Exhibit G (Seminoe FLA)

Page 1

FERC Project No. 14787 Black Canyon Hydro, LLC January 2023

Final License Application
Exhibit G: Project Maps Seminoe Pumped Storage Project

1.0 Project Maps 1

– Exhibit G
January 2023 | i
Final License Application
Seminoe Pumped Storage Project
Contents

1.0 Project Maps

Project maps are attached hereto as follows:

Map Number Title

G-1 Project Location Map Exhibit G-1

G-2 Project Boundary Map Exhibit G-2

G-3 Project Boundary Map Exhibit G-3

G-4 Project Boundary Map Exhibit G-4

G-5 Project Boundary Map Exhibit G-5

G-6 Project Boundary Map Exhibit G-6

G-7 Project Boundary Map Exhibit G-7

G-8 Project Boundary Map Exhibit G-8

– Exhibit G
January 2023 | 1
Final License Application
Seminoe Pumped Storage Project

20 28

Reference Point Existing Dams River / Stream Transmission Line Substation Project Boundary Township Section Lake/Reservoir

Bennett Mountain WSA Road Type US Highway State Highway County Road BLM Road Light Duty Road Rough bladed/2 track

N
E 1,548,835.7 N 937,811.5 1,481,884.4 N 874,989.8 E 1,454,636.3 06-103 06-E-1 06-291 06-E-1 06-102 06-351 06-115 06-102 06-102 BLM3137 06-351 06-E-1 06-191 06-121 BLM3108 06-102 US287 SR77 06-270 BLM3109 BLM3115 Kortes Reservoir Seminoe Reservoir Seminoe Reservoir Morgan C e k Cameron Creek LongCreek HamiltonCr ek MeadowCreek SmthCreek Co t tonwoodCreek Mdde D ch Sou h Fo k Sage C eek Ea t Fo kThomasCreek BullCreek Co onwoodC eek Hu t Creek MedcineBowRve Sage Cr ek Beave C eek FrstRanchCreek DryC eek Roaring Creek G r nne l l C r e e k Beaver JimmyCreek Ea BullC r e e k SledgeCreek RobinsonCreek Toublesome Creek Au inCreek CottonwoodCreek NorthPatteRve CorralCreek Ca on Ceek RockCreek D cutyCreek s nbyCreek Nelson D t c h SouthFokQuealy Creek SaintMarys D t c h D y D ch NorthForkQuealyC e k HaySlough B Ditch TincupCreek Muddy C eek SipsC eek No h D ch Lost Cr ek SullivanCreek Sayo C eek CaveCreek Muddy Creek QuealyCreek SpringCreek SmithC ee Sprng C eek HillCreek SouthBeaverCreek ThomasCreek W wSp ng C eek DryCreek WestBullCreek OBrienCreek Bennett Mountain WSA 18 10 07 30 13 15 21 26 04 08 27 16 34 31 07 26 19 10 03 03 25 32 27 17 25 07 08 05 01 07 24 34 12 31 09 02 35 29 29 20 05 05 22 20 05 24 09 32 33 20 10 29 09 33 14 03 26 27 18 14 05 14 22 12 04 23 01 35 10 12 35 31 36 07 24 11 28 07 04 27 08 36 09 17 16 22 19 34 08 18 20 33 28 13 20 06 11 03 14 08 34 18 22 34 15 10 04 17 32 12 23 19 17 32 07 21 29 16 11 08 10 20 01 26 32 25 28 30 17 36 22 29 04 36 19 18 36 36 29 14 24 25 33 11 02 19 25 24 24 26 16 04 29 22 21 15 02 32 06 11 35 04 27 35 09
05
18
27
06
15
17
14
27
07
17
18 22 16 14 23 19 13 25 32 24 11 33 14 33 13 10 11 20 11 13 13 36 33 24 35 11 18 33 09 28 06 18 12 33 08 33 07 05 04 08 16 02 21 22 23 11 21 09 11 16 T022N R080W T023N R080W T026N - R080W T023N R085W T023N R081W T022NR079W T022N R085W T023N R079W T025N R081W T026N R079W T026N - R083W T025N R083W T022N - R083W T025N - R084W T024N R082W T026N - R081W T022N R082W T026N R082W T023N R082W T024NR079W T024N R081W T023N - R083W T026N - R084W T025N R082W T024N - R080W T022N - R081W T023N R084W T024N R084W T022N R084W T025N - R079W T025N R080W T024N R083W Seminoe Dam Kortes Dam G-2 G-3 G-4 G-5 G-6 G-7 G-8 FERC Drawing Number: P-14787 P-14787 G-1 Date: January 5, 2023 CARBON COUNTY, WYOMING SEMINOE PUMPED STORAGE PROJECT FERC LICENSE NO. P-14787 PROJECT LOCATION MAP EXHIBIT G-1 Coordinate System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011 Units: Foot US Total Federal Acres = 879.04 Total Transmission Line Federal Acres = 666.10 Total Non-Transmission Line Federal Acres = 212.94 Total Project Boundary Acres = 1,522.00 LEGEND Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map.
2023 0 1 2 3 Miles
875,699.5
29 36
13 36 20 28 03 21 32
34 09 11 09 33 30 13 11 07 12 18 13
08 02 25 17 03 35 03 12 31 08 04 35 01 19
35
34 21
23
10
02 10 30 23 08 01
25 29 05 02 26 18 04 25 19 05 02 08 16 01 22 08 05 17 30 35 05 07 09 03 16 31 30 20 16 36 31
21 23 25 32 16 21 16 24 22 02 25 06 31 08 07 30 25 27 12 02 27 19 14 36 27 22 10 09 18 31 01 32 18 21 34 33 09 10 17 02 32 11 14 27 06 34 18 17 05 07 06 30 03 16 02 12
08 20 14 31 03 34 16 31 04 03 06 36 21 01 25 21 08 14 01 15 19 26 28 23 15 20 25 01 28 10 21 21 06 06 31 15 36 32 02 10 05 05 07 12 13 33 23 08 28 15 12 03 28 24 02 23 24 30 36 24 12 26 23 30 19 06 06 19 18 04 15 15 31 19 36 36 22 17 26 07 09 29 27 24 21 12 26 07 17 23 14 29 20 35 33 20 01 31 35 33 24 20 01 06 34 27 26 03 13 34 30 04 17 13 15 13 11 29 30 09 23 18 30 26 28 15 05 25 08 34 28 11 18 12 04 13 31 34 03 24 06 03 14 09 12 36 15 14 27 14 07 33 05 09 20 22 10 07 24 28 28 26 35 14 28 12 27 22 13 19 35 05 32 06 29 21 22 12 15 30 28 29 11 06 03 19 19 31 23 29 01 21 04 13 04 05 36 26 21 13 34 11 06 25 29 03 28 36 07 23 07 22 29 05 23 32 28 12 17 26 34 27 30 27 17 10 15 01 34 04 01 18 34 08 25 30 31 31 16 13 23 01 16 12 23 30 15 32 26 24 18 20 29 34 25 03 35 25 32 35 05 15 10 04 02 19 06 09 34 06 13 12 33 31 11 30 16 01 04 20 20 25 02 13 26 33 17 14 10 30 26 19 22 10 02 16 36 02 24 14 06 28 01 15 17 07 24 21 35 09 09 29 27 08 04 23 01 17 23 18 02 28 32 19 26 32 32 11 20 16 35 03 32 18 22 06 24 15 35 31 15 16 35 17 21 03 26 27 30 14 09 19 10 02 33 22 22 33 10
By………………………………… Date …………………. January 5,
Transmission Line Corridor Project Boundary Access Road Project Boundary Access Road Project Boundary Pump Station/Powerhouse Project Boundary Tunnel Project Boundary Access Road Project Boundary Tunnel Project Boundary Upper Reservoir Project Boundary Waterway Tunnel Project Boundary Waterway Tunnel Project Boundary N 937,808.6 E 1,429,208.6 N 927,341.3 E 1,429,328.3 N 927,303.2 E 1,445,069.0 06-351 06-E-1 06-E-1 BLM3109 Kortes Reservoir Seminoe Reservoir Mo g n C ee DryLakeCeek NorthPlatteRiver Lost Creek Ham on C eek Bennett Mountain WSA 09 17 33 08 10 01 05 12 34 02 03 16 36 32 15 35 13 14 11 04 T025N R084W T026N R084W Seminoe Dam Kortes Dam FERC Drawing Number: P-14787 P-14787
Date:
SEMINOE
PROJECT BOUNDARY MAP EXHIBIT G-2
Units:
Total
Total
Total
LEGEND
0 1,000 2,000 3,000 Feet
Point Existing
River / Stream Transmission Line Substation
Private
(At original document size of 22x34) Scale: 1:12,000
Index Map G-2 G-3 G-4 G-5 G-6 G-7 G-8
G-2
January 5, 2023 CARBON COUNTY, WYOMING
PUMPED STORAGE PROJECT FERC LICENSE NO. P14787
Coordinate System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011
Foot US Total Federal Acres = 879.04
Transmission Line Federal Acres = 666.10
Non-Transmission Line Federal Acres = 212.94
Project Boundary Acres = 1,522.00
Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map. By………………………………… Date …………………. January 5, 2023
Reference
Dams
Project Boundary Township Section Lake/Reservoir Bennett Mountain WSA Ownership Type
Federal State Road Type County Road BLM Road Light Duty Road Rough bladed/2 track

Ownership Type Private Federal State Road Type Light Duty Road Rough bladed/2 track

Total Federal Acres = 879.04

Total Transmission Line Federal Acres = 666.10

Total Non-Transmission Line Federal Acres = 212.94 Total Project Boundary Acres = 1,522.00

Coordinate System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011 Units: Foot US

Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map.

By………………………………… Date …………………. January 5, 2023

N
Seminoe Reservoir Co onwoodCreek Beave J mm Creek Sayo C eek Caton C eek SipsC eek Bennett Mountain WSA 21 27 19 33 34 16 28 17 30 15 18 31 29 32 20 22 T025N R083W T025N - R084W T024N R084W T024N R083W FERC Drawing Number: P-14787
CARBON COUNTY, WYOMING SEMINOE PUMPED STORAGE PROJECT FERC LICENSE NO. P14787 PROJECT BOUNDARY MAP EXHIBIT G-3
Index Map G-2 G-3 G-4 G-5 G-6 G-7 G-8 Transmission Line Corridor Project Boundary N 922,102.7 E 1,455,577.7
911,593.2 E 1,455,538.8 N 911,467.9 E 1,471,094.7
P-14787 G-3 Date: January 5, 2023
LEGEND
0 1,000 2,000 3,000 Feet
Reference Point River / Stream Transmission Line Project Boundary Township Section Lake/Reservoir Bennett Mountain WSA (At original document size of 22x34) Scale: 1:12,000

Ownership Type Private Federal State Road Type County Road Light Duty Road Rough bladed/2 track

Total Federal Acres = 879.04

Total Transmission Line Federal Acres = 666.10

Total Non-Transmission Line Federal Acres = 212.94

Total Project Boundary Acres = 1,522.00

Coordinate System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011 Units: Foot US

Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map.

By………………………………… Date …………………. January 5, 2023

Transmission Line Corridor Project Boundary
N
06-291 Corral Creek Caon Cr ek Ea tFor Thomas Creek
Sprng C eek SaylorC eek Thomas Cr ek Au tnC eek 08 35 07 05 31 36 06 12 01 28 29 30 25 26 02 32 33 11 T025N R083W T024N R082W T025N R082W T024N R083W FERC Drawing Number: P-14787
CARBON COUNTY, WYOMING SEMINOE PUMPED STORAGE PROJECT FERC LICENSE NO.
PROJECT BOUNDARY MAP EXHIBIT G-4
Index Map G-2 G-3 G-4 G-5 G-6 G-7 G-8
N 911,782.0 E 1,492,587.0
896,139.8 E 1,475,416.2 N 911,599.8 E 1,476,479.1
SouthBeaverCreek
P-14787 G-4 Date: January 5, 2023
P14787
LEGEND
0 1,000 2,000 3,000 Feet
Reference Point River / Stream Transmission Line Project Boundary Township Section Lake/Reservoir (At original document size of 22x34) Scale: 1:12,000

By………………………………… Date …………………. January 5, 2023

Index
Transmission Line Corridor Project Boundary Transmission Line Corridor Project Boundary
N 885,684.6 E 1,496,577.3 N 885,566.4 E 1,480,784.5 06-291 Seminoe Reservoir Medicine Bow River Au nCreek 26 25 08 14 17 07 24 29 18 19 20 12 28 23 21 30 09 13 16 11 T024N R082W T024N - R083W FERC Drawing Number: P-14787 P-14787 G-5 Date:
CARBON COUNTY, WYOMING SEMINOE PUMPED STORAGE PROJECT FERC LICENSE NO. P14787 PROJECT BOUNDARY MAP EXHIBIT G-5
Map G-2 G-3 G-4 G-5 G-6 G-7 G-8
N 896,228.7 E 1,501,760.8
January 5, 2023
LEGEND
Coordinate System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011 Units: Foot US Total Federal Acres = 879.04 Total Transmission Line Federal Acres = 666.10 Total Non-Transmission Line Federal Acres = 212.94 Total Project Boundary Acres = 1,522.00
Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map.
0 1,000 2,000 3,000 Feet
(At original document size of 22x34) Scale: 1:12,000
Reference Point River / Stream Transmission Line Project Boundary Township Section Lake/Reservoir Ownership Type Private Federal State Road Type County Road Light Duty Road Rough bladed/2 track

Total Transmission Line Federal Acres = 666.10

Total Non-Transmission Line Federal Acres = 212.94 Total Project Boundary Acres = 1,522.00

Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map.

By………………………………… Date …………………. January 5, 2023

Transmission
Project
N
E
N
E
D y
Dr C eek 25 27 07 29
11 12 23 10
30 24 26 08 13
22 15 14 T024N - R082W
FERC Drawing Number: P-14787
CARBON COUNTY, WYOMING SEMINOE PUMPED STORAGE PROJECT FERC LICENSE NO. P14787 PROJECT BOUNDARY MAP EXHIBIT G-6
Index Map G-2 G-3 G-4 G-5 G-6 G-7 G-8
Line Corridor
Boundary N 896,106.6 E 1,507,038.4
885,670.6
1,507,109.6
885,860.4
1,522,425.5 06-191 06-291
C ek TroubesomeCreek
19
20
17 18
T024N - R081W
P-14787 G-6 Date: January 5, 2023
Coordinate System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011 Units: Foot US Total Federal Acres = 879.04
LEGEND
0 1,000 2,000 3,000 Feet
(At original document size of 22x34) Scale: 1:12,000
Reference Point River / Stream Transmission Line Project Boundary Township Section Lake/Reservoir Ownership Type Private Federal State Road Type County Road Light Duty Road Rough bladed/2 track

Ownership Type Private Federal State Road Type County Road Light Duty Road Rough bladed/2 track

Total Transmission Line Federal Acres = 666.10

Total Non-Transmission Line Federal Acres = 212.94 Total Project Boundary Acres = 1,522.00

Coordinate

Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map.

By………………………………… Date …………………. January 5, 2023

Index Map
Transmission
Corridor Project Boundary N 896,594.4 E 1,532,648.8 N 886,025.1 E 1,532,800.1 N 886,194.0 E 1,543,422.9 06-291 06-191 06-270 DyCreek Me c ne Bow Rve DryCreek TroublesomeCeek DyC eek 09 15 10 25 21 30 14 19 28 24 12 07 26 18 13 23 16 27 22 11 T024N - R081W
FERC Drawing Number: P-14787 P-14787 G-7 Date:
CARBON COUNTY, WYOMING SEMINOE PUMPED STORAGE PROJECT FERC LICENSE NO. P14787 PROJECT BOUNDARY MAP EXHIBIT G-7
G-2 G-3 G-4 G-5 G-6 G-7 G-8
Line
T024N - R080W
January 5, 2023
System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011 Units: Foot US Total Federal Acres = 879.04
LEGEND
0 1,000 2,000 3,000 Feet
Reference Point River / Stream Transmission Line Project Boundary Township Section Lake/Reservoir (At original document size of 22x34) Scale: 1:12,000

Reference Point River / Stream

Ownership Type Private Federal State Road Type County Road Light Duty Road Rough bladed/2 track

Total Transmission Line Federal Acres = 666.10 Total Non-Transmission Line Federal Acres = 212.94 Total Project Boundary Acres = 1,522.00

Surveyors Statement: hereby state that the Seminoe Pumped Storage Project Boundary delineation and coordinates shown on this Exhibit “G” were developed from Wyoming E Central State Plane Coordinates to NAD83. The delineation as shown on this Exhibit “G” was developed within reasonable accuracies (+/- 40 feet) as required in 18CFR4.41 to show the correct geographical location on the referenced topographical map.

By………………………………… Date …………………. January 5, 2023

Index Map
AEOLUS Substation N
E
N
E
N
E
06-270 06-121 DryCreek MedcneBowRiver Sledge Creek Medcne Bow Rver Diff utyC eek 27 24 29 35 21 17 16 23 15 26 33 13 14 34 28 32 22 20 T023N - R080W T024N R080W FERC Drawing Number: P-14787 P-14787 G-8 Date:
CARBON COUNTY, WYOMING SEMINOE PUMPED STORAGE PROJECT FERC LICENSE NO. P14787 PROJECT BOUNDARY MAP EXHIBIT G-8
G-2 G-3 G-4 G-5 G-6 G-7 G-8 Transmission Line Corridor Project Boundary
881,733.6
1,575,449.0
892,059.2
1,559,494.7
881,408.5
1,559,596.7
January 5, 2023
Coordinate System: NAD 1983 2011 StatePlane Wyoming E Central FIPS 4902 Ft US Projection: Transverse Mercator Datum: NAD 1983 2011 Units: Foot US Total Federal Acres = 879.04
LEGEND
0 1,000 2,000 3,000 Feet
Transmission Line Substation Project Boundary Township Section Lake/Reservoir (At original document size of 22x34) Scale: 1:12,000

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Exhibit G (Seminoe FLA) by rPlusEnergies - Issuu