Summary of Survey Conducted on Commercial Development in the City of Fort Worth November 2022

Methodology and Respondents

Advertisement

• The online survey was conducted during the months of September and October 2022.

• Seventy-four (74) respondents completed the survey.

• Respondents are those in commercial development and related consulting (24%), construction (23%), design (31%) and other related commercial development-related professions (22%).

• Eighty-one percent (81%) of respondents have been involved in three or more development projects in Fort Worth during the most recent 24-months and 74% of respondents have been involved in five or more development projects during the most recent 24-months.

• In order to focus on the most informed respondents with wide perspectives, those respondents below were limited to those who were familiar with the entire development process , had completed 2 or more projects in Fort Worth and 1 or more projects outside of Fort Worth in the last 24 months.

o CLICK HERE FOR SURVEY DATA

NOTE: Filters discussed above are turned off by default and will not Reflect findings below

Findings

• The most challenging part of the development process in Fort Worth is infrastructure delivery (roads, water, sewer, storm drainage) 43%, followed by building development (permits, inspections) 23%.

o “There needs to be options to let competent private sector solutions meet this need. The legal trappings are awful. We just finished an IPRC Project Manual - Only took 9 months!.” o “X Team and Project Facilitators are great to work with, but the ancillary departments that they interact with are much slower in response time.” o “Every tenant is considered a change of use even if they are the same use and not remodeling. Landlords are asking me to "get out of having a C of O"

• The most challenging part of the entitlement portion of the development process in Fort Worth is platting 51.6%, followed by zoning/comprehensive plan 39.53% o “Studies being required to be approved before processing plats kills schedule. Although the state passed a house bill about this, many cities have found ways to allow simultaneous review.” o “ See Austin's Affordability Unlocked and Dallas's Density Bonus for examples. This will help reduce parking, excess paving, help reduce flooding, fights with neighborhoods NIMBY at Zoning and Council mtgs, and generally unclog the zoning system, all while helping the City with their affordable housing goal, for free.” o “Development Services is getting better, but other departments are getting worse.” o “The process is lengthy due to what appears to be zero risk policy but they are at least trying to reduce that length in some aspects.” o “No one has authority to make a decision.”

• The overall development process in Fort Worth is getting worse (52%), the same (24%) with some seeing the process getting better (24%).

• In terms of improving the current City development staff, 54% of respondents believe efforts should be focused on promoting a culture of problem solving (when looking at just commercial development and related consulting respondents that rises to 70% ) and 40% of respondents believe efforts should be focused on empowering staff to make decisions. Knowledgeability and Training was offered as a 3rd option and 0% chose this as an area to focus on. o “If lower staff could be presented with a logical solution to a permit comment, zoning comment, et c. then middle and upper mgmt can have more time to train and work on overall policies (like affordable housing bonuses, etc.) that would reduce the overall burden on a larger scale. But now they have to reso lve one problem on one development at a time.” o “General attitude is most developers are liars and burden of proof is to prove negatives constantly. This is because the few bad actors are caught red handed and get a slap on the wrist. No other cities oper ate this way.” o “Communication from Project Facilitator is the re, but there needs to be simpler systems for everyone at all levels to solve problems and prioritize as needed. ” o “Some improvements have happened, but the "I don't work for Randall" has been replaced with "I don't work for DJ " o “People from the city missed the meeting. Very insulting to the tenant for an expensive meeting ” o “Ann Nace was great to work with and helpful at all stages in coordinating permit approval. Greatly accelerates the permitting process and allows internal city staff to birddog other departments to obtain responses and clearances rather than the developers or their consultants ” o “Every tenant is treated as a Change of Use. Landlords are asking me to "get out of having a C of O " o “Mostly yes... There has been progress made but it still needs improvements and simplification. ” o “After weeks of emailing the Water Department for a response, I regularly feel terrible for having to email Chris Harder or DJ. It shouldn't be necessary but unfortunately is a regular oc currence. ” o “Need to continue to try and streamline plan review. Burleson is a good example.” o “Development Services is doing a pretty good job. The other departments are the same or getting worse.” o “I have seen Development Services trying to analyze its own processes which is great. ” o San Antonio -“They actually return calls and emails.” o Arlington and Frisco -“Tough but predictable. Decision makers are accessible, and they are final.”

• Respondents were asked if interdepartmental cooperation across all city departments involved in the development process has improved. 68% answered no, or no and getting worse. 26% said yes, but more improvement needed, and 5% said yes.

• When Asked if the X Team provided a good value 62% answered no.

• When Asked if Obtaining a Certificate of Occupancy was a positive experience 61% answered no.

• When asked which development-related department should receive the most improvement efforts, 43% of respondents said Water, 39% said Development Services, with the remainder mentioning various departments. When reviewing responses exclusively from development and related consulting professionals, 55% say Water, 9% say Development Services, 9% say TPW and 9% say Code/Health.

• When asked which development-related department has improved most in recent 24 -months, 66% said Development Services with the remainder mentioning various departments. When reviewing responses exclusively from development and related consulting professionals, 82% said Development Services.

• When asked if there was another city that the respondent felt did an exceptionally good job that Fort Worth staff could study to improve their development process, the #1 response was San Antonio, TX followed by a 3 way tie between Arlington, Frisco and Houston.

Conclusions

In wrapping up the survey, respondents were asked to identify one part of the development process in Fort Worth they would change and explain what and how they would do so. Most answers generally can be classified as

1) Expand the overwhelmingly positive trajectory within the Development Services Department to all development related departments.

2) Instill a culture of problem solving across all departments and down to the customer interface level as is the norm in most cities and

3) Resolve city’s internal process conflicts between departments and remove the expectation that the customer resolve them on their own: o “The culture needs to be changed - the majority of staff have a negative attitude. The good ones are over worked and the slackers continue to slack - there are no consequences or rewards.” o “Triple fees and use them to bonus the staff who get things done . ” o “Once you get upper managers, dept directors involved, CFW staff does genuinely help push items through/brainstorm about code exceptions permitting, IPRC/CFA, etc.” o “There is only one development process in the City of Fort Worth, and it doesn't work. Divide and conquer won't work because of the tremendous inter-relationship between departments. ” o “I would streamline the process. Instead of having to submit 10 different things to 10 different people, it would be nice to have a dedicated person to coordinate the project on th e city side.” o “Water, Fire, TPW and the other outside departments need to lead, follow or get out of the way. If they don't want to do their jobs related to development, move them under DJ or privatize those functions.”