DEVELOPMENT REPORT™ | COMPLETE

Development Feasibility & Highest and Best Use McBain Farm • 13840 Loyalist Parkway • Prince Edward County

A rare rural-commercial holding with one clear development recommendation

PRIMARY DEVELOPMENT RECOMMENDATION

Best alignment with the property’s barn, farm setting, PEC visitor

STRONG SECONDARY

LONG-TERM OPTION VALUE

rural destination

future parcel

combined house and farm area

complementary zoning framework

Highway 33 + County Road 1

commercial, agri-tourism, frontage

Strategy C as selective long-term option value. Prepared for Debra Bain & Ken McLachlan • July 17, 2026 • Preliminary development advisory

1


REPORT NAVIGATION

Table of Contents A 30-page decision document moving from verified facts to strategy, economics and next steps.

Property Overview

3

Strategy B Program

17

Existing Conditions

4

Strategy B Financial Model

18

Three Listing Configurations

5

Strategy C - Commercial Frontage / Future Parcel

19

Confirmed Due Diligence

6

Strategy C Entitlement Economics

20

Title, Merger and Planning History

7

Municipal Fees and Charges

21

Official Plan Framework

8

Incentive and Financing Strategy

22

Zoning Framework

9

Building Code and Technical Feasibility

23

Policy-Supported Capacity

10

Approvals Strategy

24

Market and Local Precedents

11

Risk Management

25

Physical Capacity

12

Development Strategy Comparison

26

Strategy A - Highway Commercial / Rural Destination

13

Financial Comparison

27

Strategy A Program and Cost

14

Highest and Best Use Conclusion

28

Strategy A Financial Hurdle

15

Realtor Marketing Package

29

Strategy B - Agri-tourism / Event Barn

16

Recommended Next Steps and Basis of Analysis

30

Pages 3-12 establish the facts. Pages 13-20 test the three development paths. Pages 21-27 compare cost, approvals, risk and financial hurdles. Pages 28-30 convert the analysis into positioning and action.

RENDERING LOCATIONS :

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

2


PROPERTY OVERVIEW

A rare commercial frontage embedded in a 68-acre agricultural holding The value is created by the combination - not by the farmhouse, barn or farmland in isolation.

Item

Property fact

House parcel

PIN 550490325 • 0.513 ac • HC

Farm parcel

Servicing

Private drilled well and septic

Roads

Loyalist Parkway / Hwy 33 south; County Rd 1 north

✓ ✓ ✓ ✓ Existing Highway Commercial component. ✓ Substantial timber-frame barn and active farm. ✓ Two-road exposure and long frontage. ✓ Majority of land outside the Quinte-regulated area. ✓ Located within PEC's agricultural and visitor economy. Important planning distinction The HC zoning is associated with the house/frontage component. The barn and balance of the farm are treated primarily through the AG / on-

Sources: GeoWarehouse / legal descriptions supplied by the owners; County planning correspondence; Quinte aerial mapping; previous MLS package.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

3


EXISTING CONDITIONS

A strong physical platform - with key measurement and legal-use gaps The existing assets reduce start-up time, but the barnʼs legal use and private servicing must be established before public operation.

Farm / barn component 2012 sale

$480,000

Reported form

2-storey brick dwelling

Systems

Forced air, central air, drilled well, septic

2010 taxes

$2,366

Listing message

HC zoning presented as an opportunity driver

Land

Current legal clue

acres

2014 variance approved an accessory private garage

Core unknowns

$480K

Measured area, occupancy, structural/code

2014

historical 2012 house transaction

Barn arial exterior view

Rear addition and landscaped grounds

Modelling approach: no current appraisal, asking price or measured building areas were provided. The financial pages therefore test incremental development capital and operating hurdles - not current property value. The MLS floor-area field is internally inconsistent with the room schedule and is excluded from analysis.

Sources: 2012 MLS package; Committee of Adjustment Minutes, File A9 14; owner-provided property history. Historical sale price is not a current appraisal.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

4


THREE LIST ING CONFIGURAT IONS

One holding, three different buyer stories The best marketing strategy should preserve whole-property appeal while explaining consent and frontage upside without overstating approvals.

1

Whole holding / legacy estate One approximately 68.2-acre offering with the HC residence, barn and active farm presented as a single rural-commercial / agri-tourism platform. Widest immediate buyer story

2

Two-component consent strategy Explore consent to recreate separately marketable house/HC and farm/barn components. Exact boundaries, retained access and zoning would be determined through a defined application. Strongest flexibility option

3

Strategic frontage entitlement Test one carefully selected commercial frontage parcel not a speculative multi-lot subdivision - through County and road-authority pre-consultation. Long-term option value

Title caution The parcels still appear separately in mapping and assessment records,

HIGHWAY 33 / HOUSE + BARN

Sources: Mitchell Korman legal correspondence, May 5, 2026; County and GeoWarehouse mapping.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

5


CONFIRMED DUE DILIGENCE

County, conservation, transportation and legal responses The report is anchored in property-specific correspondence - not only public maps or generic zoning summaries. MTO

confirmed Agricultural Area designation HC zoning at 13840 AG zoning on farm lands Defined proposal required for detailed review Site plan / consent / rezoning may

Access review scoped Only the southwest watercourse / wetland feature was identified. No mapped floodplain was noted. The majority of the holding is outside the regulated area.

MTO requested an HCMS preconsultation submission with a site plan showing the intended severance or development area before providing detailed access comments.

Low environmental screening risk

No concept approved or rejected

Property-specific written direction

ADDITIONAL CONFIRMED DIRECTION

✓ Lawyer advises the lands have merged in title. ✓ 2014 variance reduced the garage front-yard setback to 7.93 m. ✓ Quinte may still review drainage and stormwater on larger applications. ✓ Site Plan Control applies County-wide. ✓ Current survey, PINs and measured building data remain outstanding. Confidence rating High for designation, staff-confirmed zoning, merger advice and Quinte screening. Moderate for consent, legal barn use, access, servicing and final application pathway.

Written / recorded responses: Angela Buonamici, MCIP, RPP; Samantha Carney, Quinte Conservation; Allison Posthumus, MTO; Mitchell Korman, lawyer - May-June 2026.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

6


TITLE, MERGER AND PLANNING HISTORY

The 2014 approval materially changes the barn story

The property has a useful planning history - but it confirms private accessory use, not public event entitlement. CURRENT LAND COMPONENTS

2014 COMMITTEE OF ADJUSTMENT

reference

House / HC Farm / barn

Merger implication

Part 1, Plan 47R4943 PIN 550490326

File

A914

Applicant

Ken McLachlan

Decision

Approved November 19, 2014

Relief

Front yard 15 m to 7.93 m

Approved structure

Accessory private garage

Why this matters The current barn / entertainment building should not be represented as change-of-use, zoning, site plan, Building Code and Fire Code review.

Before any consent, sale structure or public use: obtain current parcel registers, an OLS survey / reference plans, the 2014 building

Sources: Committee of Adjustment Minutes, November 19, 2014, Motion COA 28 2014; legal correspondence; reference plans identified in owner records.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

7


OFFICIAL PLAN FRAMEWORK

Agriculture remains primary - diversified uses create the value-add The strongest concepts preserve the farm while using a limited portion of the property for commercial or visitor-economy activity.

Agricultural uses Crops, farm operation, farm buildings and normal farm practices remain the primary land use.

Agriculture-related uses Farm-dependent commercial or industrial uses that are directly related to farms in the area and benefit from proximity. Illustrative area test 67.714 acres is approximately 27.40 ha. A 2% on-farm diversified-use test equals approximately 0.55 ha / 1.35 acres, below the 1 ha policy cap. This is a screening calculation - not an approved development envelope.

POLICY SUPPORT

On-farm diversified uses Secondary, limited-area uses compatible with surrounding agriculture and maintaining the property's agricultural character.

POLICY LIMITS

Agriculture and agri-food activity Farm market / value-added farm use Rural tourism linked to the farm Secondary hospitality or event programming where criteria are met

✗ Conventional residential subdivision ✗ Unrelated commercial sprawl ✗ Farmland fragmentation without need ✗ Treating the entire 67.7 acres as a tourism site

Policy reality: the Agricultural designation can support the recommended concept, but only if the farm remains real, the diversified use remains secondary and limited in area, and private servicing / compatibility are demonstrated.

Sources: County Official Plan  2021, Agricultural Area policies; Ontario Guidelines for Permitted Uses in Prime Agricultural Areas; 2025 County planning rationale applying the 2% / 1 ha test.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

8


ZONING FRAMEWORK

Two zones create complementary - not interchangeable - opportunities The value is strongest when each zone performs the role it is best suited to support. 1 3 8 4 0 H O U S E / F R O N TAG E

FA R M / B A R N L A N D S

Core value

Existing commercial zoning basis

Likely concepts

Cafe / restaurant, retail, office, service, recreation, hospitality, farm-related commercial

Main limits

Small parcel, parking, septic, access, site plan, code

Best role

Commercial anchor and arrival address

Core value concepts

Farm and on-farm diversified-use Farm market, winery/cidery, value-added

Main limits

Secondary use, limited area, compatibility, servicing

Best role

Barn / farm experience and agricultural

CURRENT BY-LAW CONTEXT

NOT CONFIRMED AS-OF-RIGHT

Public event venue • full commercial use of the barn • expanded

2025 is now in effect. This Comprehensive Zoning By-law 140 report relies on the County's June 2026 property-specific HC / AG confirmation; current mapping, transition rules and exact zone standards must be confirmed before application.

Sources: County staff correspondence, June 2026; Comprehensive Zoning By-law 140 2025; County Planning 101 presentation, April 2026.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

9


POLIC Y-SU PPORT E D CAPAC IT Y

The acreage is large - the development envelope is selective The correct strategy concentrates visitor and commercial functions in a compact core and keeps the majority of the property agricultural.

ac

2 roads

ac

HC parcel confirmed

illustrative 2% OFDU test

existing Highway 33 driveway

operation 1 Residence, private accessory barn, active farming.

2 Low-risk repositioning Reuse HC house for a permitted commercial use with code / servicing / site plan review.

3 Farm-linked diversification Use a limited portion of the AG land for a compliant onfarm diversified program.

What can be supported now

4 Full entitlement Consent / rezoning / MTO review for a new commercial parcel or materially expanded use.

What is not an entitlement

A strong commercial / agri-tourism marketing story A defined HC adaptive-reuse investigation A farm-linked event / market / hospitality test A consent strategy for two separately marketable components

✗ Event occupancy or guest count ✗ Multiple frontage lots ✗ Commercial barn conversion ✗ New County Road 1 or Highway 33 entrance ✗ Septic capacity for public use

Capacity is controlled less by total acreage than by legal use, limited-area policy, private servicing, parking, fire access and road approval. These are the decision gates for the next phase.

All capacity statements are preliminary screening conclusions and remain subject to survey, zoning interpretation, servicing, code and agency approval.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

10


MARKET AND LOCAL PRECEDENTS

The concept is locally proven - the operating model still has to earn its place Prince Edward County already contains successful farm-based event and hospitality destinations, validating demand while raising the quality threshold.

326K

$37.8M

51.5%

4 seasons

accommodation spending

The Eddie 80 acres • up to 165 guests Historic Red Barn, commercial kitchen, renovated washrooms, accommodation and year-round events on Loyalist Parkway.

Compass Rose Restored two-storey barn, multiple heated/cooled spaces, bathrooms, bars and farm-to-table operations.

Farmhouse, barn, greenhouse, multiple ceremony sites and accommodation packages.

What they do not prove

What the comparables prove PEC supports premium rural destination demand. Successful venues combine indoor, outdoor, food, washroom and rain-plan infrastructure. Acreage alone is not the differentiator - execution and

✗ Approval of this property. ✗ Achievable event count or price. ✗ Septic, parking or code capacity. ✗ That a new venue can immediately match established operators.

Market implication: McBain Farm has a credible category precedent, but the winning position should be distinctive, farm-authentic and appropriately scaled - not a generic wedding barn.

Sources: PEC Economic Snapshot 2020 2024; 2025 Economic Snapshot; official venue websites for The Eddie, 100 Acre Wood and Compass Rose, accessed July 2026.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

11


PHYSICAL CAPACIT Y

The property is unconstrained at the macro scale but tight at the operating core The southern house/barn area is the logical development focus; access, parking and private servicing will determine its actual capacity. CONTROLLING SITE FACTORS

South development core House, barn and existing Highway 33 access create the logical first phase. Southwest natural feature Quinte's watercourse / wetland corridor must remain outside new structures and septic. North frontage County Road 1 creates option value, but a new entrance and AG fragmentation are untested. Active fields Large central and northern agricultural areas should remain operational.

Parking

Private servicing

Fire / waste movement

Event and restaurant demand can consume the limited southern core quickly.

Peak guest flows, commercial kitchens and public washrooms require a designflow study.

Apparatus access, forward movement, snow storage and waste service must be solved early.

Go / no-go test: before selecting a guest count or final use, commission a measured base plan and a preliminary servicing / access feasibility review. The property is physically promising, but the southern core is not unlimited.

Aerial source: Quinte Conservation GIS, June 16, 2026. Red and blue lines are approximate and for reference only.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

12


STRATEGY A

Highway Commercial / rural destination The lowest-risk development strategy uses the house as the commercial anchor and treats the barn as a complementary farmlinked asset.

HC existing zoning basis

mo

Owner-user

incremental capital range

Potential program

configuration

Cafe / restaurant • farm shop • boutique retail • gallery • office • wellness / retreat use • small hospitality • seasonal market.

House as the public-facing commercial anchor; barn as a complementary farm / event component; majority of fields retained in agriculture.

Strengths

Watch-outs

Uses existing HC zoning Strong highway visibility Lower operational complexity than a full venue Attractive to owner-users and lifestyle operators

Small HC parcel Code / accessibility / septic upgrades Parking may extend onto AG lands MTO review if access is intensified

Scenario A is a conce ptual business / development direction, not an approved use or construction program.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

13


ST RAT EGY A PROGRAM AND COST

Reuse first - expand only where the economics justify it The budget is concentrated in code, fit-out and private servicing rather than new building area. ILLUSTRATIVE DEVELOPMENT BUDGET

Item

OPERATING PROGRAM BY ASSET

Range

House / HC Guest arrival, dining / retail / professional use, accessible washroom, administration.

Planning / pre-consultation Concept / site / consultants

$55K - $75K

Code / fire / accessibility

$200K - $250K

Interior adaptive reuse

Barn / AG Private or farm-linked gatherings, workshops, market overflow, subject to legal-use confirmation.

Parking / signage / site works Contingency

$100K - $150K

Total

$880K - $1.17M

gate

Outdoor core Terrace, seasonal market, landscaped arrival, limited parking and service functions.

gate

Determine change of use, occupant load, barrier-free access and fire/life-safety scope.

Confirm water quality, well yield and septic design flow for the intended public use.

gate Submit the selected access / traffic concept through MTO HCMS preconsultation.

SRATEGY A – CONCEPTUAL RENDERING

Order-of-magnitude 2026 dollars; excludes land value, HST net of rebates, financing, operating start-up and extraordinary structural or environmental work.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

14


S TRATEGY A F I N A N C I A L H U R D L E

A viable owner-user concept needs roughly $235K-$312K in annual gross revenue This is a hurdle analysis - not a forecast. It shows the revenue level needed to justify the reported capital range. ILLUSTRATIVE CAPITAL TEST

Capital range

$880K - $1.17M

8% operating return target

$70K - $94K NOI

Gross sales at 30% margin

$50K - $67K debt service

DSCR gross at 30% margin

operator Owner-user who captures business profit, real-estate appreciation and lifestyle value.

Weakest structure Passive landlord relying only on base rent from a small rural commercial tenant.

$209K - $278K / yr

exit Stabilized operating business or turnkey destination marketed to a specialist buyer.

Interpretation: Strategy A does not need a huge sales volume to service moderate debt, but it still requires a real business plan. The property value cannot substitute for operating demand, and the existing house's small HC land base limits parking-intensive concepts.

Assumptions: 8% unlevered operating return; 30% NOI margin; 65% debt; 6.25% interest; 20-year amortization; 1.25 DSCR. Excludes land value, taxes, HST and owner compensation.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

15


S TRAT EGY B

Agri-tourism / event barn destination The property becomes a farm-based experience platform rather than a stand-alone event hall.

incremental capital

guest operating test - not entitlement

ac

mo

illustrative OFDU area test

Recommended operating concept A farm-authentic event and experience venue anchored by the existing barn, supported by seasonal events, a farm market / cafe component and active agricultural programming.

Why it leads Barn is the most distinctive physical asset Strongest PEC tourism / hospitality fit Best premium marketing story Preserves the agricultural setting

Why it is harder Assembly occupancy and code upgrades Parking, noise, lighting and neighbours Peak septic / water demand Operator execution and seasonality

STRATEGY B– CONCEPTUAL RENDERING

Strategy B is the highest and best development use because it combines planning alignment, a proven PEC category, the barn's

Guest counts are an operating test only. Final capacity depends on zoning, floor area, exits, septic, parking, fire access and approved occupant load.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

16


S T R A T E G Y B P R O G R A M AND COST

A destination venue requires more than a beautiful barn Successful rural venues combine guest experience, operational infrastructure and a legitimate farm relationship. ILLUSTRATIVE PROGRAM

LOCAL OPERATING BENCHMARKS

Existing barn

Event / workshop / gathering hall

Support wing

Catering prep, storage, staff, waste

Public amenities

Accessible washrooms, coat storage, arrival

Commercial layer

Farm cafe, market, seasonal retail, tastings

Agricultural layer

Fields, orchard / vineyard / crop programming

Rain plan

Indoor ceremony and protected service route

Code Assembly classification, structural loading, fire separations, exits, alarms / sprinklers and barrier-free access.

200 The Eddie barn capacity

100 Acre Wood indoor /

Compass Rose maximum

150 guest planning test, then let code, septic, parking Start with a 100

Operating plan

Farm test

Event calendar, catering model, alcohol, noise, staffing, waste, winter use and insurance.

Active farm relationship, limited-area calculation and agricultural compatibility.

This is a hurdle analysis - not a forecast. It shows the performance or value level needed to justify the reported capital range.

The winning program should be smaller and more curated than a generic banquet hall: premium farm experience, strong food / local-product integration, reliable rain plan and year-round shoulder-season uses.

Precedent capacities are from official venue websites and illustrate the PEC market category. They are not capacity evidence for the subject property.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

17


ST RAT EGY B FINANCIAL MODE L

The base operating case supports the strongest incremental return The model tests venue / experience revenue against the reported capital range; it is not a property appraisal or a guarantee of bookings. ILLUSTRATIVE OPERATING CASES

Case

Gross

Cash flow

Downside

$231K

$81K

Base

$438K

$175K

Upside

$670K

$302K

Cash flow means operating income before financing, property taxes, owner compensation, income tax and capital reserves.

6.7% - 8.5%

14.5% - 18.4%

24.9% - 31.7%

Debt-service test

program 24 larger events at $15K, 12 smaller events at $4K and $30K ancillary revenue. 60% operating-cost ratio.

At 65% financing, 6.25% and 20 years, base operating cash flow produces approximately 2.5x-3.2x DSCR before property tax and owner compensation.

Financial conclusion: Strategy B can support the reported capital range under a credible operating case, but the result is driven by the operator, event calendar and package pricing - not zoning alone.

Illustrative 2026-dollar model. Event fees are blended assumptions informed by public PEC venue indicators. Excludes land value, HST, property tax, financing fees, food/bar pass-through and owner compensation.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

18


S T R AT EGY C

Commercial frontage / future development parcel The concept has meaningful land-value upside, but the correct road and use must be selected before pre-consultation. TWO DIFFERENT FRONTAGE TESTS

Highway 33 adjacency Stronger relationship to the existing HC component and barn core; highest MTO access scrutiny.

Municipal road context may simplify road jurisdiction, but the concept cuts into productive AG land and has weaker zoning continuity. Recommended scope Test one commercial or agriculture-related frontage parcel only. Multiple

mo recommended test case

illustrative entitlement period

High approval and access risk

Strategy C is best treated as option value: advance it only if a defined buyer / operator need and a preliminary value test justify the planning and access cost. STRATEGY C – CONCEPTUAL RENDERING

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

19


ECONOMICS SSTRATEGY C E N A R I O C3 ENTITLEMENT ENTITLEMEN T ECONOMICS

The approval must create at least $600K-$850K of new value to be compelling Future building construction is a separate several-million-dollar decision and is not included in the entitlement budget. ILLUSTRATIVE ENTITLEMENT BUDGET

Survey / base plan

$20K - $35K

Planning / pre-consultation

$45K - $75K

Consent / ZBA / site plan

$75K - $100K

Road / traffic review

$45K - $75K

Civil / septic / drainage

$60K - $90K

Legal / reference plan

$50K - $75K

Contingency

$60K - $75K

Total

$355K - $525K

This is a hurdle analysis - not a forecast. It shows the performance or value level needed to justify the reported capital range.

Minimum uplift $444K - $656K above the underlying value just to preserve a 20% margin on entitlement spend.

target Approximately $600K - $850K of incremental value after allowance for carry, overruns and sale friction.

exit Entitle and sell, or pre-negotiate with a specific commercial / farm-related end user.

Decision rule: do not spend $355K - $525K chasing a generic parcel. Advance Scenario C only after a broker-supported value opinion

The 20% margin threshold equals entitlement cost divided by 80%. Practical target adds preliminary carry, cost-overrun and disposition allowances.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

20


MU NI CIPAL FE E S A ND CHAR GES

Application fees are manageable - consultant and infrastructure costs are decisive The Countyʼs 2026 forms clarify the cash required to start; every project remains subject to external agency and cost-recovery invoices. 2026 COUNTY PLANNING FEES

COSTS OUTSIDE THE FEE TABLE

Process

Current municipal cash requirement

One new lot + rezoning

$9,526 total due

Technical consent + rezoning

$9,241 total due

Rezoning only

$5,628 total due

Site plan pre-consultation Minor site plan Major site plan

• OLS survey / reference plan • Quinte Conservation invoice • MTO review / traffic work • Hydrogeology / septic / servicing • Stormwater / grading / civil • Planning, architecture, engineering and legal • Peer review and agreement registration

$6,166  $2,242 deposit

Development charges

Parkland / conditions

County-wide DCs are calculated and payable at building permit. Exact nonresidential rate must be confirmed for the final use.

Consent conditions can include rezoning, well proof, drainage, entrance permits, road widening, agreements and parkland cash-in-lieu.

implication Municipal fees are not the main cost. Technical studies and physical upgrades dominate all three scenarios.

Fee strategy: apply concurrently where allowed, preserve pre-consultation credits, and establish the exact application list before retaining every consultant discipline.

Sources: County Consent / Rezoning Application  January 2026; Site Plan Control Application  January 2026; 2026 Development Charge rules. Fees change annually.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

21


I N C E N T I V E A N D F I N A N C I N G S T R AT E GY

The financing story is stronger than the grant story The property aligns with County agriculture and hospitality priorities, but no current property-specific redevelopment grant should be assumed.

Community Futures Up to $300,000 Local financing for eligible new, expanding or relocating businesses in Prince Edward / Lennox & Addington.

Canada Small Business Financing Potential term / line-of-credit support for an eligible non-farm hospitality, retail or service operator. Farming businesses are generally excluded.

Rural / agri-food programs Ontario rural-development and Sustainable CAP programs may support eligible business or farm-diversification activities when intakes are open. PROGRAM STATUS MATTERS

Small-grant program exists, but the 2026 intake is closed and award scale is not a core project-financing source. Municipal Community Grants Up to $15K cash and $2K in-kind, generally for eligible community / not-for-profit organizations - not a conventional private venue. Tourism Growth Program Federal intake closed February 13, 2026. Do not underwrite it as available funding. PEC Community Improvement Plan A County-wide CIP is a 2026 policy / budget watch item, not an adopted property incentive at the date of this report.

Sources: Community Futures Prince Edward Lennox & Addington; ISED Canada Small Business Financing Program; PEC grant pages; FedDev Ontario Tourism Growth Program; PEC 2025 2030 Economic Development Action Plan.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

22


BUILDING CODE AND TECHNICAL FEASIBILITY

The three strategies trigger fundamentally different design regimes The existing barn is an asset, but public assembly creates the largest technical jump in the report. Technical topic

Strategy A

Strategy B

Strategy C

Likely code path

Change of use / renovation

Assembly occupancy / Part 3 review

New commercial building + site servicing

Primary structure

Existing house + limited barn support

Existing barn + service upgrades

Future new building

Fire / life safety

Exits, alarms, fire separation, barrier-free

Occupant load, exits, alarms / sprinkler, fire access

Full code design and fire route

Private servicing

Commercial design flow

Peak event design flow

Hydrogeology / independent system

Parking / access

Moderate; MTO if intensified

High demand; event peaks

New / intensified road approval

Key studies

Building audit, septic, code, site plan

Structural, code/fire, septic, traffic, noise

Survey, planning, traffic, hydrogeo, civil

EXISTING-BUILDING PRIORITIES

PUBLIC-USE PRIORITIES

Retrieve 2014 permit and approved plans Measure barn and house floor areas Structural review of timber frame Existing septic / well records and testing Confirm legal occupancy and current use

Barrier-free route and washrooms Fire apparatus and emergency access Forward waste / delivery movement Occupant-load and egress analysis Noise, lighting and operating curfew

Preliminary only: this report is not a Building Code, Fire Code, structural, hydrogeological or septic analysis. The final code path can only be established after a defined use, measured drawings and consultant review.

Ontarioʼs 2024 Building Code has applied since January 1, 2025. Final requirements must be confirmed by the Chief Building Official and qualified consultants.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

23


APPRO VALS ST R AT EGY

Each strategy starts with a different decision - not the same application The County and road authority review a defined proposal. Selecting the preferred path is the first formal development decision.

Strategy A process

Strategy B process

Strategy C process

    

    

    

Permit and construction

Formal pre-consultation trigger One defined concept, parcel, access and operating program not a list of unrelated options. The County and MTO need enough detail to identify approvals and studies.

Time-risk control Do not complete full architectural design until the selected concept's zoning, road and servicing premise is supported in writing.

Timelines are 3rilo indicative allowances, not municipal commitments. Appeals, revisions, seasonal studies, servicing upgrades and market conditions may extend delivery.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

24


RISK MANAGEMENT

The key risks are controllable - but not equal across strategies The absence of a broad conservation constraint removes one common fatal flaw; legal use, servicing and access remain decisive.

2. Private servicing Risk: 2014 approval identifies an accessory private garage. Mitigation: retrieve permit file; obtain zoning / code opinion before public use.

Risk: existing well / septic may not support commercial or event flow. Mitigation: records, well test, design-flow and hydrogeological review.

3. Access / MTO

4. Agricultural policy

Risk: intensified Highway 33 use or new entrance may be constrained. Mitigation: one defined concept through HCMS pre-consultation.

Risk: commercial scale or land division undermines farm protection. Mitigation: compact farm-linked use, 2% test, strong planning rationale.

5. Venue operations

6. Construction cost

Risk: seasonality, neighbours, noise, staffing and bookings. Mitigation: curated scale, year-round uses, conservative event calendar.

Risk: unknown barn / house conditions and infrastructure

15% Mitigation: building audit, early trade pricing, 10% contingency.

Highest approval risk: Strategy C. Highest operating risk: Strategy B. Lowest overall development risk: Strategy A. None of the risks

Risk ratings are preliminary and based on currently available documents and correspondence.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

25


D E V E L O P M E N T S T R AT E G Y C O M PA R I S O N

Strategy B is the strongest overall development strategy The comparison separates planning fit, execution, capital, marketability, financial resilience and optionality.

Strategy

Planning

Capital

Marketability

Financial resilience

Overall

A. HC destination

Existing HC + site plan / code

$880K - $1.17M

Strong owner-user appeal

Moderate revenue hurdle

7.7 / 10

B. Agri-tourism

Strong policy fit; detailed approvals

$950K - $1.21M

Strongest premium story

Best operating upside

8.5 / 10

C. Frontage

Consent / ZBA / road risk

$355K - $525K entitlement

Strategic developer appeal

Value-uplift dependent

6.5 / 10

Best for owner-users Scenario 1 - clear commercial anchor, lower operational scale.

overall Scenario 2 - strongest policy, story and incremental return potential.

Best for land investors Scenario 3 - entitlement upside if the value threshold is proven first.

The scoring model measures execution quality, not maximum theoretical land value. Strategy B wins because it uses the barn and farm as intended assets rather than treating the acreage as generic development land.

Scores are 3rilo qualitative ratings based on the evidence and assumptions in this report; they are not appraisal or investment ratings.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

26


FINANCIAL COMPARISON

The strongest return comes from operating value not speculative lot creation Each strategy uses a different financial measure; the purpose is to identify the decision hurdle, not present false apples-toapples precision.

ST RAT EG Y A

ST R A T E G Y B

ST R A T E G Y C

Base operating cash flow on $438K gross revenue before financing and owner compensation.

Practical incremental value target before entitlement spend becomes compelling.

$235K - $312K Annual gross revenue needed to support an 8% operating return at a 30% margin.

$600K - $850K

Why Strategy B leads financially

Why Strategy C remains optional

The base operating case can produce a mid-teens return on incremental capital and creates a differentiated incomeproducing asset. The result still depends on bookings, pricing and operational excellence.

Entitlement spend produces no income and is only justified by a clear land-value uplift. A speculative approval exercise can destroy value if the market does not pay for the resulting parcel.

Financial conclusion: the market should reward authentic operating potential and flexible ownership more than untested maximum

Financial measures are illustrative, unlevered or hurdle-based, and exclude current property value, tax effects, HST, financing fees and appraisal conclusions.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

27


HIGHEST AND BEST USE CONCLUSION

Position the property for three buyer profiles - with one clear recommendation The report supports a premium operator story, a strong commercial fallback and a disciplined land-entitlement option. R I S K - A D J U S T E D O W N E R S H I P / L I S T I N G S T R AT E G Y

Agri-tourism / event barn destination Best use of the timber-frame barn Strongest alignment with farm and PEC identity Highest premium market positioning Most credible operating-value upside

Whole holding with consent-backed flexibility Preserve the complete legacy-estate story Explain potential separate HC and farm components Broaden owner-user, farmer and operator appeal Pursue consent only if value exceeds cost / delay

What is confirmed

What is supportable

What is not approved

HC / AG zoning, Agricultural designation, two legal descriptions / PINs, merger advice, limited Quinte feature, 2014 variance.

HC adaptive reuse, farm-linked diversified use, a consent investigation, and one frontage entitlement test.

Event venue, guest capacity, new lot, commercial barn use, new entrance, septic capacity or a final site plan.

The highest and best use is one answer: Strategy B. The best way to market and preserve optionality is a separate decision: present the whole holding while clearly explaining the potential for future consent and commercial frontage review.

Marketing principle: describe the concepts as preliminary potential supported by planning and development analysis, never as approved uses, guaranteed capacity or severance entitlement.

Highest and best use conclusion is based on legal permissibility, physical potential, preliminary financial reasonableness and comparative value creation.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

28


REALTOR M AR KET ING PAC K AG E

Development-focused listing language The wording below communicates verified value while preserving the buyerʼs due-diligence obligation. :

Rare Prince Edward County rural-commercial opportunity comprising approximately 68.2 acres with active agricultural land, a two-storey brick residence, substantial timber-frame barn and existing Highway Commercial zoning associated with the 13840 Loyalist Parkway frontage. Preliminary development review identifies credible potential for farm-based hospitality, agri-tourism, event, market, cafe / retail and related destination uses, subject to zoning, servicing, code, MTO and municipal approvals. Quinte Conservation identified only a limited southwest watercourse / wetland feature.

Unique opportunity to explore separately marketable commercial / residential and agricultural components. The property historically comprises a  0.513-acre HC house parcel and  67.714-acre AG farm parcel that have merged in title through common ownership. A new consent would be required before separate conveyance. The structure may appeal to buyers seeking a commercial owner-user property, active farm, barn / agri-tourism platform, or phased ownership strategy.

Development advisory identifies an agri-tourism / event-barn destination as the property's highest and best preliminary use, with a Highway Commercial rural-destination concept as the strongest secondary strategy and one commercial frontage entitlement as long-term option value. The package includes planning, agency, cost, operating-hurdle and risk analysis to support purchaser due diligence.

Agent talking points County-confirmed HC / AG zoning Barn is the central value driver Active agriculture and PEC tourism fit Limited conservation constraint Multiple buyer and exit profiles

disclaimer All uses, costs, capacities, lot concepts and timelines are preliminary. Purchasers must independently verify zoning, title, survey, servicing, access, code, approvals and financial assumptions. No development approval is represented.

Prepared as development advisory language for adaptation by the owner / listing brokerage. It is not a legal description, appraisal or representation of approval.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway

29


R E C O M M E N D E D N E X T S T E P S A N D B A S I S O F A N A LY S I S

Convert preliminary potential into decision-grade certainty A small amount of targeted due diligence will create more value than another generic concept image. Complete title and survey review Current PINs, reference plans, merger, easements, encroachments, exact boundaries and building locations.

Select one preferred operating concept

Retrieve permit and compliance records 2014 garage approval, building permits, legal use, open orders and septic / well information.

Prepare measured concept drawings OLS base plan plus architect / designer test fit - not speculative massing.

Hold County and MTO pre-consultation

Price and underwrite the selected strategy

Confirm application list, access, zoning, OFDU criteria, site plan, servicing and

studies.

Decision gate: advance Strategy B if a measured 100 - 150 guest test can satisfy code, septic, parking and access at the base operating case. Otherwise pursue Strategy A and preserve Scenario C as unspent option value. PRIMARY PROPERTY SOURCES

KEY ASSUMPTIONS , LIMITATIONS AND RELIANCE

-

Financial All costs are order-of-magnitude estimates expressed in 2026 Canadian dollars and are intended solely for preliminary feasibility analysis. Actual development costs will vary based on final design, consultant recommendations, municipal requirements, procurement methods, market conditions, inflation, financing terms, and construction timing. Land acquisition costs, HST, income tax, owner compensation, financing costs, legal fees, carrying costs, and unforeseen conditions have generally been excluded unless specifically noted. Revenue, operating, and value scenarios are illustrative planning tools only and are not forecasts or guarantees of financial performance. Planning & Regulatory This report is based on planning policies, zoning information, agency correspondence, and publicly available information current at the time of preparation. Municipal policies, zoning by-laws, Provincial legislation, conservation regulations, MTO requirements, Building Code requirements, and approval processes may change without notice. All development concepts remain subject to detailed design, formal municipal review, agency approvals, and any additional studies required through the Planning Act process. Technical No legal survey, title opinion, appraisal, environmental site assessment (ESA), geotechnical investigation, hydrogeological study, servicing analysis, traffic impact study, structural assessment, building condition assessment, septic capacity analysis, or detailed engineering review was completed as part of this report unless specifically stated. Existing site conditions, servicing capacity, environmental constraints, and structural conditions should be independently verified before proceeding. Reliance This report is intended solely as a preliminary development consulting document to assist with strategic decision-making. It should not be relied upon as legal, engineering, architectural, surveying, environmental, financial, tax, valuation, or construction advice. The Owner should retain appropriately qualified professionals, including a planner, architect, engineer, surveyor, lawyer, accountant, appraiser, environmental consultant, contractor, and lender, before making investment or development decisions. Liability The concepts, strategies, financial analyses, and opinions presented in this report represent professional planning judgments based on the information reasonably available at the time of preparation. No representation or warranty is made that any development concept will receive municipal approval, achieve projected financial performance, obtain financing, or be economically viable. 3rilo Inc., its officers, employees, and consultants assume no liability for decisions made by the Owner or any third party relying on this report beyond its intended preliminary feasibility purpose.

County planning correspondence - Angela Buonamici, MCIP, RPP, June 2026. Quinte Conservation correspondence / meeting - Samantha Carney, June 2026. MTO response - Allison Posthumus, June 29, 2026. Mitchell Korman legal correspondence - May 5, 2026. Committee of Adjustment A914, November 19, 2014. GeoWarehouse / legal descriptions; prior MLS package; Quinte GIS aerial. County Official Plan; Zoning By-law 140 2025; 2026 application forms and DC rules.

Prepared by 3rilo inc. The report integrates planning, development strategy, operating economics and marketing positioning to clarify opportunity - while preserving the distinction between preliminary potential and approved development rights.

3rilo Development Report™ | Complete • 13840 Loyalist Parkway