Final License Application
Exhibit C: Proposed Construction
Schedule
White Pine Pumped Storage Project
FERC Project No. 14851
White Pine Waterpower, LLC
February 2023
Final License Application – Exhibit C White Pine Pumped Storage Project February 2023 | i Contents 1.0 Proposed Construction Schedule 1 1.1 First Year of Construction (2025) 2 1.2 Second Year of Construction (2026) 2 1.3 Third Year of Construction (2027) ............................................................................................. 3 1.4 Fourth Year of Construction (2028) 3 1.5 Fifth, Sixth, and Seventh Year of Construction (2029 to 2031) ................................................ 3 1.6 Commercial Operation 3 2.0 Previously Constructed Facilities 4 3.0 White Pine Pumped Storage Project Execution Schedule .................................................................. 5 Tables Table 1.0-1. Project Milestones 1
Final License Application – Exhibit C
White Pine Pumped Storage Project
List of Acronyms
BLM Bureau of Land Management
ECI Early Contractor involvement
EPC Engineering, Procurement, and Construction
FERC Federal Energy Regulatory Commission
FLA Final License Application
NTP Notice to Proceed
OEM Original Equipment Manufacturer
RFQ Request for Qualifications
ROW Right of Way
WPW White Pine Waterpower, LLC
February
2023 | ii
1.0 Proposed Construction Schedule
Final License Application – Exhibit C White Pine Pumped Storage Project February 2023 |
The White Pine Pumped Storage Project (Project) milestones are summarized in Table 1.0-1 and the proposed construction execution schedule is attached in Section 3.0.
1
Milestone Date FERC approved Board of Consultant Onboarded 09-Feb-2024 Original equipment manufacturer (OEM) – Notice to Proceed (NTP) 13-Feb-2024 OEM – Commence model development/design of major pumping/generating equipment 14-Feb-2024 Early Works (Access road, wellfield and water conveyance, laydown area, utility lines relocation etc.) NTP 09-Aug-2024 FERC License Issued 06-Feb 2025 FERC Approval of Quality Control Inspection Plan (QCIP) 03-Mar 2025 BLM Issues ROW Grant 13-Mar 2025 Early Works Start Construction 14-Mar-2025 Early Works Upper Hillside Complete 30-May-2025 Main Civil Works NTP 05-Jun-2025 Main Civil Works Start Construction 30-Sep-2025 Transformer Cavern Civil Complete 16-Sep-2027 Main Access Tunnel Ready to receive major Equipment 31-Jan-2028 Lower Reservoir Ready for Filling 20-Apr-2028 Powerhouse Cavern Last Draft Tube Pit complete 04-Aug-2028 Headrace Shaft Complete 27-Dec-2028 Upper Reservoir Ready for Filling 22-Feb-2029 Tailrace ready for water up 17-Oct-2029 Ready to Commission First Pump/Turbine (# 3) 11-Nov-2030 Commission Pump/Turbine # 3 05-Feb-2031
Table 1.0-1. Project Milestones
Final License Application – Exhibit C White Pine Pumped Storage Project
All Three Units Commissioned (Order is 3,2,1)
Final Project Completion
Activities associated with each year of construction are summarized below.
1.1 First Year of Construction (2025)
The first year of construction will consist of:
• Mobilization of construction plant, equipment, and labor
• Water Source – Site preparation, water pipeline, and wellfield installation
• Access Roads and Laydowns – Construct access roads and laydown areas
• Upper Reservoir – Start site preparation and excavation
• Lower Reservoir – Start site preparation and excavation
• Upper Hillside – Site preparation and excavation of cable and main access tunnel portals
• Tunnels – Start excavation and support of cable and main access tunnel
• Construction Power – Establish construction power connections
• Transmission Corridor – Site preparation, erect service power transmission line
1.2 Second Year of Construction (2026)
The second year of construction will consist of:
• Upper Reservoir – Complete excavation and embankments
• Lower Reservoir – Continue excavation, start embankments
• Tunnels – Continue cable and main access tunnel and start tailrace tunnel from Lower Reservoir
February 2023
| 2 Milestone Date Commission Pump/Turbine
30-Apr-2031 Commission
23-Jul-2031
# 2
Pump/Turbine # 1
23-Jul-2031
17-Sep-2031
1.3 Third Year of Construction (2027)
The third year of construction will consist of:
• Upper Reservoir – Continue excavation, start embankments
• Lower Reservoir – Complete embankments and start lining
• Tunnels – Continue cable tunnel; continue main access tunnel; start and complete excavation of construction access, headrace, high-pressure penstocks, and draft tube tunnels. Start tailrace tunnel and headrace shaft.
• Caverns – Start and complete transformer cavern and power tunnels and start powerhouse cavern
• Transmission Corridor – Start construction HV transmission line
1.4 Fourth Year of Construction (2028)
The fourth year of construction will consist of:
• Upper Reservoir – No works
• Lower Reservoir – Complete lining and inlet/outlet structure and start filling Lower Reservoir
• Tunnels – Complete all steel and concrete lining of the underground waterways with exception of the tailrace tunnel
• Caverns – Complete powerhouse cavern excavation
• Transmission Corridor – Continue construction HV transmission line
1.5 Fifth, Sixth, and Seventh Year of Construction (2029 to 2031)
The subsequent years of construction will consist of:
• Upper Reservoir – Complete lining, inlet/outlet structure and reservoir filling
• Continuing civil construction and installation of hydromechanical components
• Complete installation of the electrical and mechanical balance of plant
• Commissioning of the turbine units
• Transmission Corridor – Complete transmission line and switchyard
• Demobilization
1.6 Commercial Operation
The proposed approximate date for commercial operation is March 6, 2031.
C
2023 | 3
Final License Application – Exhibit
White Pine Pumped Storage Project February
Final License Application – Exhibit C
White Pine Pumped Storage Project
2.0 Previously Constructed Facilities
No portion of the proposed Project consists of previously constructed facilities
February 2023 |
4
Final License Application – Exhibit C
White Pine Pumped Storage Project
3.0 White Pine Pumped Storage Project Execution Schedule
February 2023 |
5