After that, every new job goes through a formal change process. Decision rule: After scope freeze, every addition must show its impact on cost, duration, safety and the critical path before approval.

4. Detailed Planning and Scheduling Break every job into work packs listing steps, crew, hours, tools, permits, isolations and materials. Build the schedule, find the critical path and add a discovery allowance based on past outages. From the field: Work-pack readiness Engineering completion does not mean a job is ready to execute. The crew still needs the right materials, access, isolations, tools, permits and work instructions. Treat a work pack as ready only when all of these are confirmed.

5. Procurement and Contractor Engagement Order long-lead materials against required-on-site dates, not just order dates. Test critical equipment before it ships with a Factory Acceptance Test (FAT). A fault found at the maker’s workshop costs far less than one found mid-outage. Book contractors, cranes, scaffolding and specialist trades early.

6. Pre-Shutdown Readiness Hold formal readiness reviews. Confirm that permits, isolations, safety plans, materials and people are in place. Walk the plant with the crews who will do the work.

7. Execution, Start-Up and Handover Hold daily progress meetings and track work against the critical path. Before restart, run a Site Acceptance Test (SAT) on new or modified systems to confirm they work in their real setting. From the field: Restart Start-up delays often trace back to small open items, such as an uncalibrated instrument, an open punch item or a valve that was never stroke-tested. Review the restart sequence before the shutdown begins, not in the final shift.

Sarom Global | Plant Shutdown and Turnaround Planning

Page 3


How Do You Decide What Goes in the Turnaround Scope? Not every maintenance request belongs in the outage. A job belongs in scope when it:

• needs the equipment isolated or the plant stopped • creates a serious safety, integrity or production risk if deferred • can be done much more efficiently during the outage Use a simple priority matrix to rank the rest. Priority

Typical work

Decision

Critical

Safety-critical, statutory or production-critical

Must be in scope

High

Significant reliability or integrity risk

Include unless a safe alternative exists

Medium

Efficiency or reliability improvement

Include only if resources allow

Low

Can be safely deferred

Move to routine maintenance

This matrix is a planning aid, not a substitute for engineering judgement, safety requirements or legal obligations. In Australia, AS/NZS 3788 provides guidance for the in-service inspection of pressure equipment. Sites may also use risk-based inspection methods such as API RP 580, depending on their equipment, risk profile and applicable requirements.

Roles: Owner, EPC, and Onsite Trades Clear roles are one of the simplest ways to protect a turnaround. The asset owner is responsible for the turnaround as a whole. The owner sets goals, approves scope and budget, and makes the final call on risk. A single turnaround manager on the owner’s side should chair readiness reviews and control changes. The EPC contractor (engineering, procurement and construction) is often used when the outage includes new equipment, upgrades or tie-ins. The EPC team should join during scope development, not in the final weeks. Onsite engineers and trades do the physical work. When fitters, welders, electricians and instrument technicians review work packs early, they spot access problems and missing tools that planners may miss. Sarom Global’s Onsite Engineering and Trades team supplies engineers, technologists and tradespeople for shutdowns and turnarounds.

Sarom Global | Plant Shutdown and Turnaround Planning

Page 4


What Is the Difference Between FAT and SAT in a Plant Turnaround? A FAT checks equipment before it leaves the supplier. A SAT checks that the installed equipment works correctly at the plant. FAT

SAT

Full name

Factory Acceptance Test

Site Acceptance Test

When

Before equipment leaves the supplier

After installation on site

What it checks

Build quality and compliance with the specification

Installation and operation on site

Setting

Controlled factory environment

Real operating environment

Both reduce the risk of start-up delays, so plan both into the turnaround schedule.

A Pre-Shutdown Checklist Use this checklist in the months before your outage. Scope and schedule ☐ Turnaround goals for safety, cost, duration and performance approved ☐ Scope freeze date approved and met ☐ All post-freeze changes documented with cost, schedule and risk impact ☐ Critical path reviewed by planning, operations and trades ☐ Discovery allowance included in time and budget Materials and equipment ☐ Long-lead materials ordered against required-on-site dates ☐ FAT complete for critical valves, skids and control systems ☐ Materials physically on site, checked and staged near the work ☐ Crane, scaffold and access plans confirmed People and work packs ☐ Critical work packs reviewed by the crews who will do the work ☐ Decision rights between owner, EPC and trades written down ☐ Contractors inducted and briefed ☐ Shift rosters and fatigue plans in place Safety and control ☐ Isolation boundaries verified in the field ☐ Permit-to-work plan and high-risk job assessments complete ☐ Alarm and control system changes documented and reviewed Commissioning and restart ☐ Mechanical completion criteria defined ☐ Commissioning sequence agreed

Sarom Global | Plant Shutdown and Turnaround Planning

Page 5


☐ Punch-list ownership assigned ☐ Critical punch items closed before start-up ☐ SAT plans ready for new or modified systems ☐ Restart sequence reviewed before shutdown begins ☐ Baseline plant performance data recorded

A Practical 5-Point Turnaround Readiness Test Before you commit to a shutdown date, ask five questions. If any answer is “no”, the outage is at risk.

1. Is the scope frozen? 2. Are critical materials physically on site? 3. Are work packs execution-ready? 4. Are isolations and permits defined? 5. Is the restart plan reviewed and tested?

Which Turnaround KPIs Should You Track? A KPI is only useful if it helps the turnaround manager make a decision. Stage

KPI

What it tells you

Before

Work-pack readiness

Whether jobs can actually be executed

Before

Material availability

Which jobs could stall

Before

Engineering completion

Whether design work will hold up planning

During

Critical-path variance

Whether the outage is drifting

During

Scope changes

Early warning of scope-control problems

During

Safety performance

Whether pace is putting people at risk

After

Actual duration vs plan

How the outage performed overall

After

Final cost vs budget

How accurate the estimate was

After

Start-up delay

How well restart was planned

Post-Shutdown Review The turnaround is not over when the plant restarts. The review is where your next outage gets better.

• Compare results with targets. Look at cost, duration, safety and scope completed against the plan.

• Check plant performance. Formal plant performance testing shows whether the outage delivered the gains you wanted.

• Record discovery work. Note what crews found inside equipment. This sets a more realistic allowance next time.

• Investigate failures. A forensic failure analysis finds the root cause of any failure so it does not return.

Sarom Global | Plant Shutdown and Turnaround Planning

Page 6


• Assign lessons learned. Give each lesson an owner and build it into the next turnaround planning cycle. Otherwise it becomes a document nobody reads.

• Close out records. Update drawings, equipment records and maintenance plans.

When Should You Use an Owner’s Engineer for a Turnaround? External support is most useful when internal teams are stretched or the outage carries high risk. Consider an owner’s engineer when:

• the scope includes complex modifications or major capital works • several contractors must work in the same areas • specialist testing such as FAT and SAT is needed • commissioning and start-up are complex • the outage has little schedule contingency An owner’s engineer acts on your behalf, reviews designs, manages vendors and checks that contractors deliver what was agreed. This keeps the turnaround tied to your goals, not a contractor’s.

Frequently Asked Questions What is the difference between a shutdown and a turnaround? A shutdown is any time a plant, or part of it, stops running. It can be planned or unplanned. A turnaround is a large, planned shutdown where major maintenance, inspection and upgrade work is done together. Every turnaround is a shutdown, but not every shutdown is a turnaround. How far in advance should a turnaround be planned? Many large turnarounds need 12 to 24 months of planning, and complex outages may need more. Smaller shutdowns may need only a few months. Starting plant shutdown and turnaround planning late is a common cause of overruns. What causes turnaround overruns? The main causes are scope creep, unplanned discovery work, late materials, poor work packs, unclear decision rights and weak start-up planning. An early scope freeze, a discovery allowance, early ordering, FAT and SAT, and clear roles reduce these risks. Who manages a plant turnaround? The asset owner is responsible and usually appoints a turnaround manager to lead it. That manager works with an owner’s engineer, EPC contractors and onsite trade crews while keeping control of scope, budget, schedule and risk. How do you control scope creep during a shutdown? Set a firm scope freeze date. After that, every new job needs a formal change request showing its cost, schedule, safety and critical-path impact. Only the turnaround manager or a change board should approve it. What is a turnaround readiness review? A readiness review is a formal check held before the outage. It confirms that scope, work packs, materials, permits, isolations, people and the restart plan are ready. Gaps are fixed, or the risk is formally accepted, before the shutdown date is confirmed.

Sarom Global | Plant Shutdown and Turnaround Planning

Page 7


Plan Your Next Turnaround Good plant shutdown and turnaround planning comes down to a few basics. A clear purpose, a firm scope freeze, tested equipment, defined roles and an honest review make the difference between an outage that runs to plan and one that does not. Planning a major plant shutdown or turnaround? Sarom Global supports asset owners across Australia, EMEA, Asia Pacific and the Americas with owner’s engineering, onsite engineering and trades, FAT and SAT, commissioning support and forensic failure analysis. Talk to our team about the engineering and execution support your next outage needs, or explore our onsite engineering and trades services.

Our Services Owners Engineering Process Engineering Process Control Plant Optimization With POSy-System Alarm Management Plant Digitalisation Instrumentation & Control Onsite Engineering and Trades Factory Acceptance Testing (FAT) Site Acceptance Testing (SAT) Forensic Failure Analysis

Our Products Process Plant Design and Construction Control Valves ESD Valves IoT IO Modules Power Factor Correction Pasteurisers

Sarom Global | Plant Shutdown and Turnaround Planning

Sarom Global Phone: +61 2 8317 5089 Email: info@saromglobal.com Web: www.saromglobal.com Address: Australia ACN 648 693 823 ABN 47 648 693 823 Home | Services | Products | Blog | Contact Us

Page 8


Turn static files into dynamic content formats.

Create a flipbook
Plant Shutdown & Turnaround Planning: Complete Guide & Checklist by Sarom Global - Issuu