4.2.3 Water Conduits
• Upper reservoir power intake; • Commence low-pressure headrace tunnel; • Low-pressure head gate shaft; and, • Excavate shaft and surge facilities.
4.2.4 Power Facilities
• Portal for and commencement of excavation of the main access tunnel to the power facilities.
4.2.5 Upper Reservoir
• Site preparation and grubbing; • Rock excavation; • Grouting; • Foundation preparation; • Produce and stockpile aggregate; • Begin RCC (Roller Compacted Concrete) placement; and, • Commence geomembrane lining.
4.2.6 Transmission Line
• Commencement of excavation of the cable shaft from surface; • Commencement of tower installation; and, • Commencement of wire stringing.
4.3 Second year of Construction
During the second year of construction, the following work will be completed.
4.3.1 Roads
• Improvement of the access road at lower gate shaft; and, • Upgrade road to surge shaft access portal.
4.3.2 Water Conduits
• Complete upper reservoir power intake; • Complete low-pressure headrace tunnel; • Construct low-pressure steel penstock; • Complete shaft and surge facilities; • Commence tailrace tunnel; and, • Commence downstream gate shaft